| Firm | Filings | Most Recent |
|---|---|---|
| MICHAEL DERUVO & ASSOC. ARCHITECTS | 4 | 05/16/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| MICHAEL ROWE CONSULTING AND EXPEDIT | 4 | 03/21/2026 |
| PATRICIA L. GASS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AVID CONSTRUCTION INC | General Contractor | 2 | 03/21/2026 |
| PAT MCCANN P&H INC | Plumbing | 2 | 07/08/2026 |
| BERGER QUALITY ELEC'L CON | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 2 | 03/17/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | PAT MCCANN P&H INC | 05/03/2023 |
| DOB NOW | Plumbing | Signed-off | PAT MCCANN P&H INC | 02/14/2022 |
| DOB NOW | General Construction | Signed-off | AVID CONSTRUCTION INC | 01/03/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2024 | Permit Issued | BERGER QUALITY ELEC'L CON | — |
| 01/24/2022 | Complete | K-10 ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/24/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/10/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/13/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/18/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/18/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/26/2022 | Concrete - Cast-In-Place | anthony santoro | special |
| 04/26/2022 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 04/26/2022 | Structural Stability – Alterations of existing buildings | anthony santoro | special |
| 04/26/2022 | Subgrade Inspections | anthony santoro | special |
| 04/26/2022 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 01/11/2022 | Energy Code Compliance Inspections | MICHAEL DERUVO | progress |
| 01/11/2022 | Final | MICHAEL DERUVO | progress |
| 01/11/2022 | Fire-Resistance Rated Construction | MICHAEL DERUVO | progress |
| 01/11/2022 | Structural Wood Frame | MICHAEL DERUVO | progress |
| 01/11/2022 | Fenestration air leakage | MICHAEL DERUVO | energy_progress |
| 01/11/2022 | Fenestration and door U-factor and product ratings | MICHAEL DERUVO | energy_progress |
| 01/11/2022 | Fenestration areas | MICHAEL DERUVO | energy_progress |
| 01/11/2022 | Air barrier - visual inspection | MICHAEL DERUVO | energy_progress |
| 01/11/2022 | Insulation placement and R values | MICHAEL DERUVO | energy_progress |