| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK UNIVERSITY | 264 | 09/13/2026 |
| SKYLINE RSTORATION INC | 1 | 03/22/2026 |
| NYU | 2 | 03/21/2026 |
| HSE SYSTEM | 1 | 03/21/2026 |
| NYU OFFICE OF CONSTRUCTION MGMT | 17 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BR+A CONSULTING ENGINEERS | 4 | 08/05/2026 |
| HC PEC | 4 | 07/27/2026 |
| SEVERUD ASSOCIATES CONSULTING ENGIN | 3 | 06/29/2026 |
| BRAND ACCESS SOLUTIONS | 3 | 06/26/2026 |
| DAVIS BRODY BOND | 2 | 03/10/2026 |
| LEVIN ENGINEERING PLLC | 2 | 01/22/2026 |
| JAROS BAUM & BOLLES | 15 | 12/08/2025 |
| CARISIMA KOENIG | 1 | 12/04/2025 |
| MITCHELL / GIURGOLA ARCHITECTS | 6 | 10/16/2025 |
| THORNTON TOMASETTI | 3 | 11/18/2024 |
| JOSEPH J. ALIOTTA, AIA | 3 | 09/03/2024 |
| HOWARD I SHAPIRO & ASSOCIATES | 2 | 08/13/2024 |
| SUPERSTRUCTURES ENG. + ARCH. | 4 | 07/09/2024 |
| GUTH DECONZO CONSULTING ENGINEERS, | 1 | 06/26/2024 |
| ENVIRONETICS | 2 | 06/25/2024 |
| ABCO-PEERLESS ENGINEERING, P.C. | 1 | 05/20/2024 |
| TOHFAZ UDDIN PE PC | 4 | 07/05/2022 |
| 360 ENGINEERING P.C. | 4 | 04/04/2021 |
| BAILEYS ENGINEERING PC | 1 | 12/17/2018 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 11/15/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 12 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 10 | 03/21/2026 |
| JM ZONING, LLC. | 8 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 2 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 40 | 03/21/2026 |
| RENAISSANCE CODE CONSULTANTS | 6 | 03/21/2026 |
| HOWARD I SHAPIRO ASSOCIATES | 4 | 03/21/2026 |
| DIRECT ACCESS EXPEDITING, INC. | 2 | 03/21/2026 |
| NEW YORK UNIVERSITY | 5 | 03/21/2026 |
| ABCO-PEERLESS SPRINKLER | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GILBANE BUILDING COMPANY | General Contractor | 22 | 07/08/2026 |
| BROSNA CONSTRUCTION CORPO | General Contractor | 12 | 07/08/2026 |
| PJP INSTALLERS INC | General Contractor | 12 | 07/29/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 7 | 07/01/2026 |
| TURNER CONSTRUCTION COMPANY | General Contractor | 7 | 07/08/2026 |
| A & F FIRE PROTECTION CO | Fire Protection | 6 | 07/08/2026 |
| KING HOIST & SCAFFOLDING | General Contractor | 5 | 07/08/2026 |
| RAEL AUTOMATIC SPR.CO INC | Fire Protection | 4 | 07/08/2026 |
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 3 | 07/08/2026 |
| LEVIN ALEXANDER | Electrical | 3 | 03/21/2026 |
| YORK SCAFFOLD EQUIPMENT CORP. | General Contractor | 3 | 07/08/2026 |
| ALEXANDER LEVIN | Electrical | 3 | 03/21/2026 |
| JOHN O'KANE | Electrical | 2 | 03/21/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 2 | 03/21/2026 |
| ASPRO PLUMBING INC | Plumbing | 2 | 07/10/2026 |
| CARDOZA PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 2 | 07/08/2026 |
| CONDUCTOR ELECL SVCS INC | Electrical | 2 | 03/22/2026 |
| EDIFICE DESIGN INC | General Contractor | 2 | 03/21/2026 |
| CONTRACT & HOSPITALITY | General Contractor | 2 | 07/08/2026 |
| MAC FELDER INC | Plumbing | 1 | 07/08/2026 |
| ASANKOMAH, KOFI | Electrical | 1 | 03/21/2026 |
| BASIL, OMAR | Electrical | 1 | 03/21/2026 |
| BIGMAN BROS., INC. | Electrical | 1 | 03/22/2026 |
| BLACKSHEAR, VINCENT | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| OUTSOURCE SPECIAL INSPECT | 2827 | 6 | 06/29/2026 |
| RICHMOND TESTING LAB | 263 | 13 | 03/10/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 19 | 11/24/2025 |
| GUTH DECONZO CONSULTING E | 1210 | 1 | 06/26/2024 |
| SKYLINE ENGINEERING, PLLC | 267 | 1 | 04/27/2023 |
| TOHFAZ UDDIN P.E. | 2001 | 1 | 07/05/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | PJP INSTALLERS INC | 07/28/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | PJP INSTALLERS INC | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 07/08/2026 |
| DOB NOW | Structural | Permit Issued | GILBANE BUILDING COMPANY | 07/06/2026 |
| DOB NOW | Construction Fence | Permit Issued | SAFWAY ATLANTIC, LLC | 06/29/2026 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 06/25/2026 |
| DOB NOW | Structural | Permit Issued | GILBANE BUILDING COMPANY | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 06/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | GILBANE BUILDING COMPANY | 06/23/2026 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 06/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | TRINITY SOLAR LLC | 06/23/2026 |
| DOB NOW | Structural | Permit Issued | GILBANE BUILDING COMPANY | 06/23/2026 |
| DOB NOW | Sprinklers | Permit Issued | A & F FIRE PROTECTION CO | 06/12/2026 |
| DOB NOW | Standpipe | Permit Issued | A & F FIRE PROTECTION CO | 06/12/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | GILBANE BUILDING COMPANY | 06/04/2026 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 05/06/2026 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 03/09/2026 |
| DOB NOW | Structural | Permit Issued | GILBANE BUILDING COMPANY | 02/23/2026 |
| DOB NOW | Plumbing | Permit Issued | MAC FELDER INC | 02/06/2026 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 01/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | ADVANCED AUTO SPR.CO.,INC | 01/29/2026 |
| DOB NOW | Structural | Permit Issued | GILBANE BUILDING COMPANY | 01/09/2026 |
| DOB NOW | Standpipe | Permit Issued | ADVANCED AUTO SPR.CO.,INC | 12/24/2025 |
| DOB NOW | Sprinklers | Permit Issued | ADVANCED AUTO SPR.CO.,INC | 12/23/2025 |
| DOB NOW | Sprinklers | Signed-off | ADVANCED AUTO SPR.CO.,INC | 12/11/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | GILBANE BUILDING COMPANY | 10/14/2025 |
| DOB NOW | Plumbing | Permit Issued | MACCARONE PLUMBING INC | 10/14/2025 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 10/10/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 09/29/2025 |
| DOB NOW | Supported Scaffold | Signed-off | SAFWAY ATLANTIC, LLC | 09/29/2025 |
| DOB NOW | General Construction | Permit Issued | GILBANE BUILDING COMPANY | 09/24/2025 |
| DOB NOW | Structural | Permit Issued | GILBANE BUILDING COMPANY | 09/24/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 08/12/2025 |
| DOB NOW | Supported Scaffold | Signed-off | SAFWAY ATLANTIC, LLC | 08/08/2025 |
| DOB NOW | General Construction | Signed-off | TURNER CONSTRUCTION COMPANY | 10/04/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | TURNER CONSTRUCTION COMPANY | 10/01/2024 |
| DOB NOW | Sprinklers | Signed-off | RAEL AUTOMATIC SPR.CO INC | 09/30/2024 |
| DOB NOW | Sprinklers | Signed-off | RAEL AUTOMATIC SPR.CO INC | 09/27/2024 |
| DOB NOW | Mechanical Systems | Signed-off | GILBANE BUILDING COMPANY | 09/12/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/29/2026 | Permit Issued | GILBANE BUILDING COMPANY | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Multistack ASF030KCHB 134 tons · Condensing Unit ×2 Ventilation Titus ×45 International Enviro-Tec HDD 3,200 CFM · Fan Coil Indoor ×2 Nortek ×1 |
| 10/16/2025 | Permit Issued | GILBANE BUILDING COMPANY | Air Conditioning Systems, Heating Systems, Ventilation Systems | — |
| 10/07/2024 | Permit Issued | TURNER CONSTRUCTION COMPA | Heating and Air Conditioning Systems, Refrigeration Systems, Ventilation Systems | Heat / Cool Nortek ×4 Ventilation Mk Plastics AXIJET-VM 4450 120,000 CFM · Kitchen Exhaust ×12 — HLY10 1,000 CFM · Fan Coil Indoor ×4 Refrigeration — PCP-5000-540-AR-WP KCL-075 52,000 CFM · Refrigeration Unit ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | A & F FIRE PROTECTION CO | — |
| 01/22/2026 | Permit Issued | A & F FIRE PROTECTION CO | 11 heads |
| 11/24/2025 | Signed-off | A & F FIRE PROTECTION CO | 35 heads |
| 10/24/2025 | Permit Issued | A & F FIRE PROTECTION CO | 993 heads, 2 outlets |
| 11/01/2022 | Signed-off | THOMAS FAY | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | Permit Issued | MAC FELDER INC | Gas, Water/Sanitary |
| 06/29/2026 | Permit Issued | ASPRO PLUMBING, INC | Gas, Medical Gas, Storm, Water/Sanitary |
| 01/22/2026 | — | — | — |
| 11/24/2025 | — | — | — |
| 10/16/2025 | Permit Issued | MACCARONE PLUMBING INC | Medical Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/15/2026 | Permit Issued | HUGH O'KANE ELEC. CO. INC | General Wiring |
| 01/09/2026 | Permit Issued | HUGH O'KANE ELEC. CO. INC | — |
| 08/12/2025 | Complete | CORPORATE ELEC. GROUP INC | — |
| 07/15/2025 | Permit Issued | HUGH O'KANE ELEC. CO. INC | General Wiring |
| 11/25/2024 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 11/25/2024 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 02/21/2024 | Permit Issued | SCHLESINGER ELECT'L CONTR | General Wiring |
| 12/06/2023 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 12/06/2023 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 12/06/2023 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 08/21/2023 | Complete | NEAD ELECTRIC INC. | — |
| 01/20/2023 | Complete | MATROS AUTOMATED ELEC'L C | General Wiring |
| 12/08/2022 | Permit Issued | CONDUCTOR ELECL SVCS INC | — |
| 07/12/2022 | Complete | CONDUCTOR ELECL SVCS INC | — |
| 12/01/2020 | Complete | HUGH O'KANE ELEC. CO. INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Permit Issued | PJP INSTALLERS INC | 1 scope_items |
| 06/29/2026 | Permit Issued | ASPRO PLUMBING, INC | Steel |
| 03/10/2026 | Permit Issued | GILBANE BUILDING COMPANY | Steel, Concrete |
| 09/23/2025 | Permit Issued | GILBANE BUILDING COMPANY | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Permit Issued | PJP INSTALLERS INC | Sidewalk Shed |
| 07/27/2026 | Permit Issued | PJP INSTALLERS INC | Scaffold |
| 06/26/2026 | Permit Issued | SAFWAY ATLANTIC, LLC | Fence |
| 04/04/2021 | Permit Issued | PJP INSTALLERS INC | Sidewalk Shed |
| 04/04/2021 | Permit Issued | PJP INSTALLERS INC | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/15/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 07/02/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/17/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/17/2026 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 06/05/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/12/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/12/2026 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 09/12/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/10/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/08/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/07/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/21/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/21/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 10/14/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 08/22/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/18/2024 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 02/09/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/13/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/27/2026 | Air barrier - visual inspection | RICHARD LEMANSKY | energy_progress |
| 04/27/2026 | Wall Panels, Curtain Walls, and Veneers | RICHARD LEMANSKY | special |
| 04/27/2026 | Fire-Resistance Rated Construction | RICHARD LEMANSKY | progress |
| 04/27/2026 | Energy Code Compliance Inspections | RICHARD LEMANSKY | progress |
| 04/27/2026 | Fenestration areas | RICHARD LEMANSKY | energy_progress |
| 04/27/2026 | Fenestration air leakage | RICHARD LEMANSKY | energy_progress |
| 04/27/2026 | Insulation placement and R values | RICHARD LEMANSKY | energy_progress |
| 04/27/2026 | Exterior lighting power | RICHARD LEMANSKY | energy_progress |
| 04/27/2026 | Final | RICHARD LEMANSKY | progress |
| 04/27/2026 | Fenestration and door U-factor and product ratings | RICHARD LEMANSKY | energy_progress |
| 12/30/2025 | Sprinkler Systems | JONAR MADRIAGA | special |
| 11/19/2025 | Maintenance information | JONAR MADRIAGA | energy_progress |
| 11/19/2025 | HVAC-R and service water piping design and insulation | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | Lighting controls | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | Interior lighting power | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | Maintenance information | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | Metering | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | Duct leakage testing, insulation and design | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | HVAC-R and service water piping design and insulation | JONAR MADRIAGA | energy_progress |
| 11/14/2025 | Electrical motors and elevators | JONAR MADRIAGA | energy_progress |
| 11/07/2025 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 11/07/2025 | Post-installed Anchors | JONAR MADRIAGA | special |
| 11/07/2025 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 11/07/2025 | Standpipe Systems | JONAR MADRIAGA | special |
| 11/07/2025 | Sprinkler Systems | JONAR MADRIAGA | special |