| Owner | Filings | Most Recent |
|---|---|---|
| DYNASTY CONTRACTING LLC | 5 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/17/2020 | $1.1M | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| JOHN C. CHEN ARCHITECT,PLLC | 4 | 01/20/2022 |
| TIMES BUILDINGS ENGINEERING SERVICE | 1 | 11/17/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| MEIYUN CHEN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZR WHITESTONE INC | General Contractor | 10 | 07/08/2026 |
| DYNASTY CONTRACTING LLC | General Contractor | 3 | 03/21/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JOHN C CHEN ARCHITECT, PL | 2205 | 2 | 01/20/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | ZR WHITESTONE INC | 05/24/2023 |
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 12/01/2022 |
| DOB NOW | Construction Fence | Signed-off | ZR WHITESTONE INC | 02/14/2022 |
| DOB NOW | Construction Fence | Signed-off | ZR WHITESTONE INC | 12/31/2021 |
| DOB NOW | Construction Fence | Signed-off | ZR WHITESTONE INC | 06/15/2021 |
| DOB NOW | Construction Fence | Signed-off | DYNASTY CONTRACTING LLC | 11/20/2020 |
| BIS | — | ISSUED | ZR WHITESTONE INC | 06/28/2022 |
| BIS | — | ISSUED | ZR WHITESTONE INC | 06/21/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2023 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/25/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | JOHN CHEN | special |
| 01/25/2022 | Fire-Resistant Penetrations and Joints | JOHN CHEN | special |
| 01/25/2022 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | JOHN CHEN | special |
| 01/25/2022 | Energy Code Compliance Inspections | JOHN CHEN | progress |
| 01/25/2022 | HVAC-R and service water heating equipment | JOHN CHEN | energy_progress |
| 01/25/2022 | Metering | JOHN CHEN | energy_progress |
| 01/25/2022 | HVAC-R and service water heating system controls | JOHN CHEN | energy_progress |
| 01/25/2022 | HVAC-R and service water piping design and insulation | JOHN CHEN | energy_progress |
| 01/25/2022 | Maintenance information | JOHN CHEN | energy_progress |
| 01/20/2022 | Fire-Resistant Penetrations and Joints | JOHN CHEN | special |
| 01/20/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | JOHN CHEN | special |
| 01/20/2022 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | JOHN CHEN | special |
| 01/20/2022 | Energy Code Compliance Inspections | JOHN CHEN | progress |
| 01/20/2022 | HVAC-R and service water piping design and insulation | JOHN CHEN | energy_progress |
| 01/20/2022 | Maintenance information | JOHN CHEN | energy_progress |
| 01/20/2022 | HVAC-R and service water heating equipment | JOHN CHEN | energy_progress |
| 01/20/2022 | Metering | JOHN CHEN | energy_progress |
| 01/20/2022 | HVAC-R and service water heating system controls | JOHN CHEN | energy_progress |
| 11/03/2020 | Final | ZHUANG MIAO | progress |