← Back
Two family frame
60-16 56 DRIVE
QUEENS · BIN 4060424
💬 Discuss this project
1930Year Built
2Stories
B2Building Class
R4-1Zoning
3,150 sfGross Floor Area
2Units
Two family frame · 2,500 sf lot · 1.26 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 25p · 2 filings · 9 docs
Floor 15p · 2 filings · 9 docs
Cellar5p · 2 filings · 9 docs
1 job · most recent 10/19/2021
General Wiring
FiledStatusContractorScope
10/19/2021Permit IssuedSUPREME ELECTRIC CORPGeneral Wiring
Building Lifecycle
All (5)Filed (2)Permit Issued (3)
06/16/2023
Permit issued — Plumbing
Q00573536-I1-PL
08/30/2021
Permit issued — General Construction
Q00573529-I1-GC
08/30/2021
Permit issued — Plumbing
Q00573536-I1-PL
08/23/2021
Filed — Alteration
PROPOSE PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
Q00573536-I1
08/23/2021
Filed — Alteration
PROPOSE INTERIOR RENOVATION OF EXISTING 2 FAMILY BUILDING WITH NEW PARTITION WORK AND FINISH WORK AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00573529-I1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GALLAHUE607/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/29/2021$775K—— → 2016 RE GROUP LLC$246/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STREET CONSULTING ENGINEERING, P. .208/23/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MODERN BUILDING CONSULTANT203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
VILLAGE P & H NY INCPlumbing207/08/2026
CONSTRUCTION XPERT INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
STREET CONSULTING ENGINEE4259208/23/2021
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedVILLAGE P & H NY INC06/16/2023
DOB NOWGeneral ConstructionPermit IssuedCONSTRUCTION XPERT INC08/30/2021
DOB NOWPlumbingPermit IssuedVILLAGE P & H NY INC08/30/2021
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
08/02/2023Pass-Final CND-Occupancy InspectionPassView ↗
05/26/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
04/13/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/29/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
11/30/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/30/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
08/18/2021Fire-Resistant Penetrations and JointsErik Streetspecial
08/18/2021Energy Code Compliance InspectionsErik Streetprogress
08/18/2021HVAC-R and service water piping design and insulationErik Streetenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/27/2026Q00573529-I1Request digital key ↗
08/27/2026Q00573536-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q00573536-I1Open ↗
08/13/2026Q00573529-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/22/2026Q00573536-I1Open ↗
08/22/2026Q00573536-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026Q00573536-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q00573529-I1Open ↗
08/13/2026Q00573536-I1Open ↗