← Back
Three families
60-22 82 STREET
QUEENS · Middle Village · BIN 4530150
💬 Discuss this project
2004Year Built
3Stories
C0Building Class
R4AZoning
3,241 sfGross Floor Area
3Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Three families · 2,966 sf lot · 1.09 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingGeneral
Floor 12p · 2 filings · 6 docs
Cellar1p · 2 filings · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
METROSE GARDENS II103/22/2026
MELROSE GARDENS603/21/2026
FABIAN CONSTRUCTION403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CO.DE CONSULTING AND DESIGN, INC.212/10/2021
Building Lifecycle
All (9)Filed (2)Violation (2)Objection (1)Special Inspection (4)
12/14/2021
Objection raised — Zoning
12/10/2021
Filed — Alteration
Proposed toilet at the cellar level, supplementary to use by the owner or by personnel for maintenance, repair or cleaning the public space (as per Sec. 80. of the MDL). Installation of new partitions and plumbing fixtures.
Q00643816-I1
12/09/2021
Filed — Alteration
Q00643450-I1
12/09/2021
Special inspection requirement — Energy Code Compliance Inspections
Wieslawa Jasiulewicz Majran
12/09/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Wieslawa Jasiulewicz Majran
12/09/2021
Special inspection requirement — Energy Code Compliance Inspections
Wieslawa Jasiulewicz Majran
12/07/2021
Special inspection requirement — Final
Wieslawa Jasiulewicz Majran
11/04/2019
Violation issued (HPD, closed)
I
08/30/2004
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISEQISSUEDFABIAN CONSTR CO.,INC11/01/2004
BIS—ISSUEDFABIAN CONSTR CO.,INC11/01/2004
BISPLISSUEDR.V.S. PLBG & HTG, INC.08/30/2004
BISEQISSUEDFABIAN CONSTR CO.,INC06/07/2004
BIS—ISSUEDFABIAN CONSTR CO.,INC06/07/2004
BIS—ISSUEDALWAYS FAST INC04/01/2004
BIS—ISSUEDALWAYS FAST INC04/01/2004
BISEQISSUEDALWAYS FAST INC04/01/2004
1 project · most recent 12/10/2021
Water/Sanitary
FiledStatusContractorScope
12/10/2021——Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
12/09/2021Energy Code Compliance InspectionsWieslawa Jasiulewicz Majranprogress
12/09/2021HVAC-R and service water piping design and insulationWieslawa Jasiulewicz Majranenergy_progress
12/09/2021Energy Code Compliance InspectionsWieslawa Jasiulewicz Majranprogress
12/07/2021FinalWieslawa Jasiulewicz Majranprogress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/26/2026Q00643450-I1Request digital key ↗
08/15/2026Q00643816-I1Request digital key ↗
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
12/19/2014421060452Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/26/2026Q00643816-I1Open ↗
08/13/2026Q00643450-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/02/2026Q00643450-I1Open ↗
08/26/2026Q00643816-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
12/19/2014421060452Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
12/19/2014421060452Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
12/19/2014421060452Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
12/19/2014421060452Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/19/2014421060452Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
12/19/2014421060452Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
12/19/2014421060452Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
12/19/2014421060452Open ↗