| Firm | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI | 3 | 08/03/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI, RA | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CAVAGNARO CONTRACTING LLC | General Contractor | 2 | 07/04/2026 |
| PREMIER PL,HTG & MECH INC | Plumbing | 1 | 08/06/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JAMES V MORRI, RA | 1042 | 1 | 02/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | SIGNATURE AUDIO DESIGN LL | 08/05/2026 |
| DOB NOW | General Construction | Permit Issued | CAVAGNARO CONTRACTING LLC | 07/02/2026 |
| DOB NOW | Construction Fence | Permit Issued | CAVAGNARO CONTRACTING LLC | 06/23/2026 |
| BIS | — | ISSUED | A.C KINGSLEY CONSTRUCTION INC. | 12/14/1993 |
| BIS | — | ISSUED | TOTH EXCAVATING INC. | 03/23/1993 |
| BIS | EQ | ISSUED | TOTH EXCAVATING INC. | 03/22/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2026 | Permit Issued | FICHERA ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/22/2026 | Permit Issued | CAVAGNARO CONTRACTING LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/22/2026 | Fire-Resistant Penetrations and Joints | James Morri | special |
| 01/22/2026 | Structural Stability – Alterations of existing buildings | James Morri | special |
| 01/22/2026 | Energy Code Compliance Inspections | James Morri | progress |
| 01/22/2026 | Fire-Resistance Rated Construction | James Morri | progress |
| 01/22/2026 | Preliminary | James Morri | progress |
| 01/22/2026 | Structural Wood Frame | James Morri | progress |
| 01/22/2026 | Final | James Morri | progress |
| 01/22/2026 | Lighting controls | James Morri | energy_progress |
| 01/22/2026 | Air barrier — testing | anthony santoro | energy_progress |
| 01/22/2026 | HVAC-R and service water heating system controls | James Morri | energy_progress |
| 01/22/2026 | Lighting in dwelling units | James Morri | energy_progress |
| 01/22/2026 | Air barrier - visual inspection | James Morri | energy_progress |
| 01/22/2026 | Maintenance information | James Morri | energy_progress |
| 01/22/2026 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 01/22/2026 | HVAC-R and service water piping design and insulation | James Morri | energy_progress |
| 01/22/2026 | Fenestration air leakage | James Morri | energy_progress |
| 01/22/2026 | Metering | James Morri | energy_progress |
| 01/22/2026 | Fenestration areas | James Morri | energy_progress |
| 01/22/2026 | Insulation placement and R values | James Morri | energy_progress |
| 01/22/2026 | Permanent certificate | James Morri | energy_progress |
| 01/22/2026 | HVAC-R and service water heating equipment | James Morri | energy_progress |