| Owner | Filings | Most Recent |
|---|---|---|
| Elysee Hotel Hospitality | 25 | 07/08/2026 |
| 60 East 54 | 10 | 03/21/2026 |
| East 54 Hotel Leasehold | 4 | 04/09/2026 |
| Shuwa | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/01/2016 | $55.0M | — | — → — | $840/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Robert Ettinger, P.E | 11 | 10/07/2026 |
| Bitopi Consultants | 3 | 08/06/2026 |
| Daniel Goldner Architects | 4 | 07/30/2026 |
| Ashraf | 3 | 07/14/2026 |
| Ospino Engineering | 2 | 03/04/2026 |
| Pramodray Shah, P.E | 3 | 02/19/2026 |
| Black Sheep Engineering Group | 2 | 10/09/2025 |
| Gace | 1 | 03/18/2025 |
| Tohfaz Uddin PE | 1 | 11/17/2022 |
| FL&M Engineering Design & Inspection | 1 | 05/24/2022 |
| All City Engineering | 2 | 05/13/2022 |
| Zachary Gidich Architecture and Des | 1 | 04/08/2022 |
| KZ Engineering | 2 | 12/17/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM Zoning | 24 | 03/21/2026 |
| Synergy Building Consultants | 3 | 03/21/2026 |
| Hierarch-E | 4 | 03/21/2026 |
| KD Designs | 5 | 03/21/2026 |
| W J Professional Expediting Company | 2 | 03/21/2026 |
| PDG Building Consultants | 3 | 03/21/2026 |
| Casa Group | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Arsenal Scaffold | Scaffold | 9 | 08/30/2026 |
| CS Bridge | Scaffold | 6 | 07/08/2026 |
| MJM Construction Associates | General Contractor | 6 | 07/08/2026 |
| F.S. Site | Fire Protection | 4 | 07/08/2026 |
| Traditional Waterproofing | specialty_contractor | 3 | 07/08/2026 |
| F.S. Site | Plumbing | 2 | 07/08/2026 |
| MJM Associates Construction | General Contractor | 2 | 07/08/2026 |
| Northeast Specialist Group | General Contractor | 1 | 04/09/2026 |
| Genco Lee Renovation | General Contractor | 1 | 07/08/2026 |
| Ebro Dique Group | Scaffold | 1 | 04/09/2026 |
| AAA Total Plumbing | Plumbing | 1 | 07/08/2026 |
| Napstar Electric | Electrical | 1 | 03/21/2026 |
| Solas Electrical | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Shahrish Shuvo Engineering | 8524 | 13 | 10/07/2026 |
| Tohfaz Uddin P.E | 2001 | 1 | 11/17/2022 |
| Geiger Engineering | 689 | 1 | 05/24/2022 |
| All City Engineering | 7115 | 2 | 05/13/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Arsenal Scaffold | 08/27/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Arsenal Scaffold | 08/11/2026 |
| DOB NOW | Construction Fence | Permit Issued | Arsenal Scaffold | 07/27/2026 |
| DOB NOW | General Construction | Permit Issued | MJM Construction Associates | 04/16/2026 |
| DOB NOW | Construction Fence | Permit Issued | Arsenal Scaffold | 03/17/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | Alps Contractor | 03/13/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Ebro Dique Group | 03/04/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Arsenal Scaffold | 02/26/2026 |
| DOB NOW | Structural | Permit Issued | MJM Construction Associates | 02/18/2026 |
| DOB NOW | Plumbing | Permit Issued | Alan J Brutosky PLBR Cont | 01/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | MJM Construction Associates | 01/07/2026 |
| DOB NOW | Standpipe | Permit Issued | Alan J. Brutosky Plumbing Con | 11/18/2025 |
| DOB NOW | Sprinklers | Permit Issued | Alan J. Brutosky Plumbing Con | 11/18/2025 |
| DOB NOW | General Construction | Permit Issued | MJM Construction Associates | 11/14/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MJM Construction Associates | 10/21/2025 |
| DOB NOW | General Construction | Signed-off | MJM Construction Associates | 10/20/2025 |
| DOB NOW | Standpipe | Permit Issued | Alan J. Brutosky Plumbing Con | 10/14/2025 |
| DOB NOW | General Construction | Signed-off | Northeast Specialist Group | 09/16/2025 |
| DOB NOW | Sprinklers | Permit Issued | Alan J. Brutosky Plumbing Con | 09/08/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Arsenal Scaffold | 09/04/2025 |
| DOB NOW | Plumbing | Permit Issued | Alan J Brutosky PLBR Cont | 08/20/2025 |
| DOB NOW | General Construction | Signed-off | MJM Associates Construction | 08/15/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MJM Associates Construction | 08/15/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | Arsenal Scaffold | 08/13/2025 |
| DOB NOW | Construction Fence | Permit Issued | Arsenal Scaffold | 08/13/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CS Bridge | 12/14/2023 |
| DOB NOW | General Construction | Signed-off | Traditional Waterproofing | 10/26/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CS Bridge | 12/14/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CS Bridge | 11/18/2022 |
| DOB NOW | General Construction | Signed-off | Traditional Waterproofing | 10/28/2022 |
| DOB NOW | Plumbing | Signed-off | AAA Total Plumbing | 05/05/2022 |
| DOB NOW | General Construction | Signed-off | Genco Lee Renovation | 04/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CS Bridge | 12/15/2021 |
| BIS | — | ISSUED | Tuc-Men Contracting | 02/02/2017 |
| BIS | — | ISSUED | Tuc-Men Contracting | 02/01/2017 |
| BIS | PL | ISSUED | J. Caiazzo Plumbing & Heating | 05/06/2015 |
| BIS | — | ISSUED | Tuc-Men Contracting | 01/14/2015 |
| BIS | OT | ISSUED | Urban D.C | 10/27/2011 |
| BIS | EQ | ISSUED | Everest Scaffolding | 08/15/2011 |
| BIS | EQ | ISSUED | Everest Scaffolding | 07/27/2011 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/07/2026 | Permit Issued | MJM Construction Associates | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2026 | Permit Issued | F.S. Site | Sprinkler System |
| 09/22/2025 | Permit Issued | F.S. Site | Sprinkler System |
| 09/19/2025 | Permit Issued | F.S. Site | 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2026 | Permit Issued | F.S. Site | Gas, Storm, Water/Sanitary |
| 09/22/2025 | Permit Issued | F.S. Site | Water/Sanitary |
| 09/19/2025 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/04/2026 | Permit Issued | Denali Electric | — |
| 12/16/2025 | Permit Issued | Napstar Electric | General Wiring |
| 09/25/2025 | Permit Issued | Solas Electrical | — |
| 09/08/2025 | Permit Issued | Solas Electrical | — |
| 08/16/2025 | Permit Issued | Napstar Electric | — |
| 06/07/2022 | Permit Issued | SNB Electrical Contng | General Wiring |
| 12/13/2021 | Permit Issued | Nash Electric Services | — |
| 06/17/2019 | Permit Issued | Nee Electrical | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2026 | Permit Issued | MJM Construction Associates | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2026 | Permit Issued | MJM Construction Associates | Scaffold |
| 07/14/2026 | Permit Issued | Arsenal Scaffold | Fence, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2026 | Permit Issued | MJM Construction Associates | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/23/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/16/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/06/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/21/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 11/21/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 09/03/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/09/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/02/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/27/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/15/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/29/2026 | Mechanical Systems | Shahrish Shuvo | special |
| 09/29/2026 | Final | Shahrish Shuvo | progress |
| 09/29/2026 | Energy Code Compliance Inspections | Shahrish Shuvo | progress |
| 09/29/2026 | Post-installed Anchors | Shahrish Shuvo | special |
| 09/29/2026 | Sprinkler Systems | Shahrish Shuvo | special |
| 09/29/2026 | Standpipe Systems | Shahrish Shuvo | special |
| 09/29/2026 | Heating Systems | Shahrish Shuvo | special |
| 09/29/2026 | Maintenance information | Shahrish Shuvo | energy_progress |
| 09/29/2026 | HVAC-R and service water heating equipment | Shahrish Shuvo | energy_progress |
| 09/29/2026 | HVAC-R and service water heating system controls | Shahrish Shuvo | energy_progress |
| 09/29/2026 | HVAC-R and service water piping design and insulation | Shahrish Shuvo | energy_progress |
| 09/28/2026 | HVAC-R and service water piping design and insulation | Shahrish Shuvo | energy_progress |
| 09/28/2026 | HVAC-R and service water heating equipment | Shahrish Shuvo | energy_progress |
| 09/28/2026 | Maintenance information | Shahrish Shuvo | energy_progress |
| 09/28/2026 | HVAC-R and service water heating system controls | Shahrish Shuvo | energy_progress |
| 09/28/2026 | Energy Code Compliance Inspections | Shahrish Shuvo | progress |
| 09/28/2026 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 06/25/2026 | Fenestration air leakage | Shahrish Shuvo | energy_progress |
| 06/25/2026 | Chimneys and vents | Shahrish Shuvo | special |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 06/25/2026 | Mastic and Intumescent Fire-resistant Coatings | Shahrish Shuvo | special |
| 06/25/2026 | Sprayed fire-resistant materials | Shahrish Shuvo | special |
| 06/25/2026 | Energy Code Compliance Inspections | Shahrish Shuvo | progress |
| 06/25/2026 | Fire-Resistance Rated Construction | Shahrish Shuvo | progress |
| 06/25/2026 | Air barrier - visual inspection | Shahrish Shuvo | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Hotel Wolfgang Joop(elysee) | Hotel / Lodging | Entire building | Project M01262081 Project M01298523 Project M01264637 Project M01280277 Project M01261741 Project M01196092 Project M08038650 Project M00710321 Project M00713407 Project M00646065 Project M01138985 |