| Owner | Filings | Most Recent |
|---|---|---|
| NICOLOSI BROS. INC. | 7 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| C&P DESIGN CONSULTANTS | 3 | 01/28/2022 |
| WILLIAM MONTAGUE ENGINEER | 2 | 09/28/2021 |
| CHRIS PONISI, ARCHITECT | 1 | 06/29/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDIA CONSULTING | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NICOLOSI BROS INC | General Contractor | 9 | 07/08/2026 |
| FINE MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SRA PLANNING & EXPEDITING | 5677 | 2 | 09/28/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | NICOLOSI BROS INC | 10/01/2021 |
| DOB NOW | Structural | Signed-off | NICOLOSI BROS INC | 10/01/2021 |
| DOB NOW | Construction Fence | Signed-off | NICOLOSI BROS INC | 08/24/2021 |
| DOB NOW | General Construction | Signed-off | NICOLOSI BROS INC | 07/23/2021 |
| DOB NOW | Plumbing | Signed-off | FINE MECHANICAL CORP | 05/11/2021 |
| DOB NOW | Construction Fence | Signed-off | NICOLOSI BROS INC | 04/29/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/09/2021 | Complete | RIDGE ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/25/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/25/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/20/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/14/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/20/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/20/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/22/2021 | Mechanical Systems | WILLIAM MONTAGUE | special |
| 09/22/2021 | Final | WILLIAM MONTAGUE | progress |