← Back
General warehouse
60 WEST STREET
BROOKLYN · BIN 3337609
💬 Discuss this project
1912Year Built
7Stories
E1Building Class
M1-2/R6AZoning
78,000 sfGross Floor Area
10Units
LL97 Covered10 Open Violations 2 unresolved · 8 paperwork only ▸FDNY Report ↗
General warehouse · Owner of record: 72 WEST LLC · 21,875 sf lot · 3.57 FAR built · Flood zone X500
Locations of Work
ArchitecturePlumbing
Roof1p · 2 filings · 12 docs
Floor 11p · 2 filings · 12 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
72 WEST503/22/2026
72 WEST ST103/22/2026
PLAZA TERMINAL HOLDIN103/22/2026
73 WEST103/22/2026
PEARL REALTY MANAGEMENT103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SCHERER DESIGN GROUP303/18/2026
STRUCTURAL ENGINEERING TECHNOLOGIES112/13/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CCM CONSULTING GROUP, INC.203/21/2026
PINE RE CONSULTING103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DIGITAL CONSTRUCTION TECHGeneral Contractor507/08/2026
L.L.G. PLBG & HTG INCPlumbing307/08/2026
GUTTMAN JOSHUAElectrical103/21/2026
JOSHUA GUTTMANElectrical103/21/2026
MASTANDREA, CElectrical103/21/2026
TORRES, OSCARElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SCHERER DESIGN GROUP7921303/18/2026
Building Lifecycle
All (28)Filed (4)Permit Issued (6)Signed Off (2)Violation (10)Inspection (2)Objection (2)Special Inspection (2)
06/22/2026
Signed off — Alteration
B08052383-I1
06/18/2026
Signed off — Alteration
Installation of gas meter and gas piping as per plan. Additional gas piping filed under separate application B00860015, generator filed under separate application B00860005, both on adjacent BIN. No change to occupancy, use, or egress.
B08052415-I1
04/23/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
COLLEEN CONNOLLY
03/18/2026
Filed — Alteration
Installation of gas meter and gas piping as per plan. Additional gas piping filed under separate application B00860015, generator filed under separate application B00860005, both on adjacent BIN. No change to occupancy, use, or egress.
B08052415-P2
01/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
COLLEEN CONNOLLY
01/09/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/05/2026
Permit issued — Plumbing
B08052415-I1-PL
06/09/2025
Permit issued — Antenna
B08052383-I1-AN
12/13/2024
Filed — Alteration
B01148333-I1
08/08/2024
Permit issued — Plumbing
B08052415-I1-PL
07/01/2024
Permit issued — Antenna
B08052383-I1-AN
07/18/2023
Permit issued — Plumbing
B08052415-I1-PL
06/12/2023
Permit issued — Antenna
B08052383-I1-AN
06/01/2023
Objection resolved — Addressed
05/31/2023
Objection raised — Admin
05/25/2023
Filed — Alteration
B08052383-I1
05/25/2023
Filed — Alteration
Installation of gas meter and gas piping as per plan. Additional gas piping filed under separate application B00860015, generator filed under separate application B00860005, both on adjacent BIN. No change to occupancy, use, or egress.
B08052415-I1
05/19/2012
Violation issued (ECB, open)
Construction
03/09/2011
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/10/2010
Violation issued (ECB, open)
Construction
04/13/2005
Violation issued (ECB, open)
Construction
04/11/2005
Violation issued (ECB, open)
Construction
01/18/2005
Violation issued (ECB, closed)
Construction
11/18/2004
Violation issued (ECB, open)
Construction
12/18/1998
Violation issued (ECB, closed)
Construction
02/13/1998
Violation issued (ECB, closed)
Construction
12/29/1997
Violation issued (DOB, open)
VW-VIOLATION WORK WITHOUT PERMIT - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offL.L.G. PLBG & HTG INC01/05/2026
DOB NOWAntennaSigned-offDIGITAL CONSTRUCTION TECH06/09/2025
DOB NOWPlumbingSigned-offL.L.G. PLBG & HTG INC08/08/2024
DOB NOWAntennaSigned-offDIGITAL CONSTRUCTION TECH07/01/2024
DOB NOWPlumbingSigned-offL.L.G. PLBG & HTG INC07/18/2023
DOB NOWAntennaSigned-offDIGITAL CONSTRUCTION TECH06/12/2023
BISPLISSUEDNEW YORK STANDARD MECH CORP04/05/2002
1 project · most recent 03/18/2026
Gas
FiledStatusContractorScope
03/18/2026Signed-offL.L.G. PLBG & HTG INCGas
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
04/23/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/09/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
03/30/2026Fire-Resistant Penetrations and JointsCOLLEEN CONNOLLYspecial
01/14/2026Fire-Resistant Penetrations and JointsCOLLEEN CONNOLLYspecial
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026B08052415-I1Request digital key ↗
08/27/2026B08052415-P2Request digital key ↗
08/27/2026B08052383-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026B08052415-I1Open ↗
08/27/2026B08052383-I1Open ↗
08/23/2026B01148333-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026B08052415-P2Open ↗
08/23/2026B08052415-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/27/2026B08052415-I1Open ↗
08/27/2026B08052383-I1Open ↗
08/13/2026B08052415-P2Open ↗