FILING HEREWITH INSTALLATION OF NEW SPRINKLER/STANDPIPE SYSTEM IN CONJUNCTION WITH NEW BUILDING APPLICATION # 121206685 AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
29 documents · 2 drawing sheets
FILING HEREWITH STRUCTURAL WORK IN CONJUNCTION WITH NB APPLICATION #121206685.
On file for this project
17 documents · 3 drawing sheets
INSTALLATION AND USE OF MINI CRANE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 8 filings on this floor.
RoofMcDonald's USA2p · 4 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Use of window washing equipment as per plans filed herewith.
On file for this project
3 documents
Hereby filing plans for the installation of Mechanical units for a proposed McDonalds restaurant. Filed in conjunction with New Building application number 121206685. No change to use, egress, or occupancy under this application.
On file for this project
20 documents
INSTALLATION OF TEMPORARY ROOF PROTECTION AT ADJACENT PROPERTY (31 TIEMANN PLACE) DURING NB CONSTRUCTION, FILED SEP. TEMPORARY ROOF PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
BulkheadMechanical system installation3p · 1 filing · 3 docs
MechanicalStructuralOther
FILING HEREWITH INSTALLATION OF THE BOILER IN CONJUNCTION WITH NEW BUILDING AS PER PLANS.
On file for this project
21 documents · 3 drawing sheets
Floor 36Window washing equipment use1 filing · 3 docs
ElectricalStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of window washing equipment as per plans filed herewith.
On file for this project
3 documents
Floor 35
Floor 34Columbia University in the City of New York2p · 2 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
TEMPORARY HOIST RUN-BACK STRUCTURE DURING NEW BLDG CONSTRUCTION, FILED SEPARATELY. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. HOIST & ELEVATOR APPL SUBMITTED SEP
On file for this project
2 documents · 1 drawing sheet
FILING HEREWITH INSTALLATION OF THE BOILER IN CONJUNCTION WITH NEW BUILDING AS PER PLANS.
On file for this project
21 documents · 1 drawing sheet
Floor 33
Floor 32
Floor 31
Floor 30
Floor 29Window washing equipment use1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Use of window washing equipment as per plans filed herewith.
On file for this project
3 documents
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20Window washing equipment use1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Use of window washing equipment as per plans filed herewith.
On file for this project
3 documents
Floor 19Columbia University in the City of New York4p · 1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
FILING HEREWITH INSTALLATION OF FUEL STORAGE FOR GENERATOR IN CONJUNCTION WITH NEW BUILDING AS PER PLANS.
On file for this project
11 documents · 4 drawing sheets
Floor 18
Floor 17
Floor 16Window washing equipment use1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Use of window washing equipment as per plans filed herewith.
On file for this project
3 documents
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1McDonald's USA4p · 8 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Filing herewith plans for the modification of existing sprinkler system. Application filed in conjunction with New Building application number 121206685. No change to use, egress, or occupancy.
On file for this project
7 documents · 2 drawing sheets
Minor structural work filed for proposed McDonalds restaurant. No change to use, egress, or occupancy.
On file for this project
5 documents
Hereby filing plans for the installation of Mechanical units for a proposed McDonalds restaurant. Filed in conjunction with New Building application number 121206685. No change to use, egress, or occupancy under this application.
On file for this project
20 documents
Latest 3 of 8 filings on this floor.
CellarMcDonald's USA, Columbia University in the City of New York5p · 3 filings
Fire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · Mechanical Systems · Plumbing · Sprinklers · Standpipe
Plumbing modification and associated piping as per plans filed herewith. Application filed in conjunction with New Building application number 121206685. No change to use, egress, or occupancy.
On file for this project
6 documents
FILING HEREWITH INSTALLATION OF FUEL STORAGE FOR GENERATOR IN CONJUNCTION WITH NEW BUILDING AS PER PLANS.
On file for this project
11 documents · 5 drawing sheets
FILING HEREWITH INSTALLATION OF THE BOILER IN CONJUNCTION WITH NEW BUILDING AS PER PLANS.
On file for this project
21 documents · 1 drawing sheet
Site & exteriorMcDonald's USA, Columbia University in the City of New York8 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Earth Work · Protection and Mechanical Methods · Sidewalk Shed · Sign
Filing plans herewith for the proposed installation of illuminated non-flashing signage. No change to use, egress, or occupancy.
On file for this project
5 documents · 1 drawing sheet
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING NB CONSTRUCTION, FILED SEPARATELY. SIDEWALK SHED SHALL COMPLY WITH CH 33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. DOT PERMITS BY OTHERS FOR SHED INSTALLED ON ROADWAY.
On file for this project
13 documents · 12 drawing sheets
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AT NORTH WEST ESCALATOR DURING NEW BLDG CONSTRUCTION, FILED SEP. TEMPORARY OVERHEAD PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents · 8 drawing sheets