← Back
City residence, one family
603 5 STREET
BROOKLYN · BIN 3025561
💬 Discuss this project
1908Year Built
3Stories
A4Building Class
R7BZoning
2,955 sfGross Floor Area
1Units
City residence, one family · 1,700 sf lot · 1.74 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Roof1p · 1 filing · 13 docs
Floor 22p · 2 filings · 20 docs
Floor 1
Cellar2p · 2 filings · 20 docs
3 jobs · most recent 11/09/2022
General Wiring
FiledStatusContractorScope
11/09/2022CompleteKRISCORP ELECL CONTNG INCGeneral Wiring
12/14/2021CompleteKRISCORP ELECL CONTNG INC1 meters, 1 new_meters
03/08/2018CompleteBROOKYLN SOLARWORKS, LLC—
Building Lifecycle
All (43)Filed (8)Permit Issued (5)Signed Off (3)Inspection (3)Objection (2)Special Inspection (22)
01/26/2023
Signed off — Alteration
INSTALLATION OF PLUMBING FIXTURES.
B00639662-I1
01/17/2023
Signed off — Alteration
INSTALLATION OF 2ND FLOOR ROOF TERRACE AND HEAT PUMPS AT THE BUILDING BACK. INSTALLATION OF A/C BLOWER AND DUCT WORK AT BUILDING INSIDE. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00661839-I1
01/10/2023
Permit issued — General Construction
B00661839-I1-GC
12/22/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Tae Chong
12/22/2022
Special inspection requirement — Mechanical Systems
Tae Chong
12/22/2022
Special inspection requirement — Final
Tae Chong
12/22/2022
Special inspection requirement — Energy Code Compliance Inspections
Tae Chong
12/22/2022
Special inspection requirement — Shutoff dampers
Tae Chong
12/22/2022
Special inspection requirement — Duct leakage testing, insulation and design
Tae Chong
12/22/2022
Special inspection requirement — Insulation placement and R values
Tae Chong
12/22/2022
Special inspection requirement — HVAC-R and service water heating system controls
Tae Chong
12/22/2022
Special inspection requirement — HVAC-R and service water heating equipment
Tae Chong
12/22/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Tae Chong
12/20/2022
Objection resolved — Addressed
12/13/2022
Signed off — Alteration
INTERIOR RENOVATION OF EXISTING 1 FAMILY, 3 STORY HOUSE. NO CHANG IN USE, EGRESS, OR OCCUPANCY.
B00639659-I1
12/06/2022
Filed — Alteration
INTERIOR RENOVATION OF EXISTING 1 FAMILY, 3 STORY HOUSE. NO CHANG IN USE, EGRESS, OR OCCUPANCY.
B00639659-P2
12/06/2022
Special inspection requirement — Final
Tae Chong
11/21/2022
Objection raised — Scope
11/17/2022
Filed — Alteration
INSTALLATION OF PLUMBING FIXTURES.
B00639662-P2
11/07/2022
Filed — Alteration
INSTALLATION OF 2ND FLOOR ROOF TERRACE AND HEAT PUMPS AT THE BUILDING BACK. INSTALLATION OF A/C BLOWER AND DUCT WORK AT BUILDING INSIDE. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00661839-P1
10/28/2022
Permit issued — Plumbing
B00639662-I1-PL
10/10/2022
Filed — Alteration
INSTALLATION OF PLUMBING FIXTURES.
B00639662-P1
10/10/2022
Filed — Alteration
INTERIOR RENOVATION OF EXISTING 1 FAMILY, 3 STORY HOUSE. NO CHANG IN USE, EGRESS, OR OCCUPANCY.
B00639659-P1
09/20/2022
Special inspection requirement — Mechanical Systems
Tae Chong
09/20/2022
Special inspection requirement — Energy Code Compliance Inspections
Tae Chong
09/20/2022
Special inspection requirement — Final
Tae Chong
09/20/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Tae Chong
09/20/2022
Special inspection requirement — HVAC-R and service water heating equipment
Tae Chong
09/20/2022
Special inspection requirement — Duct leakage testing, insulation and design
Tae Chong
09/20/2022
Special inspection requirement — HVAC-R and service water heating system controls
Tae Chong
09/20/2022
Special inspection requirement — Insulation placement and R values
Tae Chong
09/20/2022
Special inspection requirement — Shutoff dampers
Tae Chong
09/20/2022
Special inspection requirement — Final
Tae Chong
09/20/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Tae Chong
05/26/2022
Permit issued — Mechanical Systems
B00661839-I1-MS
05/19/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/11/2022
Filed — Alteration
INSTALLATION OF 2ND FLOOR ROOF TERRACE AND HEAT PUMPS AT THE BUILDING BACK. INSTALLATION OF A/C BLOWER AND DUCT WORK AT BUILDING INSIDE. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00661839-I1
03/23/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/23/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/05/2022
Permit issued — Plumbing
B00639662-I1-PL
12/14/2021
Permit issued — General Construction
B00639659-I1-GC
12/08/2021
Filed — Alteration
INSTALLATION OF PLUMBING FIXTURES.
B00639662-I1
12/08/2021
Filed — Alteration
INTERIOR RENOVATION OF EXISTING 1 FAMILY, 3 STORY HOUSE. NO CHANG IN USE, EGRESS, OR OCCUPANCY.
B00639659-I1
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/19/2024$5.5M—Private party → Private party$1,860/sf building
09/10/2021$3.5M—Private party → Private party$1,186/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ECOPLUSDESIGN812/06/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ION DESIGN1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JBJ CONCRETE RENOVATIONSGeneral Contractor307/08/2026
WINTER WOLF CORPGeneral Contractor107/08/2026
BT'S PLUMBING AND HEATINGPlumbing107/08/2026
K & Y PLBG AND HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CHONG ENGINEERING P.C.7411211/07/2022
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offJBJ CONCRETE RENOVATIONS01/10/2023
DOB NOWPlumbingSigned-offK & Y PLBG AND HTG INC10/28/2022
DOB NOWMechanical SystemsSigned-offWINTER WOLF CORP05/26/2022
DOB NOWPlumbingSigned-offBT'S PLUMBING AND HEATING01/05/2022
DOB NOWGeneral ConstructionSigned-offJBJ CONCRETE RENOVATIONS12/14/2021
BISOTISSUEDBROOKLYN SOLARWORKS LLC03/13/2018
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
05/19/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/23/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/23/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
12/22/2022Fire-Resistant Penetrations and JointsTae Chongspecial
12/22/2022Mechanical SystemsTae Chongspecial
12/22/2022FinalTae Chongprogress
12/22/2022Energy Code Compliance InspectionsTae Chongprogress
12/22/2022Shutoff dampersTae Chongenergy_progress
12/22/2022Duct leakage testing, insulation and designTae Chongenergy_progress
12/22/2022Insulation placement and R valuesTae Chongenergy_progress
12/22/2022HVAC-R and service water heating system controlsTae Chongenergy_progress
12/22/2022HVAC-R and service water heating equipmentTae Chongenergy_progress
12/22/2022HVAC-R and service water piping design and insulationTae Chongenergy_progress
12/06/2022FinalTae Chongprogress
09/20/2022Mechanical SystemsTae Chongspecial
09/20/2022Energy Code Compliance InspectionsTae Chongprogress
09/20/2022FinalTae Chongprogress
09/20/2022HVAC-R and service water piping design and insulationTae Chongenergy_progress
09/20/2022HVAC-R and service water heating equipmentTae Chongenergy_progress
09/20/2022Duct leakage testing, insulation and designTae Chongenergy_progress
09/20/2022HVAC-R and service water heating system controlsTae Chongenergy_progress
09/20/2022Insulation placement and R valuesTae Chongenergy_progress
09/20/2022Shutoff dampersTae Chongenergy_progress
09/20/2022FinalTae Chongprogress
09/20/2022Fire-Resistant Penetrations and JointsTae Chongspecial
▾Documents — 55 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/31/2026B00639662-P1Request digital key ↗
08/31/2026B00639662-P2Request digital key ↗
08/31/2026B00639662-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits9
▸DOB NOWLPC Approval/Permit7
08/15/2026B00661839-P1Open ↗
08/13/2026B00639659-P2Open ↗
08/13/2026B00639662-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION1
02/21/2018340584273Open ↗
▸BISWORK PERMIT APPLICATION1
03/13/2018340584273Open ↗
▸Seals & Professional Certifications17
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/31/2026B00639662-P1Open ↗
08/31/2026B00639662-I1Open ↗
08/31/2026B00639662-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/02/2026B00639659-I1Open ↗
08/31/2026B00639659-P1Open ↗
08/29/2026B00661839-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/29/2026B00661839-P1Open ↗
08/26/2026B00661839-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
02/21/2018340584273Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
02/21/2018340584273Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/31/2026B00639662-I1Open ↗
08/30/2026B00661839-I1Open ↗
08/13/2026B00639659-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/21/2018340584273Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
05/08/2018340584273Open ↗
02/21/2018340584273Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/08/2018340584273Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
05/08/2018340584273Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
02/21/2018340584273Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/30/2026B00661839-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
05/08/2018340584273Open ↗
02/21/2018340584273Open ↗
▸Approvals, Objections & Sign-offs4
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/08/2018340584273Open ↗
▸BISLANDMARKS SIGNOFF1
05/08/2018340584273Open ↗
▸BISLANDMARKS APPROVAL1
02/21/2018340584273Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
05/08/2018340584273Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/08/2018340584273Open ↗
02/21/2018340584273Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
03/12/2018340584273Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/21/2018340584273Open ↗