← Back
Over six families without stores
605 59 STREET
BROOKLYN · BIN 3016108
💬 Discuss this project
1924Year Built
5Stories
C1Building Class
R6AZoning
13,000 sfGross Floor Area
14Units
Rent Stabilized9 Open Violations ▸FDNY Report ↗
Over six families without stores · 2,840 sf lot · 4.58 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Roof8p · 1 filing · 13 docs
Cellar7p · 1 filing · 13 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VERIZON WIRELESS103/21/2026
OUR LADY OF PREPTL HELP CHURCH603/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TECTONIC ENGINEERING & SURVEYING CO205/13/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONSTRUCTION PERMIT SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MICHAEL MURPHYElectrical103/21/2026
MURPHY, MICHAELElectrical103/21/2026
AMP COMMUNICATIONS LLCGeneral Contractor104/08/2026
PROSTAR PLUMBING AND HEATPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106205/13/2024
Building Lifecycle
All (35)Filed (2)Permit Issued (2)Signed Off (1)Violation (22)Inspection (3)Objection (2)Special Inspection (3)
05/01/2026
Violation issued (HPD, open)
A
10/09/2025
Signed off — Alteration
Replacement of existing non-emergency gas generator with new 50 kw non-emergency gas generator and installation of new steel dunnage on the roof. No change in use, egress, or occupancy.
B01012028-I1
09/08/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
07/11/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/06/2025
Violation issued (HPD, open)
A
05/06/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
12/20/2024
Permit issued — Plumbing
B01012028-S1-PL
08/30/2024
Permit issued — Mechanical Systems
B01012028-I1-GC-CX
05/21/2024
Objection resolved — Addressed
05/20/2024
Objection raised — Scope
05/13/2024
Filed — Alteration
Replacement of existing non-emergency gas generator with new 50 kw non-emergency gas generator and installation of new steel dunnage on the roof. No change in use, egress, or occupancy.
B01012028-I1
05/13/2024
Filed — Alteration
Replacement of existing non-emergency gas generator with new 50 kw non-emergency gas generator and installation of new steel dunnage on the roof. No change in use, egress, or occupancy.
B01012028-S1
04/08/2024
Violation issued (HPD, open)
A
02/28/2024
Special inspection requirement — Mechanical Systems
Manojkumar Patel
02/28/2024
Special inspection requirement — Tenant Protection Plan Compliance
Manojkumar Patel
02/28/2024
Special inspection requirement — Final
Manojkumar Patel
03/20/2023
Violation issued (HPD, open)
A
02/22/2022
Violation issued (HPD, open)
A
04/06/2021
Violation issued (HPD, open)
A
04/04/2019
Violation issued (FDNY_NOV, closed)
02/20/2019
Violation issued (HPD, closed)
A
02/20/2019
Violation issued (HPD, closed)
B
02/20/2019
Violation issued (HPD, closed)
A
02/20/2019
Violation issued (HPD, closed)
A
02/20/2019
Violation issued (HPD, closed)
A
02/20/2019
Violation issued (HPD, closed)
A
02/20/2019
Violation issued (HPD, closed)
A
02/20/2019
Violation issued (HPD, open)
B
11/16/2017
Violation issued (HPD, closed)
I
10/07/2015
Violation issued (HPD, closed)
I
01/31/2005
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/13/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/22/1987
Violation issued (HPD, open)
B
06/07/1983
Violation issued (HPD, open)
A
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedPROSTAR PLUMBING AND HEAT12/20/2024
DOB NOWMechanical SystemsSigned-offAMP COMMUNICATIONS LLC08/30/2024
BISOTISSUEDRC3 ELECTRIC, LLC06/08/2017
BISOTISSUEDRC3 ELECTRIC, LLC12/10/2015
BISOTISSUEDRC3 ELECTRIC, LLC11/13/2014
BISOTISSUEDRC3 ELECTRIC, LLC06/12/2014
BISPLISSUEDVARSITY PLBG & HTG INC03/12/2010
BISOTISSUEDFAST TRACK ELECTRIC CORP02/23/2010
BISMHISSUEDFAST TRACK ELECTRIC CORP02/23/2010
1 project · most recent 05/13/2024
Generators
FiledStatusContractorScopeMake / Model / Capacity
05/13/2024Signed-offAMP COMMUNICATIONS LLCGenerators
Generators
Kohler Kohler KG50 50 kW · Generator ×1
1 project · most recent 05/13/2024
Gas
FiledStatusContractorScope
05/13/2024Permit IssuedPROSTAR PLUMBING AND HEATGas
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
09/08/2025Pass-Final General Construction Non-Directive 14PassView ↗
07/11/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/06/2025Fail-Final General Construction Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
02/28/2024Mechanical SystemsManojkumar Patelspecial
02/28/2024Tenant Protection Plan ComplianceManojkumar Patelspecial
02/28/2024FinalManojkumar Patelprogress
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/25/2026B01012028-S1Request digital key ↗
08/25/2026B01012028-I1Request digital key ↗
08/25/2026B01012028-P1Request digital key ↗
▸Applications & Permits11
▸BISWORK PERMIT APPLICATION7
06/13/2017320928724Open ↗
01/08/2016320928724Open ↗
11/18/2014320928724Open ↗
Showing 3 of 7 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION3
07/17/2014320928724Open ↗
01/25/2010320114595Open ↗
01/21/2010320114586Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
08/30/2017320928724Open ↗
▸Seals & Professional Certifications15
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
10/16/2018320928724Open ↗
06/04/2018320928724Open ↗
07/17/2014320928724Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/25/2026B01012028-S1Open ↗
08/25/2026B01012028-I1Open ↗
08/25/2026B01012028-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/23/2026B01012028-I1Open ↗
08/23/2026B01012028-I1Open ↗
08/22/2026B01012028-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/23/2026B01012028-I1Open ↗
▸Trade Schedules & Equipment2
▸BISEQUIPMENT USE PERMITS1
11/07/2011320114586Open ↗
▸BISSCHEDULE B - PLUMBING1
01/21/2010320114586Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
06/04/2018320928724Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/25/2026B01012028-I1Open ↗
08/25/2026B01012028-P1Open ↗
08/25/2026B01012028-S1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
01/25/2010320114595Open ↗
01/21/2010320114586Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/17/2014320928724Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
10/16/2018320928724Open ↗
06/04/2018320928724Open ↗
07/17/2014320928724Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/16/2018320928724Open ↗
▸Approvals, Objections & Sign-offs9
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
10/16/2018320928724Open ↗
11/10/2011320114586Open ↗
11/07/2011320114586Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
07/17/2014320928724Open ↗
01/25/2010320114595Open ↗
01/21/2010320114586Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
06/04/2018320928724Open ↗
06/04/2018320928724Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT7
10/16/2018320928724Open ↗
06/04/2018320928724Open ↗
07/17/2014320928724Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET1
07/17/2014320928724Open ↗
▸BISADDITIONAL INFORMATION1
06/04/2018320928724Open ↗
▸BISBOROUGH INTAKE FORM1
10/16/2018320928724Open ↗
▸Other Documents1
▸BISUnknown1
01/25/2010320114595Open ↗