← Back
Two stories - detached, small or mid-size
607 WILSON AVENUE
STATEN ISLAND · Great Kills-Eltingville · BIN 5075060
💬 Discuss this project
1940Year Built
1.75Stories
A1Building Class
R3-1Zoning
1,694 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 6,000 sf lot · 0.28 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR109/08/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281109/08/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
01/02/2026
Signed off — Alteration
Installation of solar panels, rooftop, grid tied, railed, 20 modules, 8.6 KW
S01283297-I1
09/10/2025
Permit issued — Solar
S01283297-I1-SL
09/08/2025
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 20 modules, 8.6 KW
S01283297-I1
09/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
09/08/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
09/08/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
09/08/2025
Special inspection requirement — Final
Mina Makar
09/08/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR09/10/2025
BISPLISSUEDJFR CONSTRUCTION CORP08/20/2004
1 project · most recent 09/08/2025
FiledStatusContractorScope
09/08/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
09/08/2025Fire-Resistant Penetrations and JointsMina Makarspecial
09/08/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
09/08/2025Energy Code Compliance InspectionsMina Makarprogress
09/08/2025FinalMina Makarprogress
09/08/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/18/2026S01283297-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026S01283297-I1Open ↗
08/26/2026S01283297-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01283297-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026S01283297-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01283297-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01283297-I1Open ↗