| Owner | Filings | Most Recent |
|---|---|---|
| THC CONSTRUCTION | 1 | 03/22/2026 |
| 166 PROPERTY | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/17/2023 | $1.4M | — | Private party → 166 PROPERTY LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| AMERILAND BROOK LLC | 6 | 05/11/2026 |
| BRIAN ILL DEVELOPMENT LLC | 3 | 02/09/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THC CONSTRUCTION INC | General Contractor | 18 | 07/08/2026 |
| STREAM ROCK CONTSRUCTION* | General Contractor | 2 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AMERILAND BROOK LLC | 1506 | 7 | 05/11/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | STREAM ROCK CONTSRUCTION* | 05/01/2026 |
| DOB NOW | Earth Work | Permit Issued | STREAM ROCK CONTSRUCTION* | 03/02/2026 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 02/02/2026 |
| DOB NOW | Construction Fence | Signed-off | THC CONSTRUCTION INC | 05/14/2025 |
| DOB NOW | Structural | Permit Issued | THC CONSTRUCTION INC | 05/14/2025 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 01/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | THC CONSTRUCTION INC | 05/30/2024 |
| DOB NOW | Foundation | Permit Issued | THC CONSTRUCTION INC | 05/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | THC CONSTRUCTION INC | 05/29/2024 |
| DOB NOW | General Construction | Signed-off | THC CONSTRUCTION INC | 05/29/2024 |
| DOB NOW | Full Demolition | Signed-off | THC CONSTRUCTION INC | 04/03/2024 |
| DOB NOW | Construction Fence | Signed-off | THC CONSTRUCTION INC | 01/29/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/11/2026 | Signed-off | STREAM ROCK CONTSRUCTION* | Heating Systems | Heating A.O. Smith CGR-40 200 40,000 BTU · Water Heater ×6 Williamson GWA-100-N-T 100,000 BTU · Boiler ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/11/2026 | Signed-off | WATSON'S PLBG, HTG, & BDG | Gas, Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2024 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/11/2026 | Signed-off | STREAM ROCK CONTSRUCTION* | Steel, Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/07/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/17/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/28/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/17/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/17/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/12/2026 | Final | BRIAN ILL | progress |
| 05/12/2026 | Subsurface Investigations (Borings/Test Pits) | TONY ONYEAGORO | special |
| 05/12/2026 | Structural Cold-Formed Steel | XIAOHONG ZHAO | special |
| 05/12/2026 | Structural Steel - High Strength Bolting | XIAOHONG ZHAO | special |
| 05/12/2026 | Subgrade Inspections | XIAOHONG ZHAO | special |
| 05/12/2026 | Mechanical Systems | XIAOHONG ZHAO | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | XIAOHONG ZHAO | special |
| 05/12/2026 | Masonry | XIAOHONG ZHAO | special |
| 05/12/2026 | Structural Steel - Details | XIAOHONG ZHAO | special |
| 05/12/2026 | Heating Systems | XIAOHONG ZHAO | special |
| 05/12/2026 | Excavations - Sheeting, Shoring, and Bracing | XIAOHONG ZHAO | special |
| 05/12/2026 | Structural Steel - Welding | XIAOHONG ZHAO | special |
| 05/12/2026 | Concrete - Cast-In-Place | XIAOHONG ZHAO | special |
| 05/12/2026 | Energy Code Compliance Inspections | XIAOHONG ZHAO | progress |
| 05/12/2026 | Fire-Resistance Rated Construction | XIAOHONG ZHAO | progress |
| 05/12/2026 | Footing and Foundation | XIAOHONG ZHAO | progress |
| 05/12/2026 | Duct leakage testing, insulation and design | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | Ventilation and air distribution system | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | Fenestration areas | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | HVAC-R and service water heating equipment | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | Permanent certificate | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | Electric vehicle service equipment requirements | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | Interior lighting power | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | HVAC-R and service water piping design and insulation | XIAOHONG ZHAO | energy_progress |
| 05/12/2026 | Metering | XIAOHONG ZHAO | energy_progress |