← Back
Elevator cooperative
Park Plz
61-15 97 STREET · BIN 4449614
💬 Discuss this project
1960Year Built
15Stories
D4Building Class
R7-1Zoning
416,450 sfGross Floor Area
445Units
LL97 CoveredRent Stabilized35 Open Violations 32 unresolved · 3 paperwork only ▸FISP: UNSAFEFDNY Report ↗
Elevator cooperative · Owner of record: PARK PLZ OWNERS CORP · 76,000 sf lot · 5.48 FAR built · Flood zone X
Locations of Work
Architecture
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
LOVETT REALTY1609/10/2026
TRIERA CONTRACTING1007/08/2026
CLASSIC CONSULTING GROUP304/09/2026
NCD RESTORATIONS INC103/22/2026
MGRE103/22/2026
PARK PLAZA CORP203/22/2026
METRO MANAGEMENT103/22/2026
PARK PLAZA OWNER S2603/22/2026
C O METRO MAN DEVELOPMENT203/21/2026
PARK PLAZA OWNER CORP C O MARK G303/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ALSIEUX ARCHITECTURE, LLC.101/15/2026
PARADIGM ARCHITECTURE202/05/2025
RIGID STRUCTURAL DESIGN, LLC109/24/2024
ROYAL ENGINEERING, P.C208/01/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SATO CONSTRUCTION1003/21/2026
Rigid Structural Design, LLC203/21/2026
MUNICIPAL BUILDING CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRIERA CONTRACTING INCGeneral Contractor707/08/2026
CEPRINE CONSTRUCTION INCGeneral Contractor509/10/2026
SATO CONSTRUCTION CO.INCGeneral Contractor207/08/2026
CLASSIC CONSULTING GROUPGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARADIGM ARCHITECTURE5931302/05/2025
Building Lifecycle
All (120)Filed (11)Permit Issued (11)Signed Off (1)Facade (FISP) (12)Violation (60)Inspection (5)Objection (2)Special Inspection (18)
09/09/2026
Permit issued — Sidewalk Shed
Q01082223-I1-SH
07/05/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/26/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/21/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/11/2026
Permit issued — General Construction
Q01131325-I1-GC
02/12/2026
Violation issued (HPD, open)
B
02/12/2026
Violation issued (HPD, open)
B
02/12/2026
Violation issued (HPD, open)
C
01/23/2026
Permit issued — Supported Scaffold
Q01347055-I1-SF
01/15/2026
Filed — Alteration
PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR NEW BUILDING AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01347055-I1
11/14/2025
Violation issued (HPD, open)
A
11/14/2025
Violation issued (HPD, closed)
C
11/13/2025
Permit issued — Suspended Scaffold
Q01149389-I1-SC
10/20/2025
Filed — Alteration
Amendment CD5: Adding new beam size to the chart & tieback direction options
Q01149389-P4
10/20/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
JAMES NAPOLI
10/09/2025
Objection raised — Inspections
10/09/2025
Objection resolved — Addressed
10/06/2025
Filed — Alteration
Amendment CD5: Adding new beam size to the chart & tieback direction options
Q01149389-P3
10/06/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
JAMES NAPOLI
09/16/2025
Permit issued — Sidewalk Shed
Q01082223-I1-SH
08/07/2025
Violation issued (ECB, closed)
Cranes and Derricks
07/24/2025
Filed — Alteration
Amendment CD5: Adding new beam size to the chart & tieback direction options
Q01149389-P2
07/24/2025
Violation issued (HPD, open)
B
07/24/2025
Violation issued (HPD, open)
B
07/24/2025
Violation issued (HPD, open)
B
07/24/2025
Violation issued (HPD, closed)
C
07/24/2025
Violation issued (HPD, open)
A
07/24/2025
Violation issued (HPD, open)
B
07/24/2025
Violation issued (HPD, open)
B
07/24/2025
Violation issued (HPD, open)
A
07/24/2025
Violation issued (HPD, open)
A
07/24/2025
Violation issued (HPD, open)
A
07/24/2025
Violation issued (HPD, open)
B
07/24/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
JAMES NAPOLI
06/16/2025
Violation issued (HPD, closed)
A
05/07/2025
Violation issued (HPD, open)
C
05/07/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/04/2025
Filed — Alteration
Amendment CD5: Adding new beam size to the chart & tieback direction options
Q01149389-P1
04/04/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
JAMES NAPOLI
03/25/2025
Permit issued — General Construction
Q01131325-I1-GC
02/25/2025
Special inspection requirement — Energy Code Compliance Inspections
Anthony Addesso
02/25/2025
Special inspection requirement — Final
Anthony Addesso
02/25/2025
Special inspection requirement — Air barrier - visual inspection
Anthony Addesso
02/25/2025
Special inspection requirement — Masonry
Anthony Addesso
02/25/2025
Special inspection requirement — Post-installed Anchors
Anthony Addesso
02/25/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Addesso
02/25/2025
Special inspection requirement — Tenant Protection Plan Compliance
Anthony Addesso
02/05/2025
Filed — Alteration
EXTERIOR RESTORATION TO INCLUDE BRICK REPLACEMENT, COPING AND SHELF ANGLE REPLACEMENT AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY
Q01131325-P1
01/30/2025
Special inspection requirement — Tenant Protection Plan Compliance
01/30/2025
Special inspection requirement — Masonry
Anthony Addesso
01/30/2025
Special inspection requirement — Post-installed Anchors
Anthony Addesso
01/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Addesso
01/30/2025
Special inspection requirement — Energy Code Compliance Inspections
Anthony Addesso
01/30/2025
Special inspection requirement — Final
Anthony Addesso
01/30/2025
Special inspection requirement — Air barrier - visual inspection
Anthony Addesso
12/19/2024
Cycle 9 facade report submitted
12/19/2024
Cycle 9 facade report signed — UNSAFE
12/19/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/12/2024
Permit issued — Suspended Scaffold
Q01149389-I1-SC
12/02/2024
Filed — Alteration
Amendment CD5: Adding new beam size to the chart & tieback direction options
Q01149389-I1
Latest 60 of 120 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedCEPRINE CONSTRUCTION INC09/09/2026
DOB NOWGeneral ConstructionPermit IssuedSATO CONSTRUCTION CO.INC03/11/2026
DOB NOWSupported ScaffoldPermit IssuedCLASSIC CONSULTING GROUP01/23/2026
DOB NOWSuspended ScaffoldPermit IssuedSATO CONSTRUCTION CO. INC11/13/2025
DOB NOWSidewalk ShedPermit IssuedCEPRINE CONSTRUCTION INC09/16/2025
DOB NOWGeneral ConstructionPermit IssuedSATO CONSTRUCTION CO.INC03/25/2025
DOB NOWSuspended ScaffoldPermit IssuedSATO CONSTRUCTION CO. INC12/12/2024
DOB NOWSidewalk ShedPermit IssuedCEPRINE CONSTRUCTION INC09/24/2024
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC07/06/2020
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC07/05/2019
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC07/11/2018
BISOTISSUEDRCD RESTORATIONS INC05/26/2020
BISOTISSUEDRCD RESTORATIONS INC04/14/2020
BISOTISSUEDRCD RESTORATIONS INC12/05/2018
BISOTISSUEDRCD RESTORATIONS INC07/26/2018
BISPLISSUEDG.BASSOLINO PLUMBING LTD10/26/2017
BISOTISSUEDHERITAGE CHIMNEY SERVICE08/09/2016
BISEQISSUEDHERITAGE CHIMNEY SERVICE07/18/2016
BISPLISSUEDALJER PLBG & HTG CORP03/05/2015
BISOTISSUEDAAA P INTERNATIONAL INC02/25/2015
BISEQISSUEDROCK GROUP NY CORP04/23/2014
BISEQISSUEDEVEREST SCAFFOLDING INC03/20/2012
BISEQISSUEDEVEREST SCAFFOLDING INC03/24/2011
BISOTISSUEDSATO CONSTRUCTION CO.INC01/03/2011
BISEQISSUEDEVEREST SCAFFOLDING INC06/22/2010
BISOTISSUEDSATO CONSTRUCTION CO.INC04/27/2010
BISOTISSUEDPHEONIX CONSTRUCTION INC03/27/2009
BISOTISSUEDPHOENIX CONSTRUCTION INC.01/10/2008
BISPLISSUEDAURORA P & H CONT INC11/16/2007
BISOTISSUEDDJM CONTRACTING SERVICES, CORP06/21/2002
BISEQISSUEDSPRING SCAFFOLDING INC.10/23/1998
5 projects · most recent 09/30/2024
General Wiring Lighting
FiledStatusContractorScope
09/30/2024Permit IssuedHIGH QUALITY ELECTRIC OF—
03/07/2023Permit IssuedROBERT CHIMENTI62 meters, 1 new_meters
09/20/2021Permit IssuedY.S ELECTRICGeneral Wiring, Lighting
11/30/2020Permit IssuedBEZOLD & ALBA ELEC'L CONTGeneral Wiring
07/11/2018CompleteMEO ELECTRIC CORP—
1 project · most recent 01/15/2026
Scaffold
FiledStatusContractorScope
01/15/2026Permit IssuedCLASSIC CONSULTING GROUPScaffold
1 project · most recent 10/20/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
10/20/2025Permit IssuedSATO CONSTRUCTION CO. INCSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
07/05/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/26/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/21/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/03/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/03/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
10/20/2025Alternative Materials - OTCR Buildings Bulletin NumberJAMES NAPOLIspecial
10/06/2025Alternative Materials - OTCR Buildings Bulletin NumberJAMES NAPOLIspecial
07/24/2025Alternative Materials - OTCR Buildings Bulletin NumberJAMES NAPOLIspecial
04/04/2025Alternative Materials - OTCR Buildings Bulletin NumberJAMES NAPOLIspecial
02/25/2025Energy Code Compliance InspectionsAnthony Addessoprogress
02/25/2025FinalAnthony Addessoprogress
02/25/2025Air barrier - visual inspectionAnthony Addessoenergy_progress
02/25/2025MasonryAnthony Addessospecial
02/25/2025Post-installed AnchorsAnthony Addessospecial
02/25/2025Structural Stability – Alterations of existing buildingsAnthony Addessospecial
02/25/2025Tenant Protection Plan ComplianceAnthony Addessospecial
01/30/2025Tenant Protection Plan Compliance—special
01/30/2025MasonryAnthony Addessospecial
01/30/2025Post-installed AnchorsAnthony Addessospecial
01/30/2025Structural Stability – Alterations of existing buildingsAnthony Addessospecial
01/30/2025Energy Code Compliance InspectionsAnthony Addessoprogress
01/30/2025FinalAnthony Addessoprogress
01/30/2025Air barrier - visual inspectionAnthony Addessoenergy_progress
▾Documents — 188 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/28/2026Q00060700-I1Request digital key ↗
08/28/2026Q00060700-P1Request digital key ↗
08/21/2026Q01082223-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits28
▸BISWORK PERMIT APPLICATION16
05/28/2020421648863Open ↗
08/05/2019421648863Open ↗
12/19/2018421648863Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION11
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
08/05/2016440332775Open ↗
Showing 3 of 11 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
03/15/2016421051195Open ↗
▸Seals & Professional Certifications53
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
07/24/2018421571132Open ↗
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
09/03/2026Q01149389-P2Open ↗
09/02/2026Q01131325-I1Open ↗
09/02/2026Q01131325-I1Open ↗
Showing 3 of 11 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
04/30/2014420972870Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/02/2026Q01131325-I1Open ↗
09/02/2026Q01131325-I1Open ↗
09/02/2026Q01131325-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/28/2026Q00060700-I1Open ↗
08/28/2026Q00060700-P1Open ↗
08/21/2026Q01131325-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
08/05/2016440332775Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
05/23/2011420204610Open ↗
06/23/2010420204610Open ↗
11/16/2007410030185Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
08/05/2016440332775Open ↗
07/15/2016440325523Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
08/05/2016440332775Open ↗
07/15/2016440325523Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
10/28/2017421571132Open ↗
11/24/2014421051195Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
12/04/2015421051195Open ↗
06/15/2009410030185Open ↗
▸BISSCHEDULE B - PLUMBING1
11/19/2007410030185Open ↗
▸Safety & Tenant Protection7
▸BISTenant Protection Plan and Notes6
10/20/2018421648863Open ↗
10/03/2018421648863Open ↗
07/19/2018421648863Open ↗
Showing 3 of 6 on file for this type
▸BISSTREET TREE CHECKLIST1
11/24/2014421051195Open ↗
▸Environmental & Asbestos12
▸BISASBESTOS: CERTIFICATION (DEP ACP5)7
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
08/05/2016440332775Open ↗
Showing 3 of 7 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
11/16/2007410030185Open ↗
04/16/2010420175054Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/21/2026Q01131325-I1Open ↗
08/13/2026Q01131325-P1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
06/23/2010420204610Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
07/24/2018421571132Open ↗
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
07/24/2018421571132Open ↗
02/07/2017440332775Open ↗
03/15/2016421051195Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
08/05/2016440332775Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/16/2020421648863Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
08/05/2016440332775Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
10/16/2020421648863Open ↗
08/05/2016440332775Open ↗
07/15/2016440325523Open ↗
▸Approvals, Objections & Sign-offs19
▸BISADMINISTRATIVE OBJECTIONS6
11/24/2014421051195Open ↗
08/29/2014421006645Open ↗
04/30/2014420972870Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION6
07/24/2018421571132Open ↗
04/10/2018421571132Open ↗
04/10/2018421571132Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
10/16/2020421648863Open ↗
07/24/2018421571132Open ↗
02/16/2017440332775Open ↗
Showing 3 of 5 on file for this type
▸BISSHED LETTER1
05/26/2011420204610Open ↗
▸BISSUPERSEDING LETTER1
06/02/2009410030185Open ↗
▸Cost, Insurance & Ownership12
▸BISCOST AFFIDAVIT11
07/24/2018421571132Open ↗
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
Showing 3 of 11 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
10/16/2020421648863Open ↗
▸Filing & Intake Forms11
▸BISEFILING COVER SHEET7
07/19/2018421648863Open ↗
10/28/2017421571132Open ↗
11/24/2014421051195Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
08/05/2016440332775Open ↗
07/15/2016440325523Open ↗
▸BISADDITIONAL INFORMATION2
05/24/2011420204610Open ↗
05/23/2011420204610Open ↗
▸Other Documents13
▸DOB NOWCalculations5
08/18/2026Q01149389-P2Open ↗
08/18/2026Q01149389-P3Open ↗
08/18/2026Q01149389-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWManufacturer's Specifications5
08/18/2026Q01149389-P3Open ↗
08/18/2026Q01149389-I1Open ↗
08/18/2026Q01149389-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWBSA Meeting Minutes/BSA Resolution2
08/13/2026Q00060700-P1Open ↗
08/13/2026Q00060700-I1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
04/10/2018421571132Open ↗