← Back
Primarily 5-6 family with 1 store or office
61 2 AVENUE
MANHATTAN · BIN 1006575
💬 Discuss this project
1842Year Built
5Stories
S5Building Class
R7AZoning
8,280 sfGross Floor Area
6Units
Rent Stabilized0 Open Violations
Primarily 5-6 family with 1 store or office · Owner of record: 61 MEATH REALTY CORP · 2,400 sf lot · 3.45 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 33p · 1 filing · 16 docs
Floor 2
Floor 1
Basement4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
61 MEATH REALTY3407/08/2026
OWNER OF OREMISES103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BH INTERIORS INCGeneral Contractor307/08/2026
METROTECH MECHANICAL CORPPlumbing207/08/2026
DEREK KINGElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ERIC SAFYAN ARCHITECTPC3248207/06/2026
JAMES D. FERRANTE, ARCHIT8149212/29/2021
CTHREE ARCHITECTURE + DES1124412/28/2021
Building Lifecycle
All (65)Filed (9)Permit Issued (5)Signed Off (3)Violation (12)Inspection (7)Objection (8)Special Inspection (21)
07/17/2026
Objection resolved — Addressed
07/17/2026
Objection resolved — Addressed
07/15/2026
Objection raised — Inspections
07/15/2026
Objection raised — Other
07/10/2026
Objection resolved — Resolved
07/08/2026
Objection raised — Accessibility
07/06/2026
Filed — Alteration
INTERIOR RENOVATION OF 3RD FLOOR APARTMENT. PARTITION WORK, KITCHEN AND BATHROOM RENOVATIONS. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M01425547-S1
07/06/2026
Filed — Alteration
INTERIOR RENOVATION OF 3RD FLOOR APARTMENT. PARTITION WORK, KITCHEN AND BATHROOM RENOVATIONS. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M01425547-I1
07/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Eric Safyan
07/02/2026
Special inspection requirement — Lighting controls
Eric Safyan
07/02/2026
Special inspection requirement — Fire-Resistance Rated Construction
Eric Safyan
07/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Eric Safyan
07/02/2026
Special inspection requirement — Energy Code Compliance Inspections
Eric Safyan
07/02/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Eric Safyan
07/02/2026
Special inspection requirement — Energy Code Compliance Inspections
Eric Safyan
07/02/2026
Special inspection requirement — Lighting in dwelling units
Eric Safyan
07/02/2026
Special inspection requirement — Interior lighting power
Eric Safyan
07/01/2026
Special inspection requirement — Final
Eric Safyan
11/02/2022
Violation issued (HPD, closed)
I
02/24/2022
Signed off — Alteration
GENERAL CONSTRUCTION IN CONNECTION WITH THE COMBINATION OF APT 5-A AND APT 5-B LOCATED ON THE 4TH FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00566224-I1
02/24/2022
Signed off — Alteration
M00583740-I1
02/17/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/17/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/15/2022
Violation issued (HPD, closed)
A
02/15/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/11/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
james ferrante
01/11/2022
Special inspection requirement — Mechanical Systems
james ferrante
01/11/2022
Special inspection requirement — Final
james ferrante
01/11/2022
Special inspection requirement — Lighting in dwelling units
james ferrante
01/11/2022
Special inspection requirement — Lighting controls
james ferrante
01/06/2022
Objection resolved — Addressed
01/04/2022
Objection raised — Other
12/29/2021
Filed — Alteration
GENERAL CONSTRUCTION IN CONNECTION WITH THE COMBINATION OF APT 5-A AND APT 5-B LOCATED ON THE 4TH FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00566224-P1
12/28/2021
Filed — Alteration
Plumbing work relocation of fixtures for renovation of existing restaurant
M00545454-P2
11/24/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/15/2021
Permit issued — General Construction
M00566224-I1-GC-CX
11/12/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/04/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Salvatore Croce
10/14/2021
Permit issued — Plumbing
M00583740-I1-PL
10/08/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/20/2021
Permit issued — General Construction
M00566224-I1-GC-CX
09/10/2021
Signed off — Alteration
Plumbing work relocation of fixtures for renovation of existing restaurant
M00545454-I1
09/02/2021
Filed — Alteration
GENERAL CONSTRUCTION IN CONNECTION WITH THE COMBINATION OF APT 5-A AND APT 5-B LOCATED ON THE 4TH FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00566224-I1
09/02/2021
Filed — Alteration
M00583740-I1
08/03/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/23/2021
Filed — Alteration
Plumbing work relocation of fixtures for renovation of existing restaurant
M00545454-P1
07/23/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Salvatore Croce
07/21/2021
Permit issued — Plumbing
M00545454-S1-PL
07/19/2021
Filed — Alteration
Plumbing work relocation of fixtures for renovation of existing restaurant
M00545454-S1
07/19/2021
Permit issued — General Construction
M00545454-I1-GC
07/09/2021
Filed — Alteration
Plumbing work relocation of fixtures for renovation of existing restaurant
M00545454-I1
07/08/2021
Special inspection requirement — Interior lighting power
Salvatore Croce
07/08/2021
Special inspection requirement — Energy Code Compliance Inspections
Salvatore Croce
07/08/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Salvatore Croce
06/23/2021
Special inspection requirement — Final
Salvatore Croce
04/01/2021
Violation issued (HPD, closed)
A
10/05/2018
Violation issued (HPD, closed)
I
07/22/2018
Violation issued (HPD, closed)
B
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/24/2016
Violation issued (HPD, closed)
I
Latest 60 of 65 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offBH INTERIORS11/15/2021
DOB NOWPlumbingSigned-offMETROTECH MECHANICAL CORP10/14/2021
DOB NOWGeneral ConstructionSigned-offBH INTERIORS09/20/2021
DOB NOWPlumbingSigned-offMETROTECH MECHANICAL CORP07/21/2021
DOB NOWGeneral ConstructionSigned-offBH INTERIORS07/19/2021
BISPLISSUEDACCURATE MECHANICAL INC05/16/2016
BISOTISSUEDNAVAC BUILDERS INC04/26/2016
BISFPISSUEDMASTER FIRE PREV SYS INC10/10/2007
BISOTISSUEDAJK CONSTRUCTION CORP.06/29/2007
BISBLISSUEDDEMAR PLUMBING CORP04/22/2005
BISPLISSUEDDEMAR PLUMBING CORP04/22/2005
BIS—ISSUEDMONTANA ELECTRICAL DECORATING CO12/02/2003
BISPLISSUEDBISSETTA & LIST INC12/09/1998
BIS—ISSUEDCOMPLETE CONSTRUCTION SERVICE,IN12/09/1998
BISPLRE-ISSUEDBISSETTA & LIST INC11/18/1998
BISOTISSUEDCOMPLETE CONSTRUCTION SERVICE,IN08/24/1998
BISOTISSUEDSAME04/18/1996
2 projects · most recent 07/06/2026
Water/Sanitary Gas
FiledStatusContractorScope
07/06/2026——Gas, Water/Sanitary
12/28/2021Signed-offMETROTECH MECHANICAL CORPWater/Sanitary
1 project · most recent 03/19/2022
General Wiring
FiledStatusContractorScope
03/19/2022CompleteEURO ELEC'L CONTRG, INCGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/17/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/17/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/15/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/24/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/12/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/08/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/03/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
07/02/2026Fire-Resistant Penetrations and JointsEric Safyanspecial
07/02/2026Lighting controlsEric Safyanenergy_progress
07/02/2026Fire-Resistance Rated ConstructionEric Safyanprogress
07/02/2026Fire-Resistant Penetrations and JointsEric Safyanspecial
07/02/2026Energy Code Compliance InspectionsEric Safyanprogress
07/02/2026HVAC-R and service water piping design and insulationEric Safyanenergy_progress
07/02/2026Energy Code Compliance InspectionsEric Safyanprogress
07/02/2026Lighting in dwelling unitsEric Safyanenergy_progress
07/02/2026Interior lighting powerEric Safyanenergy_progress
07/01/2026FinalEric Safyanprogress
01/11/2022Fire-Resistant Penetrations and Jointsjames ferrantespecial
01/11/2022Mechanical Systemsjames ferrantespecial
01/11/2022Finaljames ferranteprogress
01/11/2022Lighting in dwelling unitsjames ferranteenergy_progress
01/11/2022Lighting controlsjames ferranteenergy_progress
11/04/2021Fire-Resistant Penetrations and JointsSalvatore Crocespecial
07/23/2021Fire-Resistant Penetrations and JointsSalvatore Crocespecial
07/08/2021Interior lighting powerSalvatore Croceenergy_progress
07/08/2021Energy Code Compliance InspectionsSalvatore Croceprogress
07/08/2021Fire-Resistant Penetrations and JointsSalvatore Crocespecial
06/23/2021FinalSalvatore Croceprogress
▾Documents — 84 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
09/03/2026M00545454-S1Request digital key ↗
09/03/2026M00545454-I1Request digital key ↗
09/03/2026M00545454-P2Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits14
▸DOB NOWLPC Approval/Permit9
09/03/2026M00545454-S1Open ↗
09/03/2026M00545454-P1Open ↗
08/15/2026M01425547-S1Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION3
06/16/2016122716837Open ↗
06/14/2016122716837Open ↗
05/02/2016122716837Open ↗
▸BISWORK PERMIT APPLICATION2
05/26/2016122716837Open ↗
05/02/2016122716837Open ↗
▸Seals & Professional Certifications35
▸DOB NOWProgress Inspector Seal & Signature14
09/25/2026M00545454-I1Open ↗
09/25/2026M00545454-I1Open ↗
09/25/2026M00545454-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/03/2026M00545454-P1Open ↗
09/03/2026M00545454-S1Open ↗
09/03/2026M00566224-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/25/2026M00545454-I1Open ↗
08/29/2026M00545454-P1Open ↗
08/28/2026M00545454-P2Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
10/13/2016122716837Open ↗
06/13/2016104817067Open ↗
05/02/2016122716837Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
05/02/2016122716837Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
05/02/2016122716837Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
06/16/2016122716837Open ↗
06/14/2016122716837Open ↗
05/02/2016122716837Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
05/02/2016122716837Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/03/2026M00545454-P1Open ↗
09/03/2026M00545454-S1Open ↗
09/03/2026M00566224-I1Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/02/2016122716837Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
10/13/2016122716837Open ↗
05/02/2016122716837Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00566224-I1Open ↗
08/13/2026M00545454-I1Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/13/2016122716837Open ↗
▸Approvals, Objections & Sign-offs5
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
10/13/2016122716837Open ↗
06/13/2016104817067Open ↗
▸BISLANDMARKS APPROVAL2
10/13/2016122716837Open ↗
05/02/2016122716837Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/13/2016104817067Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
10/13/2016122716837Open ↗
06/13/2016104817067Open ↗
05/02/2016122716837Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
05/02/2016122716837Open ↗