| Owner | Filings | Most Recent |
|---|---|---|
| JIN SUN CONSTRUCTION | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/06/2022 | $1.6M | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| SYNERGIC DESIGN ARCHITECTS | 1 | 07/22/2025 |
| AMERILAND BROOK LLC | 6 | 01/01/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JIN SUN CONSTRUCTION INC | General Contractor | 11 | 07/08/2026 |
| ACCORD POWER ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| CL ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| ACCORD POWER INC | General Contractor | 1 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SYNERGIC DESIGN LLC | 8561 | 1 | 07/22/2025 |
| AMERILAND BROOK LLC | 1506 | 4 | 01/01/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 07/23/2025 |
| DOB NOW | Curb Cut | Signed-off | JIN L. LIN | 01/29/2025 |
| DOB NOW | Plumbing | Signed-off | RALPH W. LANDOLFI JR. | 12/05/2024 |
| DOB NOW | Earth Work | Permit Issued | JIN L. LIN | 05/31/2024 |
| DOB NOW | Construction Fence | Signed-off | JIN L. LIN | 04/29/2024 |
| DOB NOW | Sprinklers | Signed-off | WATSON'S PLBG, HTG, & BDG | 04/23/2024 |
| DOB NOW | Foundation | Permit Issued | JIN L. LIN | 12/29/2023 |
| DOB NOW | Construction Fence | Signed-off | JIN L. LIN | 10/19/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/01/2025 | Signed-off | JIN SUN CONSTRUCTION INC | Associated Ducts and Piping, Heating Systems | Heating Williamson GWA-140 140,000 BTU · Boiler ×2 Ducts & Piping Delta Breeze SLIM50 50 CFM · Exhaust Fan ×8 Air King EB30BL 130 CFM · Kitchen Exhaust ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/01/2025 | Signed-off | WATSON'S PLBG, HTG, & BDG | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2025 | Complete | ACCORD POWER ELECTRIC LLC | — |
| 06/10/2024 | Complete | CL ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/01/2025 | Signed-off | JIN SUN CONSTRUCTION INC | Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/14/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/20/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 02/04/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 02/01/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/09/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/06/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/05/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/20/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/20/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/25/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/25/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2025 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |
| 07/21/2025 | Final | Malathi Ananthakrishnan | progress |
| 07/21/2025 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 07/21/2025 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 07/21/2025 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 01/13/2025 | Subgrade Inspections | XIAOHONG ZHAO | special |
| 01/13/2025 | Structural Steel - Details | XIAOHONG ZHAO | special |
| 01/13/2025 | Structural Steel - High Strength Bolting | XIAOHONG ZHAO | special |
| 01/13/2025 | Concrete - Cast-In-Place | XIAOHONG ZHAO | special |
| 01/13/2025 | Mechanical Systems | XIAOHONG ZHAO | special |
| 01/13/2025 | Final | XIAOHONG ZHAO | progress |
| 01/13/2025 | Footing and Foundation | XIAOHONG ZHAO | progress |
| 01/13/2025 | Structural Steel - Welding | XIAOHONG ZHAO | special |
| 01/13/2025 | Fire-Resistance Rated Construction | XIAOHONG ZHAO | progress |
| 01/13/2025 | Air barrier - visual inspection | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Interior lighting power | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Insulation placement and R values | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Metering | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | HVAC-R and service water heating system controls | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Maintenance information | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Permanent certificate | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Fenestration and door U-factor and product ratings | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Air barrier — testing | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | HVAC-R and service water heating equipment | XIAOHONG ZHAO | energy_progress |
| 01/13/2025 | Fenestration areas | XIAOHONG ZHAO | energy_progress |