← Back
BuildNYC
Large suburban residence
61 ANDREWS AVENUE
STATEN ISLAND · BIN 5175149
💬 Discuss this project
2022Year Built
2Stories
A3Building Class
R1-2Zoning
3,122 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Large suburban residence · 6,500 sf lot · 0.48 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 24p · 1 filing · 20 docs
Floor 117p · 1 filing · 20 docs
Basement3p · 1 filing · 20 docs
Site & exteriorProposed construction fence1p · 1 filing · 2 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Tony Sayad Architect711/14/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NiroGeneral Contractor1107/08/2026
NiroScaffold207/08/2026
D and H Electrical ConstructionElectrical103/22/2026
Flow-Right Plumbing & HeatingPlumbing107/08/2026
Solar StringGeneral Contractor112/05/2022
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SRA Planning & Expediting5677311/11/2022
Building Lifecycle
06/24/2023
Permit expired, never signed off — Earth Work
The city's record still shows this permit as issued, with no sign-off on its filing
S00564701-I1-GC-CX
12/22/2022
Signed off — New Building
ADDITIONAL CURB CUT IN CONJUNCTION WITH NEW ONE-FAMILY RESIDENCE FILED UNDER THIS APPLICATION.
S00564701-S1
12/22/2022
Signed off — New Building
ADDITIONAL CURB CUT IN CONJUNCTION WITH NEW ONE-FAMILY RESIDENCE FILED UNDER THIS APPLICATION.
S00564701-S5
12/21/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/21/2022
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
61 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offNiro11/14/2022
DOB NOWCurb CutSigned-offNiro11/04/2022
DOB NOWFoundationSigned-offNiro11/04/2022
DOB NOWEarth WorkPermit IssuedNiro10/26/2022
DOB NOWConstruction FenceSigned-offNiro10/26/2022
DOB NOWPlumbingSigned-offFlow-Right Plumbing & Heating11/17/2021
DOB NOWFoundationPermit IssuedNiro09/20/2021
DOB NOWConstruction FenceSigned-offNiro09/15/2021
BISOTISSUEDSolar String12/05/2022
1 project · most recent 11/14/2022
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScope
11/14/2022Signed-offNiroAir Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
1 project · most recent 11/14/2022
Gas Storm Water/Sanitary
FiledStatusContractorScope
11/14/2022Signed-offFlow-Right Plumbing & HeatingGas, Storm, Water/Sanitary
3 projects · most recent 09/02/2022
General Wiring
FiledStatusContractorScope
09/02/2022CompleteD and H Electrical Construction—
02/09/2022CompleteD and H Electrical ConstructionGeneral Wiring
12/10/2021CompleteD and H Electrical Construction—
1 project · most recent 11/14/2022
Steel Wood
FiledStatusContractorScope
11/14/2022Signed-offNiroSteel, Wood
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
12/21/2022Pass-Final CND-Occupancy InspectionPassView ↗
12/21/2022Pass-Final Curb Cut Non-Directive 14PassView ↗
11/16/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/26/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/25/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
03/30/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/23/2021Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 65
DateRequirementInspectorRole
12/01/2022Fire-Resistant Penetrations and JointsWILLIAM MONTAGUEspecial
12/01/2022Subgrade InspectionsWILLIAM MONTAGUEspecial
12/01/2022Exterior Insulation and Finish Systems (EIFS)WILLIAM MONTAGUEspecial
12/01/2022Mechanical SystemsWILLIAM MONTAGUEspecial
12/01/2022Structural Steel - DetailsWILLIAM MONTAGUEspecial
12/01/2022Subsurface Investigations (Borings/Test Pits)WILLIAM MONTAGUEspecial
12/01/2022Concrete - Cast-In-PlaceWILLIAM MONTAGUEspecial
12/01/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationWILLIAM MONTAGUEspecial
12/01/2022Wood – Prefabricated I-JoistsWILLIAM MONTAGUEspecial
12/01/2022Fire-Resistance Rated ConstructionWILLIAM MONTAGUEprogress
12/01/2022Footing and FoundationWILLIAM MONTAGUEprogress
12/01/2022Structural Wood FrameWILLIAM MONTAGUEprogress
12/01/2022FinalWILLIAM MONTAGUEprogress
12/01/2022Energy Code Compliance InspectionsWILLIAM MONTAGUEprogress
12/01/2022Fenestration and door U-factor and product ratingsWILLIAM MONTAGUEenergy_progress
12/01/2022Electric vehicle service equipment requirementsWILLIAM MONTAGUEenergy_progress
12/01/2022Fenestration areasWILLIAM MONTAGUEenergy_progress
12/01/2022Permanent certificateWILLIAM MONTAGUEenergy_progress
12/01/2022Air barrier - visual inspectionWILLIAM MONTAGUEenergy_progress
12/01/2022Interior lighting powerWILLIAM MONTAGUEenergy_progress
12/01/2022Maintenance informationWILLIAM MONTAGUEenergy_progress
12/01/2022Duct leakage testing, insulation and designWILLIAM MONTAGUEenergy_progress
12/01/2022FireplacesWILLIAM MONTAGUEenergy_progress
12/01/2022Fenestration air leakageWILLIAM MONTAGUEenergy_progress
12/01/2022HVAC-R and service water heating system controlsWILLIAM MONTAGUEenergy_progress
Latest 25 of 65.
96 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account