| Owner | Filings | Most Recent |
|---|---|---|
| Buchbinder & Warren | 9 | 07/08/2026 |
| 61 E 11 St | 8 | 03/22/2026 |
| 61 East 11th Street | 7 | 03/21/2026 |
| 61 East 11 | 3 | 03/21/2026 |
| New Century Construction | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Rand Engineering & Architecture | 4 | 02/12/2025 |
| Cribstone Engineering | 1 | 02/12/2025 |
| Dean Mendez RA | 3 | 05/10/2023 |
| J&R Design and Inspection | 3 | 11/15/2021 |
| Vakota Architecture | 1 | 10/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| Rand Engineering & Arch | 8 | 03/21/2026 |
| Xinos Construction | 6 | 03/21/2026 |
| High Quality 338 | 6 | 03/21/2026 |
| S M Expediting | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Xinos Construction | Scaffold | 8 | 07/08/2026 |
| Xinos Construction | General Contractor | 4 | 07/08/2026 |
| C.W.C. Fire Suppression | Plumbing | 2 | 07/08/2026 |
| High Quality Construction | General Contractor | 2 | 03/21/2026 |
| R & L Systems | Electrical | 1 | 03/21/2026 |
| Tower Electric | Electrical | 1 | 03/21/2026 |
| P&H Electric D/B/A Mage Electric | Electrical | 1 | 03/21/2026 |
| Citywide Electrical Contracting | Electrical | 1 | 03/21/2026 |
| American Standard P&H Cororp | Plumbing | 1 | 07/08/2026 |
| Jumper Electric | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Rand Engineering & Architects | 266 | 4 | 02/12/2025 |
| J&R Design and Inspection | 6637 | 3 | 11/15/2021 |
| Vakota Architecture | 7281 | 1 | 10/10/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | Xinos Construction | 05/13/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | Xinos Construction | 02/26/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Xinos Construction | 02/12/2025 |
| DOB NOW | General Construction | Signed-off | Xinos Construction | 09/18/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Xinos Construction | 08/09/2023 |
| DOB NOW | General Construction | Signed-off | Xinos Construction | 09/22/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | Xinos Construction | 09/08/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Xinos Construction | 08/09/2022 |
| DOB NOW | Plumbing | Permit Issued | American Standard P&H Cororp | 10/15/2021 |
| DOB NOW | General Construction | Permit Issued | High Quality Construction | 09/27/2021 |
| DOB NOW | Plumbing | Permit Issued | C.W.C. Fire Suppression | 10/13/2020 |
| DOB NOW | Plumbing | Signed-off | C.W.C. Fire Suppression | 10/13/2020 |
| BIS | OT | ISSUED | Bednarz Construction | 01/26/2021 |
| BIS | OT | ISSUED | Bednarz Construction | 09/29/2020 |
| BIS | OT | ISSUED | Easco Boiler | 01/24/2018 |
| BIS | FS | ISSUED | Larry Berge | 12/20/2017 |
| BIS | OT | ISSUED | Vesta Contracting Group | 08/12/2014 |
| BIS | EQ | ISSUED | Everest Scaffolding | 07/15/2014 |
| BIS | BL | RE-ISSUED | Approved Oil Co of Brooklyn | 05/31/2011 |
| BIS | SP | ISSUED | R.J.C. Mechanical | 01/10/2011 |
| BIS | PL | ISSUED | R.J.C. Mechanical | 04/29/2009 |
| BIS | SP | ISSUED | R.J.C. Mechanical | 10/17/2008 |
| BIS | OT | ISSUED | Able Construction & Restoration | 06/12/2008 |
| BIS | OT | ISSUED | Able Construction & Restoration | 04/29/2008 |
| BIS | EQ | ISSUED | HI-Tech Bridging | 04/25/2008 |
| BIS | PL | ISSUED | R.J.C. Mechanical | 02/14/2008 |
| BIS | MH | ISSUED | McGraime Woodworking | 01/14/2008 |
| BIS | PL | ISSUED | Henry Myers Plumbing & Heating | 05/18/2004 |
| BIS | OT | ISSUED | Marquis CWC | 04/30/2004 |
| BIS | EQ | ISSUED | New Century Construction | 03/29/2000 |
| BIS | EQ | ISSUED | New Century Construction | 07/29/1999 |
| BIS | EQ | ISSUED | New Century Construction | 04/21/1999 |
| BIS | PL | ISSUED | Magor Plumbing & Heating | 11/12/1998 |
| BIS | PL | ISSUED | Amok | 02/24/1998 |
| BIS | OT | ISSUED | David B Kyner & Howard Kaplan | 02/19/1998 |
| BIS | EQ | ISSUED | Colgate Scaffolding | 11/25/1996 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/17/2021 | Permit Issued | High Quality Construction | Air Conditioning Systems | Cooling Mitsubishi Electric PUY-A36NKA7 36,000 BTU · Split System ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/15/2021 | Permit Issued | American Standard P&H | Water/Sanitary |
| 10/10/2020 | Signed-off | C.W.C. Fire Suppression | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Permit Issued | Tower Electric | — |
| 08/09/2022 | Permit Issued | Tower Electric | — |
| 07/02/2020 | Complete | Jumper Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/12/2025 | Signed-off | Xinos Construction | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/10/2023 | Signed-off | Xinos Construction | Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2025 | Permit Issued | Xinos Construction | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/01/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/03/2025 | Structural Steel - Welding | James Vignola | special |
| 03/03/2025 | Post-installed Anchors | James Vignola | special |
| 03/03/2025 | Tenant Protection Plan Compliance | James Vignola | special |
| 03/03/2025 | Concrete - Cast-In-Place | James Vignola | special |
| 03/03/2025 | Structural Steel - Details | James Vignola | special |
| 03/03/2025 | Final | James Vignola | progress |
| 02/12/2025 | Final | James Vignola | progress |
| 02/12/2025 | Concrete - Cast-In-Place | James Vignola | special |
| 02/12/2025 | Post-installed Anchors | James Vignola | special |
| 02/12/2025 | Structural Steel - Details | James Vignola | special |
| 02/12/2025 | Structural Steel - Welding | James Vignola | special |
| 02/12/2025 | Tenant Protection Plan Compliance | — | special |
| 08/30/2024 | Structural Stability – Alterations of existing buildings | John Monroe | special |
| 08/30/2024 | Masonry | John Monroe | special |
| 08/30/2024 | Final | Michael Larkin | progress |
| 08/30/2024 | Post-installed Anchors | John Monroe | special |
| 04/05/2024 | Post-installed Anchors | John Monroe | special |
| 04/05/2024 | Masonry | John Monroe | special |
| 04/05/2024 | Final | Michael Larkin | progress |
| 04/05/2024 | Structural Stability – Alterations of existing buildings | John Monroe | special |
| 11/17/2021 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 11/17/2021 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 11/17/2021 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 09/15/2021 | Interior lighting power | Robert Truskosky | energy_progress |
| 09/15/2021 | Energy Code Compliance Inspections | Robert Truskosky | progress |