1925Year Built
2Stories
A9Building Class
R5BZoning
1,170 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Miscellaneous one family · 1,431 sf lot · 0.82 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/19/2024$1.3M—Private party → Private party$1,111/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AHT ENGINEERING PLLC204/08/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
G & T CONSULTANT CORPGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AHT ENGINEERING PLLC8836204/08/2025
Building Lifecycle
All (22)Filed (2)Permit Issued (2)Signed Off (2)Violation (2)Objection (10)Special Inspection (4)
01/09/2026
Signed off — Alteration
LEGALIZATION WORK TO ADDRESS VIOLATION #39141839H. GC WORK TO RESTORE OPENING IN INTERIOR PARTY WALL PARTITION BETWEEN 61 LAKE STREET & 63 LAKE STREET TO EXISTING LEGAL CONDITIONS. NO DEMOLITION WORK PROPOSED. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01200494-I1
01/09/2026
Signed off — Alteration
INSTALLATION OF NEW AESTHETIC STUCCO FINISH OVER EXISTING BUILDING EXTERIOR. EXISTING THERMAL ENVELOPE TO REMAIN. REPLACEMENT OF FRONT STEPS. REPLACEMENT OF EXISTING FRONT WINDOW IN PLACE (NO NEW OPENING). NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01207819-I1
05/13/2025
Permit issued — General Construction
B01207819-I1-GC
05/12/2025
Objection resolved — Addressed
05/11/2025
Objection resolved — Addressed
05/09/2025
Objection raised — Scope
05/09/2025
Objection raised — Cost
05/02/2025
Objection resolved — Addressed
04/28/2025
Objection resolved — Addressed
04/17/2025
Objection resolved — Addressed
04/16/2025
Objection raised — Admin
04/16/2025
Objection raised — Zoning
04/16/2025
Objection raised — Scope
04/08/2025
Filed — Alteration
INSTALLATION OF NEW AESTHETIC STUCCO FINISH OVER EXISTING BUILDING EXTERIOR. EXISTING THERMAL ENVELOPE TO REMAIN. REPLACEMENT OF FRONT STEPS. REPLACEMENT OF EXISTING FRONT WINDOW IN PLACE (NO NEW OPENING). NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01207819-I1
04/08/2025
Special inspection requirement — Masonry
ABRAHAM TAWIL
04/08/2025
Special inspection requirement — Final
ABRAHAM TAWIL
04/08/2025
Special inspection requirement — Fenestration air leakage
ABRAHAM TAWIL
04/08/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
ABRAHAM TAWIL
04/07/2025
Permit issued — General Construction
B01200494-I1-GC
03/25/2025
Filed — Alteration
LEGALIZATION WORK TO ADDRESS VIOLATION #39141839H. GC WORK TO RESTORE OPENING IN INTERIOR PARTY WALL PARTITION BETWEEN 61 LAKE STREET & 63 LAKE STREET TO EXISTING LEGAL CONDITIONS. NO DEMOLITION WORK PROPOSED. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01200494-I1
03/17/2025
Violation issued (ECB, closed)
Unknown
03/17/2025
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offG T CONSULTANT05/13/2025
DOB NOWGeneral ConstructionSigned-offAHT ENGINEERING PLLC04/07/2025
1 project · most recent 04/04/2025
General Wiring
FiledStatusContractorScope
04/04/2025Permit IssuedKINGS ELECTRIC CO., INC.General Wiring
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
04/08/2025MasonryABRAHAM TAWILspecial
04/08/2025FinalABRAHAM TAWILprogress
04/08/2025Fenestration air leakageABRAHAM TAWILenergy_progress
04/08/2025Fenestration and door U-factor and product ratingsABRAHAM TAWILenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/22/2026B01200494-I1Request digital key ↗
08/22/2026B01207819-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026B01207819-I1Open ↗
08/28/2026B01207819-I1Open ↗
08/28/2026B01207819-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/22/2026B01200494-I1Open ↗
08/22/2026B01207819-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/28/2026B01207819-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026B01207819-I1Open ↗