610 EAST 181 STREET
BRONX · Tremont · BIN 2012033
💬 Discuss this project
1901Year Built
2Stories
A5Building Class
R7-1Zoning
1,352 sfGross Floor Area
1Units
One family attached or semi-detached · 2,186 sf lot · 0.62 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/17/2025$380K—— → —$281/sf building
05/31/2023$308K—Private party → JPMORGAN CHASE BANK, NATIONAL ASSOCIATION$228/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR108/26/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281108/26/2026
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Special Inspection (7)
09/03/2026
Permit issued — Solar
X01450176-I1-SL
08/26/2026
Filed — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP, RAILED, GRID-TIED, 7 MODULES, 2.87KW
X01450176-I1
08/26/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
08/26/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
08/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
08/26/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
08/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
08/24/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
08/24/2026
Special inspection requirement — Final
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR09/03/2026
2 projects · most recent 08/24/2026
General Wiring
FiledStatusContractorScope
08/24/2026Permit IssuedISLAND ELECTRIC CORP—
07/22/2025Permit IssuedB.D. ELECTRIC INCGeneral Wiring
1 project · most recent 08/26/2026
FiledStatusContractorScope
08/26/2026Permit IssuedMOMENTUM SOLAR14 panels, 5.74 kw, 123 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
08/26/2026Post-installed AnchorsMina Makarspecial
08/26/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
08/26/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
08/26/2026Air barrier - visual inspectionMina Makarenergy_progress
08/24/2026Fire-Resistant Penetrations and JointsMina Makarspecial
08/24/2026Energy Code Compliance InspectionsMina Makarprogress
08/24/2026FinalMina Makarprogress
▾Documents — 7 on file (BIS + DOB NOW)
▸Seals & Professional Certifications6
▸DOB NOWSpecial Inspector Seal & Signature3
09/23/2026X01450176-I1Open ↗
09/23/2026X01450176-I1Open ↗
09/23/2026X01450176-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026X01450176-I1Open ↗
09/23/2026X01450176-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
09/10/2026X01450176-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
09/10/2026X01450176-I1Open ↗