| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK CITY AQUARIUM | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KEVIN M. FINN, P.E., INC. | 2 | 06/27/2024 |
| LIZARDOS ENGINEERING | 4 | 05/16/2024 |
| THORNTON TOMASETTI | 4 | 06/26/2023 |
| TOHFAZ UDDIN PE PC | 1 | 05/23/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| RPO | 20 | 03/21/2026 |
| DIRECT ACCESS EXPEDITING, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ALMAR PLUMBING & HTG CORP | Plumbing | 11 | 07/08/2026 |
| COMMODORE CONSTRUCT CORP | General Contractor | 6 | 07/08/2026 |
| KING HOIST & SCAFFOLDING | General Contractor | 3 | 07/08/2026 |
| C. D. E. AIR-CONDITIONING | General Contractor | 3 | 07/08/2026 |
| TURNER CONSTRUCTION COMPANY | General Contractor | 3 | 07/08/2026 |
| JCC CONSTRUCTION CORP | General Contractor | 3 | 07/08/2026 |
| SEGRETI JOSEPH | Electrical | 1 | 03/21/2026 |
| JOSEPH SEGRETI | Electrical | 1 | 03/21/2026 |
| BIG SKY CONSTRUCTION CO | General Contractor | 1 | 08/18/2026 |
| BRENDAN LEIGH | Electrical | 1 | 03/21/2026 |
| MCCLEARY ELEC CONT INC 004737 | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 7 | 06/27/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | BIG SKY CONSTRUCTION CO | 08/17/2026 |
| DOB NOW | Structural | Permit Issued | TURNER CONSTRUCTION COMPANY | 05/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | C. D. E. AIR-CONDITIONING | 09/22/2025 |
| DOB NOW | Structural | Permit Issued | JCC CONSTRUCTION CORP | 06/06/2025 |
| DOB NOW | Structural | Permit Issued | TURNER CONSTRUCTION COMPANY | 05/28/2025 |
| DOB NOW | Structural | Permit Issued | JCC CONSTRUCTION CORP | 04/01/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | C. D. E. AIR-CONDITIONING | 10/21/2024 |
| DOB NOW | General Construction | Permit Issued | COMMODORE CONSTRUCT | 09/19/2024 |
| DOB NOW | General Construction | Signed-off | COMMODORE CONSTRUCT | 09/19/2024 |
| DOB NOW | Structural | Permit Issued | TURNER CONSTRUCTION COMPANY | 06/04/2024 |
| DOB NOW | Plumbing | Signed-off | ALMAR PLUMBING & HTG CORP | 03/06/2024 |
| DOB NOW | Plumbing | Signed-off | ALMAR PLUMBING & HTG CORP | 09/08/2023 |
| DOB NOW | General Construction | Permit Issued | COMMODORE CONSTRUCT | 09/06/2023 |
| DOB NOW | Structural | Signed-off | COMMODORE CONSTRUCT | 09/06/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | C. D. E. AIR-CONDITIONING | 08/31/2023 |
| DOB NOW | Construction Fence | Permit Issued | KING HOIST & SCAFFOLDING | 04/04/2019 |
| DOB NOW | Construction Fence | Permit Issued | KING HOIST & SCAFFOLDING | 01/11/2019 |
| DOB NOW | Construction Fence | Permit Issued | KING HOIST & SCAFFOLDING | 05/23/2018 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/27/2025 |
| BIS | MH | ISSUED | TURNER CONSTRUCTION COMPANY | 10/27/2025 |
| BIS | PL | ISSUED | ALMAR PLUMBING & HTG CORP | 09/15/2025 |
| BIS | PL | ISSUED | ALMAR PLUMBING & HTG CORP | 10/31/2024 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/23/2024 |
| BIS | MH | ISSUED | TURNER CONSTRUCTION COMPANY | 10/23/2024 |
| BIS | MH | ISSUED | TURNER CONSTRUCTION COMPANY | 10/09/2024 |
| BIS | PL | ISSUED | ALMAR PLBG&HTG CORP | 11/16/2023 |
| BIS | MH | RE-ISSUED | TURNER CONSTRUCTION COMPANY | 11/01/2023 |
| BIS | OT | RE-ISSUED | TURNER CONSTRUCTION COMPANY | 11/01/2023 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2022 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2022 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/24/2022 |
| BIS | PL | ISSUED | SHAW MECHANICAL INC | 01/19/2022 |
| BIS | PL | ISSUED | ALMAR PLBG&HTG CORP | 11/24/2021 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| BIS | MH | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 10/26/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/27/2024 | Permit Issued | BIG SKY CONSTRUCTION CO | Associated Ducts and Piping, Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/27/2024 | Signed-off | ALMAR PLUMBING & HTG CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/08/2026 | Permit Issued | HELLMAN ELECTRIC LLC | General Wiring |
| 10/05/2025 | Complete | MCCLEARY ELEC CONT INC | HVAC Wiring |
| 09/12/2023 | Permit Issued | HELLMAN ELECTRIC LLC | — |
| 10/26/2021 | Complete | ATLAS-ACON ELEC. SERVICE | Boiler Controls |
| 03/01/2021 | Complete | METROPOLIS ELECTRIC CORP | General Wiring |
| 02/28/2020 | Permit Issued | HY-LEE ELECTRIC CO., INC. | HVAC Wiring |
| 12/20/2019 | Permit Issued | NEWBRIDGE ELECTL CONTNG | — |
| 09/28/2018 | Permit Issued | R.C.M. ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/27/2024 | Permit Issued | BIG SKY CONSTRUCTION CO | Concrete |
| 06/26/2023 | Permit Issued | TURNER CONSTRUCTION COMPA | Steel |
| 06/22/2023 | Permit Issued | JCC CONSTRUCTION CORP | Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/10/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 06/08/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/03/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/12/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/28/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/18/2024 | Air barrier - visual inspection | GEORGE GHEBRYAL | energy_progress |
| 06/18/2024 | Interior lighting power | GEORGE GHEBRYAL | energy_progress |
| 06/18/2024 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 06/18/2024 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 06/18/2024 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 06/18/2024 | Subsurface Conditions – Fill Placement & In-Place Density | GEORGE GHEBRYAL | special |
| 06/18/2024 | Energy Code Compliance Inspections | GEORGE GHEBRYAL | progress |
| 06/18/2024 | Final | GEORGE GHEBRYAL | progress |
| 06/18/2024 | Exterior lighting power | GEORGE GHEBRYAL | energy_progress |
| 07/10/2023 | Lighting controls | GEORGE GHEBRYAL | energy_progress |
| 07/10/2023 | Interior lighting power | GEORGE GHEBRYAL | energy_progress |
| 06/29/2023 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 06/29/2023 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 06/29/2023 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 06/29/2023 | Final | GEORGE GHEBRYAL | progress |
| 06/29/2023 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 06/29/2023 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 06/29/2023 | Sprayed fire-resistant materials | GEORGE GHEBRYAL | special |
| 06/28/2023 | HVAC-R and service water piping design and insulation | GEORGE GHEBRYAL | energy_progress |
| 06/28/2023 | Maintenance information | GEORGE GHEBRYAL | energy_progress |
| 06/28/2023 | HVAC-R and service water heating system controls | GEORGE GHEBRYAL | energy_progress |
| 06/28/2023 | HVAC-R and service water heating equipment | GEORGE GHEBRYAL | energy_progress |
| 06/27/2023 | Mechanical Systems | GEORGE GHEBRYAL | special |
| 06/27/2023 | Final | GEORGE GHEBRYAL | progress |
| 06/12/2023 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |