| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/06/2022 | Signed-off | PROGETTO GROUP INC | Ventilation Systems | Ventilation N/A n/a 50 CFM · Exhaust Fan ×9 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/06/2022 | Signed-off | VILLAGE P & H NY INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/19/2021 | Complete | BROOKYLN SOLARWORKS, LLC | 2 meters |
| 10/03/2021 | Complete | GRAND ELECTRIC , INC. | General Wiring |
| 08/20/2021 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/06/2022 | Signed-off | VILLAGE P & H NY INC | Steel, Concrete |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/11/2015 | $880K | — | — → — | $346/sf building |
| 09/16/2014 | $725K | — | Private party → 613 QUINCY LLC | $285/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BERGEN STREET STUDIO FOR ARCHITECTU | 5 | 07/06/2022 |
| ROBERT SILMAN ASSOC STRUCT ENG DPC | 1 | 09/13/2021 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PROGETTO GROUP INC | General Contractor | 12 | 03/21/2026 |
| DAVID MILLER | Electrical | 6 | 03/21/2026 |
| VILLAGE P & H NY INC | Plumbing | 3 | 07/08/2026 |
| L&J PLG & HTG CO OF NY IN | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BERGEN STREET STUDIO FOR | 6988 | 5 | 07/06/2022 |
| CELIN MUNOZ CONSULTING EN | 1064 | 1 | 09/13/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 07/28/2022 |
| DOB NOW | Structural | Signed-off | PROGETTO GROUP INC | 02/15/2022 |
| DOB NOW | General Construction | Permit Issued | PROGETTO GROUP INC | 02/15/2022 |
| DOB NOW | Plumbing | Signed-off | L&J PLG & HTG CO OF NY IN | 10/15/2021 |
| DOB NOW | Structural | Signed-off | PROGETTO GROUP INC | 09/22/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | PROGETTO GROUP INC | 09/03/2021 |
| BIS | OT | ISSUED | BROOKLYN SOLARWORKS LLC | 07/14/2021 |
| BIS | PL | ISSUED | NEW YORK STANDARD MECH CORP | 10/19/2015 |
| BIS | OT | ISSUED | TALL BUILDERS LLC | 06/04/2015 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/28/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/20/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/11/2022 | No Access-Final CND-Occupancy Inspection | No Access | View ↗ |
| 07/29/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/29/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/30/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/11/2022 | Fire-Resistant Penetrations and Joints | David Miller | special |
| 07/11/2022 | Energy Code Compliance Inspections | David Miller | progress |
| 07/11/2022 | HVAC-R and service water piping design and insulation | David Miller | energy_progress |
| 07/06/2022 | HVAC-R and service water piping design and insulation | David Miller | energy_progress |
| 07/06/2022 | Energy Code Compliance Inspections | David Miller | progress |
| 07/06/2022 | Fire-Resistant Penetrations and Joints | David Miller | special |
| 07/05/2022 | Interior lighting power | David Miller | energy_progress |
| 07/05/2022 | Air barrier - visual inspection | David Miller | energy_progress |
| 07/05/2022 | Metering | David Miller | energy_progress |
| 07/05/2022 | Fire-Resistant Penetrations and Joints | David Miller | special |
| 07/05/2022 | Mechanical Systems | David Miller | special |
| 07/05/2022 | Energy Code Compliance Inspections | David Miller | progress |
| 07/05/2022 | Final | David Miller | progress |
| 07/05/2022 | Fenestration and door U-factor and product ratings | David Miller | energy_progress |
| 07/05/2022 | Permanent certificate | David Miller | energy_progress |
| 07/21/2021 | Structural Steel - High Strength Bolting | Celin Munoz | special |
| 07/21/2021 | Structural Steel - Welding | Celin Munoz | special |
| 07/21/2021 | Subgrade Inspections | Celin Munoz | special |
| 07/21/2021 | Subsurface Conditions – Fill Placement & In-Place Density | Celin Munoz | special |
| 07/21/2021 | Post-installed Anchors | Celin Munoz | special |
| 07/21/2021 | Final | Celin Munoz | progress |
| 07/21/2021 | Structural Steel - Details | Celin Munoz | special |
| 07/21/2021 | Concrete - Cast-In-Place | Celin Munoz | special |
| 07/21/2021 | Structural Stability – Alterations of existing buildings | Celin Munoz | special |
| 07/20/2021 | Fire-Resistant Penetrations and Joints | David Miller | special |