| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/08/2021 | $1.5M | — | Private party → Private party | $1,008/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SUNG HO SHIN ARCHITECT, PC | 6 | 02/21/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KATAN P & H INC | Plumbing | 10 | 07/08/2026 |
| NORTHBRIDGE CONTRACTING L | General Contractor | 4 | 07/08/2026 |
| KATAN P H | General Contractor | 2 | 03/22/2026 |
| A PLUS PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SUNG HO SHIN ARCHITECT | 2997 | 3 | 02/21/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | KATAN P & H INC | 11/27/2023 |
| DOB NOW | Plumbing | Signed-off | A PLUS PLUMBING CORP | 01/07/2022 |
| DOB NOW | Plumbing | Signed-off | KATAN P & H INC | 11/10/2021 |
| DOB NOW | General Construction | Signed-off | NORTHBRIDGE CONTRACTING L | 11/09/2021 |
| DOB NOW | Mechanical Systems | Signed-off | NORTHBRIDGE CONTRACTING L | 11/08/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/21/2024 | — | — | Air Conditioning Systems | Cooling Daikin 4MXL36TVJU 36,000 BTU · Condensing Unit ×2 FDXS09LVJU 9,000 BTU · Vrf Indoor ×2 CDXS18LVJU 18,000 BTU · Fan Coil Indoor ×1 FTXS09LVJU 9,000 BTU · Fan Coil Indoor ×1 FTXS18LVJU 18,000 BTU · Fan Coil Indoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/14/2022 | Complete | NELSON & TOM MAINT INC DB | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/28/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/24/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/16/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/23/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/13/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/25/2024 | Mechanical Systems | SUNG HO SHIN | special |
| 01/25/2024 | Final | SUNG HO SHIN | progress |
| 02/14/2023 | Air barrier - visual inspection | — | energy_progress |
| 02/14/2023 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 02/14/2023 | Fenestration areas | — | energy_progress |
| 02/14/2023 | Fenestration air leakage | — | energy_progress |
| 02/15/2022 | Fire-Resistant Penetrations and Joints | SUNG HO SHIN | special |
| 02/15/2022 | Mechanical Systems | SUNG HO SHIN | special |
| 02/15/2022 | Final | SUNG HO SHIN | progress |
| 02/15/2022 | Interior lighting power | SUNG HO SHIN | energy_progress |