City residence, one family
615 2 STREET
BROOKLYN · BIN 3025268
💬 Discuss this project
1908Year Built
3Stories
A4Building Class
R7BZoning
4,660 sfGross Floor Area
1Units
City residence, one family · 2,000 sf lot · 2.33 FAR built · Flood zone X
Locations of Work
Mechanical
Roof1p · 1 filing · 7 docs
Floor 21p · 1 filing · 7 docs
Floor 1
Basement1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ORSAR ENGINEERING208/01/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
J WITKIN CONSULTING403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ICE AGE MECHANICAL CORPGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ORSAR ENGINEERING PLLC8338108/01/2024
Building Lifecycle
All (24)Filed (2)Permit Issued (1)Signed Off (1)Objection (20)
02/11/2025
Signed off — Alteration
INSTALLATION OF NEW TOILET EXHAUST AND SUPPLY AIR DUCTWORK INCLUDING, FRESH AIR AS SHOWN ON PLANS. INSTALL A NEW PACKAGE WATER COOLED AC UNIT. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED UNDER THIS APPLICATION.
B01080551-I1
09/04/2024
Permit issued — Mechanical Systems
B01080551-I1-MS
08/14/2024
Objection resolved — Addressed
08/14/2024
Objection resolved — Addressed
08/14/2024
Objection resolved — Addressed
08/14/2024
Objection resolved — Addressed
08/09/2024
Objection resolved — Addressed
08/09/2024
Objection resolved — Addressed
08/09/2024
Objection resolved — Addressed
08/08/2024
Objection raised — Admin
08/08/2024
Objection raised — Energy
08/08/2024
Objection resolved — Addressed
08/08/2024
Objection raised — Other
08/08/2024
Objection raised — Scope
08/08/2024
Objection resolved — Addressed
08/08/2024
Objection raised — Energy
08/08/2024
Objection resolved — Addressed
08/08/2024
Objection raised — Fire_Protection
08/08/2024
Objection raised — Scope
08/08/2024
Objection raised — Inspections
08/08/2024
Objection raised — Inspections
08/08/2024
Objection raised — Scope
08/01/2024
Filed — Alteration
INSTALLATION OF NEW TOILET EXHAUST AND SUPPLY AIR DUCTWORK INCLUDING, FRESH AIR AS SHOWN ON PLANS. INSTALL A NEW PACKAGE WATER COOLED AC UNIT. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED UNDER THIS APPLICATION.
B01080551-I1
08/01/2024
Filed — Alteration
INSTALLATION OF NEW TOILET EXHAUST AND SUPPLY AIR DUCTWORK INCLUDING, FRESH AIR AS SHOWN ON PLANS. INSTALL A NEW PACKAGE WATER COOLED AC UNIT. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED UNDER THIS APPLICATION.
B01080551-S1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offICE AGE MECHANICAL CORP09/04/2024
BISOTISSUEDAMERICAN SOLAR PARTNERS,07/11/2017
1 project · most recent 08/01/2024
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/01/2024Signed-offICE AGE MECHANICAL CORPAir Conditioning Systems
Cooling
Mitsubishi Electric MITSUBISHI - MXZ-SM48NAMHZ 36,000 BTU · Condensing Unit ×2
MITSUBISHI - MXZ-SM60NAMHZ 48,000 BTU · Condensing Unit ×1
1 project · most recent 08/01/2024
Gas Water/Sanitary
FiledStatusContractorScope
08/01/2024——Gas, Water/Sanitary
Nothing on file for this building.
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/24/2026B01080551-S1Request digital key ↗
08/24/2026B01080551-I1Request digital key ↗
▸Applications & Permits4
▸DOB NOWLPC Approval/Permit2
08/13/2026B01080551-S1Open ↗
08/13/2026B01080551-I1Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/03/2017340503306Open ↗
▸BISWORK PERMIT APPLICATION1
07/11/2017340503306Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026B01080551-I1Open ↗
08/13/2026B01080551-S1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/03/2017340503306Open ↗
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
07/03/2017340503306Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
07/03/2017340503306Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/03/2017340503306Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/23/2018340503306Open ↗
07/03/2017340503306Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/23/2018340503306Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/03/2017340503306Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
07/27/2018340503306Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
07/23/2018340503306Open ↗
07/03/2017340503306Open ↗
▸Approvals, Objections & Sign-offs6
▸BISThird Party Electrical Signoff Compliance Report2
07/27/2018340503306Open ↗
07/23/2018340503306Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/23/2018340503306Open ↗
▸BISLANDMARKS APPROVAL1
07/03/2017340503306Open ↗
▸BISLANDMARKS SIGNOFF1
07/23/2018340503306Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
07/23/2018340503306Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
07/27/2018340503306Open ↗
07/03/2017340503306Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
07/03/2017340503306Open ↗
▸Other Documents1
▸DOB NOWProof of Historic Building1
08/13/2026B01080551-I1Open ↗