Church, synagogue, chapel
616 EAST 180TH STREET
BRONX · BIN 2012013
💬 Discuss this project
1931Year Built
2Stories
M1Building Class
R7-1Zoning
11,500 sfGross Floor Area
1Units
3 Active Violations 1 unresolved · 2 paperwork only 5 old, status unconfirmed ▸
Church, synagogue, chapel · Owner of record: Church of Pentecost USA · 7,365 sf lot · 1.56 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 2Church of Pentecost USA2 filings · 11 docs
Floor 1Church of Pentecost USA1 filing · 5 docs
MezzanineChurch of Pentecost USA1 filing · 5 docs
CellarChurch of Pentecost USA1 filing · 5 docs
Site & exteriorChurch of Pentecost USA7p · 3 filings · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Church of Pentecost Bethel2110/04/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/12/2016$910K—EN RESOURCES LLC → Church of Pentecost USA$79/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Rojas Engineering109/21/2026
Jim Kusi PE211/19/2025
Bangash Associates209/19/2024
Green Design105/03/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Dockery Associates403/21/2026
Sheikh Expediting403/21/2026
Atlantic Building Supply203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HI-Tech RestorationScaffold707/08/2026
Geo USA ConstructionScaffold403/21/2026
Mamc Consulting RepsScaffold407/08/2026
Jeco Electrical ServiceElectrical103/21/2026
Denali ElectricElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Jim Kusi, PE3757211/19/2025
Building Lifecycle
All (78)Filed (6)Permit Issued (7)Signed Off (2)Violation (55)Special Inspection (8)
09/21/2026
Filed — Alteration
Application being filed to install new awning above the main entry. No change in use, occupancy or egress.
X01319118-S1
08/13/2026
Special inspection requirement — Mechanical Systems
08/13/2026
Special inspection requirement — Final
11/19/2025
Filed — Alteration
Application being filed to install new awning above the main entry. No change in use, occupancy or egress.
X01319118-I1
11/18/2025
Special inspection requirement — Final
Jim Kusi
11/18/2025
Special inspection requirement — Post-installed Anchors
Jim Kusi
07/28/2025
Signed off — Alteration
X01113848-I1
07/28/2025
Signed off — Alteration
X01098480-I1
10/02/2024
Permit issued — Sidewalk Shed
X01113848-I1-SH
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/19/2024
Filed — Alteration
X01113848-I1
08/27/2024
Permit issued — Supported Scaffold
X01098480-I1-SF
08/23/2024
Filed — Alteration
X01098480-I1
06/26/2024
Violation issued (ECB, open)
Construction
06/26/2024
Violation issued (ECB, open)
Unknown
05/29/2024
Permit issued — Sidewalk Shed
X00161175-I1-SH
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/09/2023
Violation issued (ECB, closed)
Construction
05/09/2023
Violation issued (ECB, closed)
Construction
05/09/2023
Violation issued (ECB, closed)
Construction
05/09/2023
Violation issued (ECB, closed)
Construction
05/09/2023
Violation issued (ECB, closed)
Construction
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/14/2022
Violation issued (ECB, closed)
Construction
10/06/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/06/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/06/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/28/2022
Violation issued (ECB, closed)
Construction
05/24/2022
Violation issued (ECB, closed)
Construction
04/14/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/25/2021
Filed — Alteration
APPLICATION BEING FILED TO TEMPORARY BRACE 2ND FLOOR CONCRETE MASONRY WALL DURING CONSTRUCTION. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
X00443245-I1
12/28/2020
Special inspection requirement — Wood – Prefabricated I-Joists
Jim Kusi
12/28/2020
Special inspection requirement — Structural Stability – Alterations of existing buildings
Jim Kusi
12/28/2020
Special inspection requirement — Structural Cold-Formed Steel
Jim Kusi
12/23/2020
Permit issued — Sidewalk Shed
X00161175-I1-SH
12/21/2020
Permit issued — Sidewalk Shed
X00161175-I1-SH
12/21/2020
Special inspection requirement — Final
Jim Kusi
12/14/2020
Violation issued (ECB, closed)
Construction
12/14/2020
Violation issued (ECB, closed)
Construction
12/14/2020
Violation issued (ECB, closed)
Construction
12/14/2020
Violation issued (ECB, closed)
Construction
12/14/2020
Violation issued (ECB, closed)
Construction
12/14/2020
Violation issued (ECB, closed)
Construction
12/14/2020
Violation issued (ECB, closed)
Construction
11/02/2020
Permit issued — Sidewalk Shed
X00161175-I1-SH
01/17/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/10/2019
Permit issued — Sidewalk Shed
X00161175-I1-SH
07/10/2019
Violation issued (ECB, closed)
Construction
05/03/2019
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE.
X00161175-I1
03/03/2015
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
03/01/2013
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
12/13/2011
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
12/31/2009
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/03/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/19/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/06/2006
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offGeo USA Construction10/02/2024
DOB NOWSupported ScaffoldSigned-offGeo USA Construction08/27/2024
DOB NOWSidewalk ShedPermit IssuedMamc Consulting Reps05/29/2024
DOB NOWSidewalk ShedPermit IssuedMamc Consulting Reps12/23/2020
DOB NOWSidewalk ShedPermit IssuedHI-Tech Restoration12/21/2020
DOB NOWSidewalk ShedPermit IssuedHI-Tech Restoration11/02/2020
DOB NOWSidewalk ShedPermit IssuedHI-Tech Restoration07/10/2019
BIS—ISSUEDA.N.C. Contracting Co01/22/2026
BIS—ISSUEDA.N.C. Contracting Co06/04/2025
BISEQISSUEDA.N.C. Contracting Co05/23/2024
BIS—ISSUEDA.N.C. Contracting Co05/23/2024
BISSPISSUEDExpert Fire Sprinkler05/07/2024
BISEQISSUEDA.N.C. Contracting Co06/15/2023
BIS—ISSUEDA.N.C. Contracting Co03/23/2023
BIS—ISSUEDA.N.C. Contracting Co01/31/2023
BIS—ISSUEDMamc Consulting Reps12/02/2022
BIS—ISSUEDTemple Developers03/31/2022
BISEQISSUEDTemple Developers03/28/2022
BIS—ISSUEDTemple Developers10/14/2021
BIS—ISSUEDTemple Developers09/16/2021
BIS—ISSUEDTemple Developers11/25/2020
BISEQISSUEDTemple Developers11/25/2020
BISPLISSUEDAustin Plumbing & Heating Co06/21/2019
BIS—ISSUEDUniversal Design & Construction04/25/2019
BIS—ISSUEDUniversal Design & Construction04/16/2019
BISEQISSUEDUniversal Design & Construction10/30/2018
BISOTISSUEDMC General Contractors05/06/2005
BISOTISSUEDMC General Contractors08/09/2004
BISOTISSUEDMC General Contractors08/09/2004
BISOTISSUEDN/A01/12/1999
BISOTISSUEDNone06/26/1997
1 project · most recent 09/21/2026
Air Conditioning Systems Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/21/2026——Air Conditioning Systems, Heating and Air Conditioning Systems
Cooling
Trane MODEL # TEMG6AOC42H41SBA 4 tons · Ahu ×1
Heat / Cool
Gree MODEL # FLEXX60HP230V1BH 5 tons · Ahu ×9
MODEL # FLEXX60HP230V1BH 5 tons · Ahu ×4
Tosot MODEL # TU60-24WADU 5 tons · Condensing Unit ×10
Friedrich MODEL # WFPU18Z363C 3 tons · Condensing Unit ×2
Oxbox By Trane MODEL # J4AH4P36A1B00AA 3 tons · Ahu ×1
Trane MODEL # TEM6AOC42H41SB 4 tons · Ahu ×1
4 projects · most recent 10/17/2025
General Wiring
FiledStatusContractorScope
10/17/2025Permit IssuedDenali Electric—
03/12/2023Permit IssuedAttractive Lighting ElectricalGeneral Wiring
03/18/2020Permit IssuedMacintosh ElectricGeneral Wiring
05/03/2019Permit IssuedRichard Neu—
1 project · most recent 02/25/2021
FiledStatusContractorScope
02/25/2021——1 scope_items
1 project · most recent 05/03/2019
Sidewalk Shed
FiledStatusContractorScope
05/03/2019Permit IssuedMamc Consulting RepsSidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
08/13/2026Mechanical Systems—special
08/13/2026Final—progress
11/18/2025FinalJim Kusiprogress
11/18/2025Post-installed AnchorsJim Kusispecial
12/28/2020Wood – Prefabricated I-JoistsJim Kusispecial
12/28/2020Structural Stability – Alterations of existing buildingsJim Kusispecial
12/28/2020Structural Cold-Formed SteelJim Kusispecial
12/21/2020FinalJim Kusiprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Church of Pentecost USAReligiousEntire building
Project X01319118 Alteration · Approved · 11/19/2025
Project X01113848 Alteration · LOC Issued · 09/19/2024
Project X01098480 Alteration · LOC Issued · 08/23/2024
Project X00443245 Alteration · Approved · 02/25/2021
Project X00161175 Alteration · Permit Entire · 05/03/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 108 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch3
08/21/2026X01098480-I1Request digital key ↗
08/20/2026X01113848-I1Request digital key ↗
08/17/2026X01319118-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
08/25/2026X00443245-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/26/2026X00161175-I1Request digital key ↗
▸Applications & Permits30
▸BISWORK PERMIT APPLICATION18
05/31/2024220546210Open ↗
05/10/2024220600810Open ↗
03/27/2024220546210Open ↗
Showing 3 of 18 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION7
12/29/2025220546210Open ↗
05/17/2024220600810Open ↗
04/01/2022220546210Open ↗
Showing 3 of 7 on file for this type
▸BISPLACE OF ASSEMBLY4
09/05/2017220596282Open ↗
05/22/2017220596273Open ↗
05/22/2017220596282Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
12/29/2025220546210Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISZONING DIAGRAM1
08/09/2017220546210Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/08/2017220546210Open ↗
▸Seals & Professional Certifications21
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
09/18/2018220546210Open ↗
08/08/2017220546210Open ↗
08/08/2017220546210Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
10/04/2026X01319118-S1Open ↗
08/26/2026X00161175-I1Open ↗
08/21/2026X01098480-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/24/2026X00443245-I1Open ↗
08/24/2026X00443245-I1Open ↗
08/24/2026X00443245-I1Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
05/11/2017220596022Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/24/2026X00443245-I1Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
06/19/2017220600810Open ↗
08/30/2016220546210Open ↗
▸Safety & Tenant Protection2
▸BISTenant Protection Plan and Notes1
09/05/2017220600810Open ↗
▸BISSTREET TREE CHECKLIST1
09/14/2018220546210Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
08/08/2017220546210Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
10/04/2026X01319118-S1Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
08/08/2017220546210Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
09/18/2018220546210Open ↗
09/18/2018220546210Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
09/18/2018220546210Open ↗
09/18/2018220546210Open ↗
▸BISHYDRO FLOW TEST LETTER2
08/08/2017220546210Open ↗
06/19/2017220600810Open ↗
▸Approvals, Objections & Sign-offs16
▸BISSUPERSEDING LETTER6
03/27/2024220600810Open ↗
06/15/2023220546210Open ↗
01/31/2023220546210Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
10/04/2026X01319118-S1Open ↗
08/21/2026X01098480-I1Open ↗
08/13/2026X01319118-I1Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
06/19/2017220600829Open ↗
06/19/2017220600810Open ↗
08/30/2016220546210Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE2
08/08/2017220546210Open ↗
08/30/2016220546210Open ↗
▸Cost, Insurance & Ownership10
▸BISPROJECT-SPECIFIC GL INSURANCE6
05/31/2024220546210Open ↗
05/31/2024220546210Open ↗
04/01/2022220546210Open ↗
Showing 3 of 6 on file for this type
▸BISCOST AFFIDAVIT4
06/19/2017220600829Open ↗
06/19/2017220600810Open ↗
05/11/2017220596022Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms10
▸BISEFILING COVER SHEET4
06/19/2017220600829Open ↗
06/19/2017220600810Open ↗
05/11/2017220596022Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
03/27/2024220546210Open ↗
10/18/2021220546210Open ↗
11/05/2020220546210Open ↗
▸BISADDITIONAL INFORMATION3
12/29/2025220546210Open ↗
01/25/2021220546210Open ↗
01/25/2021220546210Open ↗
▸Other Documents1
▸BISPROOF OF FEE EXEMPTION1
11/30/2020220546210Open ↗