← Back
Hospital, sanitarium, mental institution
Georgian Building
617 WEST 168 STREET · Name © OpenStreetMap contributors · Washington Heights (South) · BIN 1063382
💬 Discuss this project
1931Year Built
7Stories
I1Building Class
R8Zoning
93,600 sfGross Floor Area
129Units
LL97 CoveredRent Stabilized37 Open Violations 36 unresolved · 1 paperwork only ▸FISP: SWARMPFDNY Report ↗
Hospital, sanitarium, mental institution · Owner of record: COLUMBIA UNIVERSITYIN THE CITY OF NEW YO RK TRUSTE · 18,000 sf lot · 5.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionEquipment
Permit Issued — active, not yet Signed-off
RoofUnder Construction10p · 2 filings · 6 docs
Cellar3p · 1 filing · 17 docs
Site & exteriorUnder Construction17p · 3 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HENRY RESTORATION LIMITED603/22/2026
ROCK GROUP NY203/21/2026
NEW YORK PRESBYTERIAN HOSPITAL203/21/2026
COLUMBIA UNIVERSITY203/21/2026
COLUMBIA UNIVERSITYIN THE CITY OF NEW YO RK TRUSTE103/22/2026
CUMC103/21/2026
PRESBYTERIAN HOSPITAL103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HOFFMANN ARCHITECTS, INC.210/07/2025
ALWAYS FAST SERVICES CORP209/16/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONVERSANO ASSOCIATES, INC.403/21/2026
PS ENGINEERS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ANDAMIO SCAFFOLDING LLCGeneral Contractor509/01/2026
GREGORY PAPANTONIOUElectrical103/21/2026
HEMSING, ROBERTElectrical103/21/2026
JEWNANDAN, RAJESHElectrical103/21/2026
JOHN KILGALLENElectrical103/21/2026
NOTO, CHARLESElectrical103/21/2026
SHORT, HENRYElectrical103/21/2026
A.T. ELECT'L CONSTR. CORPElectrical103/22/2026
HENRY RESTORATION LTDGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOCOTEC ENGINEERING4983210/07/2025
Building Lifecycle
All (103)Filed (6)Permit Issued (7)Signed Off (1)Facade (FISP) (15)Violation (60)Inspection (8)Special Inspection (6)
08/31/2026
Permit issued — Sidewalk Shed
M01282504-I1-SH
07/17/2026
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01286343-I1
01/06/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/22/2025
Permit issued — Suspended Scaffold
M01286993-I1-SC
10/29/2025
Permit issued — General Construction
M01210331-I1-GC
10/08/2025
Special inspection requirement — Post-installed Anchors
ALEXIS SCHLESSINGERMAN
10/08/2025
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
10/08/2025
Special inspection requirement — Final
Juan Kuriyama
10/07/2025
Filed — Alteration
Application filed for Facade repair at Georgian Residence LL11 Cycle 9 as per plans. No changes to egress or occupancy.
M01210331-P1
09/30/2025
Special inspection requirement — Post-installed Anchors
ALEXIS SCHLESSINGERMAN
09/30/2025
Special inspection requirement — Tenant Protection Plan Compliance
09/30/2025
Special inspection requirement — Final
Juan Kuriyama
09/29/2025
Permit issued — Suspended Scaffold
M01286993-I1-SC
09/26/2025
Permit issued — Suspended Scaffold
M01286991-I1-SC
09/22/2025
Filed — Alteration
M01286993-I1
09/22/2025
Filed — Alteration
FILE SUSPENDED SCAFFOLD OUTRIGGER SYSTEMS FOR FACADE RESTORATION AND INSPECTION
M01286991-I1
09/16/2025
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01286343-I1
09/16/2025
Permit issued — Supported Scaffold
M01286343-I1-SF
09/15/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/15/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
09/08/2025
Permit issued — Sidewalk Shed
M01282504-I1-SH
09/06/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01282504-I1
09/05/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/14/2025
Filed — Alteration
Application filed for Facade repair at Georgian Residence LL11 Cycle 9 as per plans. No changes to egress or occupancy.
M01210331-I1
04/17/2025
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
03/28/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/23/2025
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
01/13/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
07/11/2022
Cycle 9 facade report submitted
07/11/2022
Cycle 9 facade report signed — SWARMP
06/30/2022
Cycle 9 facade inspection completed
02/11/2022
Violation issued (ECB, closed)
Elevators
02/11/2022
Violation issued (ECB, closed)
Elevators
02/11/2022
Violation issued (ECB, closed)
Elevators
02/11/2022
Violation issued (ECB, closed)
Elevators
12/01/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/02/2021
Violation issued (HPD, closed)
A
04/02/2021
Violation issued (HPD, closed)
I
07/08/2019
Violation issued (ECB, closed)
Boilers
01/31/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/09/2019
Violation issued (ECB, closed)
Elevators
10/10/2018
Cycle 8 facade report submitted
10/07/2018
Cycle 8 facade report signed — SAFE
09/20/2018
Cycle 8 facade inspection completed
09/20/2018
Cycle 8 facade inspection completed
06/14/2018
Violation issued (HPD, open)
C
06/14/2018
Violation issued (HPD, open)
A
06/14/2018
Violation issued (HPD, open)
A
06/14/2018
Violation issued (HPD, open)
A
06/14/2018
Violation issued (HPD, open)
A
06/14/2018
Violation issued (HPD, open)
A
02/21/2018
Cycle 8 facade report submitted
01/26/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/26/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/26/2017
Violation issued (ECB, closed)
Construction
07/20/2017
Violation issued (ECB, closed)
Unknown
07/20/2017
Violation issued (ECB, closed)
Unknown
01/03/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/03/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/27/2016
Violation issued (HPD, closed)
I
Latest 60 of 103 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC08/31/2026
DOB NOWSuspended ScaffoldPermit IssuedHONEYBEE SERVICES INC12/22/2025
DOB NOWGeneral ConstructionPermit IssuedHENRY RESTORATION LTD10/29/2025
DOB NOWSuspended ScaffoldPermit IssuedHONEYBEE SERVICES INC09/29/2025
DOB NOWSuspended ScaffoldPermit IssuedHENRY RESTORATION LTD09/26/2025
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC09/16/2025
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC09/08/2025
BISOTISSUEDACC CONSTRUCTION CORP06/28/2018
BISMHISSUEDACC CONSTRUCTION CORP06/28/2018
BISOTISSUEDACC CONSTRUCTION CORP04/24/2018
BISMHISSUEDACC CONSTRUCTION CORP04/24/2018
BISOTISSUEDACC CONSTRUCTION CORP04/02/2018
BISMHISSUEDACC CONSTRUCTION CORP04/02/2018
BISOTISSUEDKAY WATERPROOFING CORP02/06/2018
BISEQISSUEDROCK GROUP NY CORP06/19/2017
BISOTISSUEDKAY WATERPROOFING CORP06/19/2017
BISOTISSUEDHELLMAN CONSTRUCTION CO05/13/2011
BISOTISSUEDINTERBORO SIGN & MAINTENANCE03/11/2008
BIS—ISSUEDINTERBORO SIGN & ELEC MAI03/11/2008
BIS—ISSUEDINTERBORO SIGN & ELEC MAI05/01/2007
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.04/27/2007
BISOTISSUEDAM&G WATERPROOFING LLC04/09/2007
BISEQISSUEDS & E MAITENANCE INC02/23/2007
3 projects · most recent 10/07/2025
General Wiring
FiledStatusContractorScope
10/07/2025Permit IssuedBOROWIDE ELECT'L CONTR'S—
02/10/2020Permit IssuedMHO'S ELECTRIC CORPGeneral Wiring
03/25/2018CompleteA.T. ELECT'L CONSTR. CORP—
2 projects · most recent 09/16/2025
Scaffold Sidewalk Shed
FiledStatusContractorScope
09/16/2025Signed-offANDAMIO SCAFFOLDING LLCScaffold
09/06/2025Permit IssuedANDAMIO SCAFFOLDING LLCSidewalk Shed
1 project · most recent 09/22/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
09/22/2025Permit IssuedHENRY RESTORATION LTDSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
01/06/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/15/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/15/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
09/05/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/17/2025Pass-Final PL - More than 10 Requested FloorsPassView ↗
03/28/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/23/2025Pass-Final PL - UndergroundPassView ↗
01/13/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
10/08/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
10/08/2025Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
10/08/2025FinalJuan Kuriyamaprogress
09/30/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
09/30/2025Tenant Protection Plan Compliance—special
09/30/2025FinalJuan Kuriyamaprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
NewYork-PresbyterianMedical / Healthcare—
Project M01363635 Alteration · Approved · 03/13/2026
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 122 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/21/2026M01282504-I1Request digital key ↗
08/21/2026M01286343-I1Request digital key ↗
08/21/2026M01286993-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits17
▸BISPLAN / WORK APPROVAL APPLICATION9
04/23/2025123119927Open ↗
11/09/2018123349723Open ↗
08/23/2017123349723Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION8
04/27/2018123119927Open ↗
04/27/2018123119927Open ↗
04/03/2018123119927Open ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications28
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION11
08/17/2018123035321Open ↗
08/09/2018140656813Open ↗
04/03/2018123119927Open ↗
Showing 3 of 11 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
08/23/2017123119927Open ↗
08/23/2017123119927Open ↗
06/18/2017140656813Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/21/2026M01286343-I1Open ↗
08/21/2026M01210331-P1Open ↗
08/21/2026M01210331-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
08/23/2017123119927Open ↗
03/29/2017123035321Open ↗
05/17/2011120690298Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026M01210331-P1Open ↗
08/23/2026M01210331-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/18/2017140656813Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
05/17/2011120690298Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/18/2017140656813Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026M01210331-I1Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING1
02/21/2013121532387Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
11/20/2020123349723Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
04/24/2025123119927Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
04/24/2025123119927Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
03/29/2017123035321Open ↗
▸Environmental & Asbestos6
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
05/17/2011120690298Open ↗
05/17/2011120690298Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/21/2026M01210331-I1Open ↗
08/21/2026M01210331-P1Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
08/17/2018123035321Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
04/03/2018123119927Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
08/17/2018123035321Open ↗
04/03/2018123119927Open ↗
08/23/2017123119927Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
04/25/2025123119927Open ↗
04/25/2025123119927Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/24/2025123119927Open ↗
▸BISTECHNICAL REPORT: ENERGY1
05/17/2011120690298Open ↗
▸BIS* HVAC INSULATION AND SEALING1
04/24/2025123119927Open ↗
▸BISLIGHTING CONTROLS1
04/24/2025123119927Open ↗
▸BISTR8: Energy Code Progress Inspections1
05/18/2011120690298Open ↗
▸BISINTERIOR LIGHTING POWER1
04/24/2025123119927Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
08/17/2018123035321Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
06/18/2017140656813Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY5
04/25/2025123119927Open ↗
04/25/2025123119927Open ↗
04/25/2025123119927Open ↗
Showing 3 of 5 on file for this type
▸BISFIRE-RESISTIVE RATED CONSTRUCTION2
04/24/2025123119927Open ↗
04/24/2025123119927Open ↗
▸BISMECHANICAL SYSTEMS1
04/24/2025123119927Open ↗
▸Approvals, Objections & Sign-offs14
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/15/2026M00365553-I1Open ↗
08/13/2026M01363635-S1Open ↗
08/13/2026M01210331-I1Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
04/30/2025123119927Open ↗
08/17/2018123035321Open ↗
08/09/2018140656813Open ↗
▸BISFINAL1
04/24/2025123119927Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
05/17/2011120690298Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/23/2017123349723Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT7
08/17/2018123035321Open ↗
08/23/2017123349723Open ↗
08/23/2017123119927Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
04/24/2025123119927Open ↗
04/14/2025123349723Open ↗
▸Filing & Intake Forms8
▸BISEFILING COVER SHEET5
08/23/2017123349723Open ↗
08/23/2017123119927Open ↗
08/23/2017123119927Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM2
08/17/2018123035321Open ↗
08/09/2018140656813Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/18/2017140656813Open ↗
▸Other Documents7
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
06/26/2017123035321Open ↗
03/21/2017123035321Open ↗
▸DOB NOWCalculations2
08/13/2026M01286993-I1Open ↗
08/13/2026M01286991-I1Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026M01286993-I1Open ↗
08/13/2026M01286991-I1Open ↗
▸BISMAINTENANCE INFORMATION1