| Owner | Filings | Most Recent |
|---|---|---|
| ELLI | 60 | 07/08/2026 |
| HAWK CONTRACTING OF NY IN | 1 | 03/22/2026 |
| DLM CONTRACTORS | 2 | 03/22/2026 |
| 6247 REALTY | 2 | 03/21/2026 |
| ELLI NY DESIGN | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NODE ARCHITECTURE,ENGINEERING, CONS | 19 | 06/17/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| NODE ENGINEERING CONSULTING | 18 | 03/21/2026 |
| NODE ARCHITECTURE,ENGINEERING,CON | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DLM CONTRACTORS INC | General Contractor | 14 | 07/08/2026 |
| CARPEX INC | General Contractor | 3 | 03/21/2026 |
| HAWK CONTRACTING OF NY IN | General Contractor | 1 | 04/09/2026 |
| MRM PROPERTY GROUP INC | General Contractor | 1 | 04/09/2026 |
| MASTER 2 PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| HAWK. AA LLC | General Contractor | 1 | 07/08/2026 |
| MASTER PLBG AND HTG INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NODE ARCHITECTURE,ENGINEE | 6799 | 16 | 06/17/2026 |
| INTERNATIONAL GEOTEHCNICA | 1795 | 13 | 01/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | MRM PROPERTY GROUP INC | 01/12/2026 |
| DOB NOW | General Construction | Permit Issued | DLM CONTRACTORS | 08/01/2025 |
| DOB NOW | Construction Fence | Signed-off | DLM CONTRACTORS | 07/30/2025 |
| DOB NOW | Sprinklers | Signed-off | MASTER PLBG AND HTG INC | 04/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CARPEX INC | 04/11/2025 |
| DOB NOW | Plumbing | Signed-off | MASTER 2 PLBG & HTG INC | 04/08/2025 |
| DOB NOW | General Construction | Permit Issued | DLM CONTRACTORS | 02/07/2025 |
| DOB NOW | Construction Fence | Signed-off | DLM CONTRACTORS | 01/30/2025 |
| DOB NOW | Construction Fence | Signed-off | DLM CONTRACTORS | 07/30/2024 |
| DOB NOW | General Construction | Permit Issued | DLM CONTRACTORS | 07/29/2024 |
| DOB NOW | Structural | Signed-off | DLM CONTRACTORS | 02/16/2024 |
| DOB NOW | Construction Fence | Signed-off | DLM CONTRACTORS | 02/16/2024 |
| DOB NOW | General Construction | Permit Issued | DLM CONTRACTORS | 02/16/2024 |
| DOB NOW | General Construction | Permit Issued | DLM CONTRACTORS | 10/24/2023 |
| DOB NOW | Structural | Signed-off | DLM CONTRACTORS | 09/14/2023 |
| DOB NOW | Construction Fence | Signed-off | DLM CONTRACTORS | 07/10/2023 |
| DOB NOW | Earth Work | Signed-off | DLM CONTRACTORS | 07/07/2023 |
| DOB NOW | Construction Fence | Signed-off | HAWK. AA LLC | 11/11/2022 |
| DOB NOW | Construction Fence | Signed-off | HAWK CONTRACTING OF NY IN | 07/09/2021 |
| BIS | — | ISSUED | HAWK CONTRACTING OF NY IN | 08/18/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/17/2026 | Signed-off | MRM PROPERTY GROUP INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MSZ-FS06NA-U1 6,000 BTU · Fan Coil Indoor ×22 MSZ-FS09NA 9,000 BTU · Fan Coil Indoor ×7 MXZ-4C36NA3 35,400 BTU · Condensing Unit ×5 MXZ-3C24NA3 22,000 BTU · Condensing Unit ×3 MSZ-FS12NA 12,000 BTU · Fan Coil Indoor ×1 Ventilation Panasonic FV-0511VKS2 1 kW · Exhaust Fan ×13 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/23/2025 | Signed-off | MASTER PLBG AND HTG INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | MRM PROPERTY GROUP INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/23/2025 | Signed-off | DLM CONTRACTORS INC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | MRM PROPERTY GROUP INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/14/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/13/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/24/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/20/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/19/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 09/30/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/25/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/25/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/29/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/15/2026 | Protection of exposed foundation insulation | Radomir Delic | energy_progress |
| 07/15/2026 | Lighting controls | Radomir Delic | energy_progress |
| 07/15/2026 | Exterior lighting power | Radomir Delic | energy_progress |
| 07/15/2026 | Lighting in dwelling units | Radomir Delic | energy_progress |
| 07/15/2026 | Permanent certificate | Radomir Delic | energy_progress |
| 07/15/2026 | Energy Code Compliance Inspections | Radomir Delic | progress |
| 07/15/2026 | Fire-Resistance Rated Construction | Radomir Delic | progress |
| 07/15/2026 | Fire-Resistant Penetrations and Joints | Radomir Delic | special |
| 07/15/2026 | HVAC-R and service water heating equipment | Radomir Delic | energy_progress |
| 07/15/2026 | Interior lighting power | Radomir Delic | energy_progress |
| 07/15/2026 | HVAC-R and service water heating system controls | Radomir Delic | energy_progress |
| 07/15/2026 | Electric vehicle service equipment requirements | Radomir Delic | energy_progress |
| 07/15/2026 | Maintenance information | Radomir Delic | energy_progress |
| 07/15/2026 | Fenestration air leakage | Radomir Delic | energy_progress |
| 07/15/2026 | Air barrier — testing | Radomir Delic | energy_progress |
| 07/15/2026 | HVAC-R and service water piping design and insulation | Radomir Delic | energy_progress |
| 07/15/2026 | Air barrier - visual inspection | Radomir Delic | energy_progress |
| 07/15/2026 | Fenestration areas | Radomir Delic | energy_progress |
| 07/15/2026 | Duct leakage testing, insulation and design | Radomir Delic | energy_progress |
| 07/15/2026 | Fenestration and door U-factor and product ratings | Radomir Delic | energy_progress |
| 07/15/2026 | Metering | Radomir Delic | energy_progress |
| 07/15/2026 | Insulation placement and R values | Radomir Delic | energy_progress |
| 05/08/2026 | Duct leakage testing, insulation and design | Radomir Delic | energy_progress |
| 05/08/2026 | HVAC-R and service water heating equipment | Radomir Delic | energy_progress |
| 05/08/2026 | Interior lighting power | Radomir Delic | energy_progress |