| Owner | Filings | Most Recent |
|---|---|---|
| TERRA PRETA ARCHITECTS | 3 | 03/22/2026 |
| EMPIRE CONTRACTING OF NY | 2 | 03/22/2026 |
| SKYWORX CONTRACTING | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TERRA PRETA ARCHITECTS | 1 | 03/05/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| DESIGN CONCEPTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MAXIMUM CONTRACTING INC | General Contractor | 3 | 03/21/2026 |
| IRVING BAPTISTE | Electrical | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | MAXIMUM CONTRACTING INC | 05/08/2025 |
| BIS | MH | ISSUED | BEYOND BUILDING INC | 10/31/2018 |
| BIS | OT | ISSUED | EMPIRE CONTRACTING OF NY | 07/22/2014 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 07/16/2014 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 06/30/2014 |
| BIS | PL | ISSUED | ATTACK PLUMBING INC | 10/03/2012 |
| BIS | BL | ISSUED | ATTACK PLUMBING INC | 08/17/2011 |
| BIS | PL | ISSUED | ATTACK PLUMBING INC | 08/17/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2018 | Permit Issued | W 8 ELECTRIC CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/04/2025 | Final | George Turner | progress |
| 03/04/2025 | Energy Code Compliance Inspections | George Turner | progress |
| 03/04/2025 | Fire-Resistance Rated Construction | George Turner | progress |
| 03/04/2025 | Preliminary | George Turner | progress |