| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2021 | Complete | R & T ELECTRICAL CORP | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| HUAN DESIGN INC. | 6 | 07/12/2021 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SHUN SHENG CONSTRUCTION | General Contractor | 5 | 07/08/2026 |
| TT&T CONSTRUCTION INC | General Contractor | 2 | 03/21/2026 |
| R & T ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HUAN DESIGN INC | 7669 | 7 | 07/12/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | SHUN SHENG CONSTRUCTION | 04/30/2021 |
| DOB NOW | General Construction | Signed-off | TT&T CONSTRUCTION INC | 04/16/2021 |
| DOB NOW | General Construction | Signed-off | SHUN SHENG CONSTRUCTION | 03/05/2021 |
| DOB NOW | General Construction | Signed-off | SHUN SHENG CONSTRUCTION | 01/22/2021 |
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 01/21/2021 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/15/2021 | Fenestration areas | ZHENHUAN XU | energy_progress |
| 08/15/2021 | Fire-Resistant Penetrations and Joints | ZHENHUAN XU | special |
| 08/15/2021 | Concrete - Cast-In-Place | ZHENHUAN XU | special |
| 08/15/2021 | Fire-Resistance Rated Construction | ZHENHUAN XU | progress |
| 08/15/2021 | Final | ZHENHUAN XU | progress |
| 08/15/2021 | Energy Code Compliance Inspections | ZHENHUAN XU | progress |
| 08/15/2021 | Air barrier - visual inspection | ZHENHUAN XU | energy_progress |
| 08/15/2021 | Lighting in dwelling units | ZHENHUAN XU | energy_progress |
| 08/15/2021 | Fenestration and door U-factor and product ratings | ZHENHUAN XU | energy_progress |
| 08/15/2021 | Insulation placement and R values | ZHENHUAN XU | energy_progress |
| 08/15/2021 | Fenestration air leakage | ZHENHUAN XU | energy_progress |
| 04/28/2021 | Energy Code Compliance Inspections | ZHENHUAN XU | progress |
| 04/28/2021 | Energy Code Compliance | ZHENHUAN XU | progress |
| 04/28/2021 | Final | ZHENHUAN XU | progress |
| 04/28/2021 | Maintenance information | ZHENHUAN XU | energy_progress |
| 04/28/2021 | HVAC and service water heating equipment | ZHENHUAN XU | energy_progress |
| 04/28/2021 | HVAC and service water heating system controls | ZHENHUAN XU | energy_progress |
| 04/28/2021 | Fire-Resistant Penetrations and Joints | ZHENHUAN XU | special |
| 04/28/2021 | High Temperature Hot Water Piping (Welding) | ZHENHUAN XU | special |
| 04/28/2021 | HVAC insulation and sealing | ZHENHUAN XU | energy_progress |
| 04/22/2021 | Maintenance information | ZHENHUAN XU | energy_progress |
| 04/22/2021 | Fire-Resistant Penetrations and Joints | ZHENHUAN XU | special |
| 04/22/2021 | High Temperature Hot Water Piping (Welding) | ZHENHUAN XU | special |
| 04/22/2021 | Energy Code Compliance | ZHENHUAN XU | progress |
| 04/22/2021 | Energy Code Compliance Inspections | ZHENHUAN XU | progress |