| Owner | Filings | Most Recent |
|---|---|---|
| YUCO MANAGEMENT | 78 | 07/08/2026 |
| MOKLAM ENTERPRISES IN | 143 | 03/22/2026 |
| FIONUCCI INC | 1 | 03/22/2026 |
| F;PRICCO INC | 1 | 03/22/2026 |
| OWNER OF 622BROADWAY | 3 | 03/22/2026 |
| LIKA CONSTRUCTION | 1 | 03/22/2026 |
| FATHER BRADS BWAY INC | 1 | 03/22/2026 |
| MOLKAN ENTERPRISES | 1 | 03/22/2026 |
| YUCO BUILDERS, LLC | 1 | 03/21/2026 |
| COLGATE ENTERPRISES | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DESIGN REPUBLIC | 3 | 04/16/2026 |
| SEVERUD ASSOCIATES | 1 | 10/23/2025 |
| HNY CONSULTING ENGINEERS LLC | 12 | 02/25/2025 |
| PIRO STUDIO LLC | 2 | 08/09/2021 |
| LOREN E CANNON ARCHITECT | 1 | 02/06/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| EMPIRE CITY CONSULTANTS, INC. | 15 | 03/21/2026 |
| LILY L | 2 | 03/21/2026 |
| MBE CODE & ZONING LLC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 18 | 07/08/2026 |
| BP MECHANICAL CORP | General Contractor | 3 | 07/08/2026 |
| FULL CAPACITY FIRE CORP | Fire Protection | 2 | 07/08/2026 |
| SPENELLI, RICHARD | Electrical | 1 | 03/21/2026 |
| YUCO BUILDERS, LLC | General Contractor | 1 | 07/08/2026 |
| DICAPUA, JOHN | Electrical | 1 | 03/21/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| JOHN DICAPUA | Electrical | 1 | 03/21/2026 |
| RAMDATH, JAIDATH | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SOCOTEC ENGINEERING | 4983 | 2 | 10/23/2025 |
| AK ENGINEERING PC | 678 | 12 | 02/25/2025 |
| PIRO STUDIO LLC | 7503 | 2 | 08/09/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/24/2025 |
| DOB NOW | Structural | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/24/2025 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/24/2025 |
| DOB NOW | Structural | Signed-off | SPK/LEWIS CONSTRUCTION LL | 10/24/2025 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 10/24/2025 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 10/22/2025 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 06/09/2025 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 06/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/25/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/30/2021 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 10/19/2021 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 10/18/2021 |
| DOB NOW | Mechanical Systems | Signed-off | BP MECHANICAL CORP | 08/17/2021 |
| DOB NOW | Mechanical Systems | Signed-off | BP MECHANICAL CORP | 04/21/2021 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/27/2020 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 10/05/2020 |
| DOB NOW | Construction Fence | Permit Issued | YUCO BUILDERS, LLC | 02/07/2019 |
| BIS | OT | ISSUED | SPK/LEWIS CONSTRUCTION LL | 11/23/2022 |
| BIS | OT | ISSUED | SPK/LEWIS CONSTRUCTION LL | 11/30/2021 |
| BIS | OT | ISSUED | SPK/LEWIS CONSTRUCTION LL | 11/25/2020 |
| BIS | OT | ISSUED | SPK/LEWIS CONSTRUCTION LL | 10/02/2020 |
| BIS | OT | ISSUED | SPK/LEWIS CONSTRUCTION LL | 11/27/2019 |
| BIS | OT | ISSUED | SPK/LEWIS CONSTRUCTION LL | 10/11/2019 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 07/09/2019 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 01/10/2019 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 10/01/2018 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 10/01/2018 |
| BIS | MH | ISSUED | DONNELLY MECHANICAL CORP | 06/13/2018 |
| BIS | OT | ISSUED | DONNELLY MECHANICAL CORP | 06/13/2018 |
| BIS | MH | ISSUED | DONNELLY MECHANICAL CORP | 05/07/2018 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 07/20/2017 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 07/19/2017 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 09/29/2016 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 08/05/2016 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 10/26/2015 |
| BIS | OT | ISSUED | DECKER DESIGN LTD | 06/08/2015 |
| BIS | MH | ISSUED | DECKER DESIGN LTD | 06/08/2015 |
| BIS | OT | ISSUED | YUCO BUILDERS, LLC | 05/20/2015 |
| BIS | MH | ISSUED | DECKER DESIGN LTD | 03/09/2015 |
| BIS | OT | ISSUED | DECKER DESIGN LTD | 03/04/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/10/2026 | Permit Issued | A.S.K. ELECTRICAL CORP | General Wiring |
| 01/22/2025 | Complete | DENALI ELECTRIC CORP | — |
| 07/31/2023 | Complete | A.S.K. ELECTRICAL CORP | General Wiring |
| 03/17/2023 | Complete | A.S.K. ELECTRICAL CORP | General Wiring |
| 01/19/2023 | Complete | A.S.K. ELECTRICAL CORP | General Wiring |
| 01/18/2023 | Complete | A.S.K. ELECTRICAL CORP | — |
| 12/03/2019 | Complete | JUMPER ELECTRIC CORP | General Wiring |
| 12/11/2017 | Complete | METROPOLIS ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/16/2026 | Signed-off | SPK/LEWIS CONSTRUCTION LL | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/19/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/19/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/25/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/25/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/15/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/04/2026 | Fire-Resistance Rated Construction | ALEXIS SCHLESSINGERMAN | progress |
| 02/04/2026 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 09/23/2025 | Energy Code Compliance Inspections | ALEXIS SCHLESSINGERMAN | progress |
| 09/17/2025 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 09/17/2025 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 06/12/2025 | Structural Steel - Details | ALEXIS SCHLESSINGERMAN | special |
| 06/12/2025 | Structural Stability – Alterations of existing buildings | ALEXIS SCHLESSINGERMAN | special |
| 12/05/2024 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 06/29/2023 | Sprinkler Systems | Ari Kamo | special |
| 06/29/2023 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 06/29/2023 | Mechanical Systems | Ari Kamo | special |
| 06/29/2023 | Final | Ari Kamo | progress |
| 06/29/2023 | HVAC insulation and sealing | Ari Kamo | energy_progress |
| 06/28/2023 | Mechanical Systems | Ari Kamo | special |
| 06/28/2023 | Final | Ari Kamo | progress |
| 06/28/2023 | HVAC insulation and sealing | Ari Kamo | energy_progress |
| 06/28/2023 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 06/27/2023 | Sprinkler Systems | Ari Kamo | special |
| 02/15/2022 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 12/22/2021 | Sprinkler Systems | Ari Kamo | special |
| 12/22/2021 | Mechanical Systems | Ari Kamo | special |
| 12/22/2021 | Final | Ari Kamo | progress |
| 12/22/2021 | HVAC insulation and sealing | Ari Kamo | energy_progress |
| 12/22/2021 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 12/22/2021 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Rockstar Games | Office | Floors 3–6 | Project M00432579 Project M00419435 Project M00366847 Project M00366866 |