| Owner | Filings | Most Recent |
|---|---|---|
| DASNY | 75 | 09/13/2026 |
| CUNY | 1 | 09/13/2026 |
| SHAH GROUP ENTERPRISES | 6 | 03/21/2026 |
| CUNY DEPT OF DESIGN CONSTRUCT | 10 | 03/21/2026 |
| DORMITORY AUTHORITY-STATE OF NY | 22 | 03/21/2026 |
| DOMITORY AUTHORITY STATE OF NY | 2 | 03/21/2026 |
| DORMITORY AUTHORITY OF THE STATE | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| A&J CONSULTING ENGINEERING SERVICES | 2 | 07/30/2026 |
| FIRMITAS ENGR'G & STRC'T DSG'N PLLC | 1 | 07/20/2026 |
| GRAF & LEWENT ARCHITECTS, LLP | 1 | 07/14/2026 |
| SETTY | 10 | 07/08/2026 |
| WILLDAN ENERGY SOLUTIONS | 6 | 01/16/2026 |
| AHUJA PARTNERSHIP ARCHITECTS | 3 | 07/07/2025 |
| IAQ SYSTEMS INC | 1 | 05/27/2025 |
| MICHIELLI & WYETZNER ARCHITECTS | 1 | 05/22/2025 |
| GENESYS ENGINEERING | 9 | 02/18/2025 |
| JOSEPH J. ALIOTTA, AIA | 2 | 12/06/2024 |
| SILMAN | 1 | 10/22/2024 |
| ROBERT SILMAN ASSOCIATES | 1 | 09/27/2022 |
| HOWARD I SHAPIRO & ASSOCIATES | 1 | 09/29/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CONSTRUCTION PERMIT SERVICES | 4 | 03/21/2026 |
| J CALLAHAN CONSULTING | 22 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 20 | 03/21/2026 |
| HOWARD I SHAPIRO ASSOCIATES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MARIC MECHANICAL INC | General Contractor | 16 | 07/08/2026 |
| CAULDWELL WINGATE CO LLC | General Contractor | 4 | 07/08/2026 |
| NEW STYLE CONTRACTORS INC | General Contractor | 4 | 07/08/2026 |
| EASTERN PLBG & MECH CONTR | Plumbing | 3 | 07/08/2026 |
| TRISTATE PLBG SVCS CORP | Plumbing | 2 | 06/28/2026 |
| GEOMATRIX SERVICES INC | General Contractor | 2 | 03/21/2026 |
| CARDOZA PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| SPADARO, JERRY | Electrical | 1 | 03/21/2026 |
| KANE, PAPA | Electrical | 1 | 03/21/2026 |
| SIRINA FIRE PROT | General Contractor | 1 | 04/09/2026 |
| INTERBORO PLBG & HTG CORP | Electrical | 1 | 03/21/2026 |
| JEMCO ELECT. CONTRS INC | Electrical | 1 | 03/22/2026 |
| I.M.P. PLBG. & HTG. CORP | Plumbing | 1 | 07/08/2026 |
| JEMCO ELECTRICAL CONT INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 22 | 07/08/2026 |
| FUTURE TECH CONSULTANTS O | 589 | 7 | 01/16/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | CAULDWELL WINGATE CO LLC | 02/18/2026 |
| DOB NOW | General Construction | Signed-off | CAULDWELL WINGATE CO LLC | 02/18/2026 |
| DOB NOW | Plumbing | Signed-off | TRISTATE PLBG SVCS CORP | 02/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | MARIC MECHANICAL INC | 04/08/2025 |
| DOB NOW | General Construction | Signed-off | MARIC MECHANICAL INC | 03/19/2025 |
| DOB NOW | General Construction | Signed-off | CAULDWELL WINGATE CO LLC | 02/05/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | CAULDWELL WINGATE CO LLC | 02/05/2025 |
| DOB NOW | Plumbing | Signed-off | TRISTATE PLBG SVCS CORP | 02/04/2025 |
| DOB NOW | Structural | Permit Issued | MARIC MECHANICAL INC | 01/09/2025 |
| DOB NOW | General Construction | Signed-off | MARIC MECHANICAL INC | 01/08/2025 |
| DOB NOW | Plumbing | Signed-off | EASTERN PLBG & MECH CONTR | 07/12/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | MARIC MECHANICAL INC | 03/26/2024 |
| DOB NOW | General Construction | Signed-off | MARIC MECHANICAL INC | 03/26/2024 |
| DOB NOW | General Construction | Signed-off | MARIC MECHANICAL INC | 05/19/2023 |
| DOB NOW | General Construction | Signed-off | MARIC MECHANICAL INC | 05/19/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | MARIC MECHANICAL INC | 05/19/2023 |
| DOB NOW | Plumbing | Permit Issued | I.M.P. PLBG. & HTG. CORP | 01/12/2023 |
| DOB NOW | Structural | Permit Issued | MARIC MECHANICAL INC | 12/07/2022 |
| DOB NOW | General Construction | Signed-off | MARIC MECHANICAL INC | 12/07/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | MARIC MECHANICAL INC | 11/18/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | NEW STYLE CONTRACTORS INC | 08/08/2022 |
| DOB NOW | Plumbing | Signed-off | EASTERN PLBG & MECH CONTR | 07/20/2022 |
| DOB NOW | Supported Scaffold | Signed-off | NEW STYLE CONTRACTORS INC | 09/30/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | NEW STYLE CONTRACTORS INC | 08/26/2021 |
| DOB NOW | Plumbing | Signed-off | EASTERN PLBG & MECH CONTR | 07/15/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | NEW STYLE CONTRACTORS INC | 06/30/2021 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING CORP | 02/03/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GEOMATRIX SERVICES | 01/07/2021 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING CORP | 01/22/2020 |
| DOB NOW | Mechanical Systems | Signed-off | JEMCO ELECTRICAL CONT | 01/14/2020 |
| BIS | OT | ISSUED | NEW STYLE CONTRACTORS INC | 08/12/2022 |
| BIS | OT | ISSUED | NEW STYLE CONTRACTORS INC | 08/09/2022 |
| BIS | OT | ISSUED | NEW STYLE CONTRACTORS INC | 08/23/2021 |
| BIS | OT | ISSUED | NEW STYLE CONTRACTORS INC | 08/23/2021 |
| BIS | OT | ISSUED | GEOMATRIX SERVICES INC | 07/23/2021 |
| BIS | OT | ISSUED | GEOMATRIX SERVICES INC | 07/23/2021 |
| BIS | OT | ISSUED | NEW STYLE CONTRACTORS INC | 06/29/2021 |
| BIS | OT | ISSUED | NEW STYLE CONTRACTORS INC | 06/29/2021 |
| BIS | OT | ISSUED | GEOMATRIX SERVICES INC | 10/30/2020 |
| BIS | OT | ISSUED | GEOMATRIX SERVICES INC | 10/30/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/30/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool Trane MAKE: TRANE, MODEL # HORIZON(OAD/NREV6-OADG/OANG) 146,300 BTU · Rooftop Unit ×2 MAKE: TRANE, MODEL # HORZION(OAD/NREV6-OADG/OANG) 380,700 BTU · Rooftop Unit ×1 |
| 01/16/2026 | Permit Issued | NEW STYLE CONTRACTORS INC | Air Conditioning Systems, Heating Systems | Cooling Heating Mitsubishi Electric RCAUC80-1 700 CFM · Heat Pump Outdoor ×3 |
| 09/23/2025 | Permit Issued | CAULDWELL WINGATE CO LLC | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems | |
| 09/10/2025 | Permit Issued | MARIC MECHANICAL INC | Associated Ducts and Piping | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/06/2024 | — | — | 18 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/30/2026 | — | — | Gas, Water/Sanitary |
| 07/08/2026 | Signed-off | TRISTATE PLBG SVCS CORP | Gas, Water/Sanitary |
| 05/27/2025 | — | — | Water/Sanitary |
| 02/18/2025 | Permit Issued | I.M.P. PLBG. & HTG. CORP | Water/Sanitary |
| 04/22/2022 | Signed-off | EASTERN PLBG & MECH CONTR | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/27/2025 | Complete | TRIBECA ELECTRICAL CORP | General Wiring |
| 07/06/2021 | Permit Issued | J.H. ELEC. OF NEW YORK IN | General Wiring |
| 01/15/2020 | Complete | JEMCO ELECT. CONTRS INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/30/2026 | — | — | Concrete |
| 10/22/2024 | Permit Issued | MARIC MECHANICAL INC | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/31/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/20/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/24/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 10/24/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/07/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/29/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/18/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/20/2026 | Structural Steel - High Strength Bolting | — | special |
| 07/20/2026 | Structural Steel - Details | — | special |
| 07/20/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 07/20/2026 | Concrete - Cast-In-Place | — | special |
| 07/20/2026 | Structural Steel - Welding | — | special |
| 07/16/2026 | Energy Code Compliance Inspections | GEORGE GHEBRYAL | progress |
| 07/16/2026 | HVAC-R and service water piping design and insulation | GEORGE GHEBRYAL | energy_progress |
| 07/16/2026 | Maintenance information | GEORGE GHEBRYAL | energy_progress |
| 07/16/2026 | Mechanical Systems | GEORGE GHEBRYAL | special |
| 07/16/2026 | Final | Firas Karkar | progress |
| 06/15/2026 | Final | — | progress |
| 06/12/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 06/11/2026 | Post-installed Anchors | — | special |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/11/2026 | Energy Code Compliance Inspections | — | progress |
| 06/11/2026 | Mechanical Systems | — | special |
| 06/11/2026 | Heating Systems | — | special |
| 06/11/2026 | Preliminary | — | progress |
| 06/11/2026 | Final | — | progress |
| 06/11/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/01/2026 | Final | — | progress |
| 01/15/2026 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 11/17/2025 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 10/02/2025 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 10/02/2025 | Mechanical Systems | GEORGE GHEBRYAL | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| CUNY Queens College Remsen Hall Chemistry Lab | Laboratory | Basement | Project Q00742117 Project Q00742149 |
| CUNY Queens College Remsen Hall | Laboratory | Sub-basement, Basement | Project Q00689685 |
| Queens College | Education | Floors 2, 3 | Project Q00737217 |
| Queens Community College | Education | Floors 1–3 | Project Q00599328 |