6 Open Violations ▸FDNY Report ↗
Two family brick · Owner of record: 637 LLC · 5,110 sf lot · 0.67 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Roof21p · 1 filing · 20 docs
Floor 320p · 1 filing · 20 docs
Floor 219p · 1 filing · 20 docs
Floor 124p · 1 filing · 20 docs
Cellar20p · 1 filing · 20 docs
1 job · most recent 03/11/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/11/2026Signed-offP.H. WORKS INCGas, Storm, Water/Sanitary
4 jobs · most recent 06/14/2026
General Wiring
FiledStatusContractorScope
06/14/2026CompletePOWER DIRECT ELECTRIC INCGeneral Wiring
01/07/2026CompletePOWER DIRECT ELECTRIC INC—
12/23/2025CompleteS&R ELECTRICAL & MECHANIC1 meters, 1 new_meters
02/02/2024CompleteS&R ELECTRICAL & MECHANIC—
1 job · most recent 03/11/2026
FiledStatusContractorScope
03/11/2026Signed-offP.H. WORKS INC3 scope_items
Building Lifecycle
All (126)Filed (13)Permit Issued (23)Signed Off (8)Violation (6)Inspection (6)Objection (40)Special Inspection (30)
04/10/2026
Signed off — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-S2
03/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
03/24/2026
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
03/24/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
03/24/2026
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
03/24/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
03/11/2026
Filed — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-P3
02/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/17/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
02/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
02/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
02/17/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
02/09/2026
Signed off — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-S3
02/09/2026
Signed off — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-S1
01/22/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/06/2026
Objection resolved — Addressed
01/06/2026
Objection resolved — Addressed
12/16/2025
Objection raised — Cost
12/16/2025
Objection raised — Scope
12/11/2025
Filed — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-P2
12/09/2025
Signed off — Alteration
B00773990-I1
12/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
12/01/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
12/01/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
12/01/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
12/01/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
10/27/2025
Permit issued — Plumbing
B00583486-S2-PL
08/08/2025
Permit issued — Structural
B00583486-S3-ST
08/07/2025
Permit issued — Construction Fence
B00773990-I1-FN
04/24/2025
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B01078488-I1
04/07/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/18/2025
Permit issued — Mechanical Systems
B00583486-S1-MS
02/13/2025
Permit issued — Structural
B00583486-S3-ST
01/21/2025
Permit issued — Construction Fence
B00773990-I1-FN
01/09/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/29/2024
Permit issued — Plumbing
B00583486-S2-PL
10/08/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/20/2024
Permit issued — General Construction
B00583486-I1-GC
08/06/2024
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B01078488-I1
08/06/2024
Permit issued — Supported Scaffold
B01078488-I1-SF
06/05/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/05/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
02/16/2024
Permit issued — Mechanical Systems
B00583486-S1-MS
02/16/2024
Permit issued — Construction Fence
B00773990-I1-FN
01/25/2024
Signed off — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-S4
12/13/2023
Permit issued — Structural
B00583486-S3-ST
11/07/2023
Signed off — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-S6
11/03/2023
Permit issued — Plumbing
B00583486-S2-PL
10/31/2023
Signed off — Alteration CO
Foundation / Earthwork application filed subsequent to Alt-CO, job number; B00583486-I1.
B00583486-S5
08/21/2023
Permit issued — General Construction
B00583486-I1-GC
02/17/2023
Permit issued — Construction Fence
B00773990-I1-FN
02/17/2023
Permit issued — Mechanical Systems
B00583486-S1-MS
01/10/2023
Permit issued — Structural
B00583486-S3-ST
01/05/2023
Permit issued — Earth Work
B00583486-S4-FO-EA
12/06/2022
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
12/06/2022
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
FAHAD FATEH
12/06/2022
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
12/06/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
12/06/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
12/06/2022
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
Latest 60 of 126 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BLUSTONE CONTRACTING5207/08/2026
CZBM403/21/2026
637 LLC403/21/2026
BLUESTONE CONTRACTING LLC103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/25/2017$2.3M—— → —$684/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ADVANCED BUILDERS SERVICES1103/21/2026
BAC Developers Group103/21/2026
THE GREEN STUDIO103/21/2026
MILLENNIUM DESIGNS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BLUSTONE CONTRACTING LLCGeneral Contractor2907/08/2026
P.H. WORKS INCPlumbing307/08/2026
S&R ELECTRICAL & MECHANICElectrical203/22/2026
MC SUPERSTRUCTURE INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161003/11/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offP.H. WORKS INC10/27/2025
DOB NOWStructuralSigned-offBLUSTONE CONTRACTING LLC08/08/2025
DOB NOWConstruction FenceSigned-offBLUSTONE CONTRACTING LLC08/07/2025
DOB NOWMechanical SystemsSigned-offBLUSTONE CONTRACTING LLC02/18/2025
DOB NOWStructuralSigned-offBLUSTONE CONTRACTING LLC02/13/2025
DOB NOWConstruction FenceSigned-offBLUSTONE CONTRACTING LLC01/21/2025
DOB NOWPlumbingSigned-offP.H. WORKS INC10/29/2024
DOB NOWGeneral ConstructionPermit IssuedBLUSTONE CONTRACTING LLC08/20/2024
DOB NOWSupported ScaffoldSigned-offMC SUPERSTRUCTURE INC08/06/2024
DOB NOWMechanical SystemsSigned-offBLUSTONE CONTRACTING LLC02/16/2024
DOB NOWConstruction FenceSigned-offBLUSTONE CONTRACTING LLC02/16/2024
DOB NOWStructuralSigned-offBLUSTONE CONTRACTING LLC12/13/2023
DOB NOWPlumbingSigned-offP.H. WORKS INC11/03/2023
DOB NOWGeneral ConstructionPermit IssuedBLUSTONE CONTRACTING LLC08/21/2023
DOB NOWConstruction FenceSigned-offBLUSTONE CONTRACTING LLC02/17/2023
DOB NOWMechanical SystemsSigned-offBLUSTONE CONTRACTING LLC02/17/2023
DOB NOWStructuralSigned-offBLUSTONE CONTRACTING LLC01/10/2023
DOB NOWEarth WorkSigned-offBLUSTONE CONTRACTING LLC01/05/2023
DOB NOWFoundationPermit IssuedBLUSTONE CONTRACTING LLC11/30/2022
DOB NOWSupport of ExcavationSigned-offBLUSTONE CONTRACTING LLC11/29/2022
DOB NOWGeneral ConstructionPermit IssuedBLUSTONE CONTRACTING LLC11/21/2022
DOB NOWGeneral ConstructionPermit IssuedBLUSTONE CONTRACTING LLC08/24/2022
DOB NOWConstruction FenceSigned-offBLUSTONE CONTRACTING LLC07/27/2022
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
01/22/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
04/07/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/09/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/08/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
06/05/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/05/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 58
DateRequirementInspectorRole
03/24/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
03/24/2026HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
03/24/2026Maintenance informationFAHAD FATEHenergy_progress
03/24/2026HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
03/24/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
02/17/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/17/2026Maintenance informationFAHAD FATEHenergy_progress
02/17/2026HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
02/17/2026HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
02/17/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
12/01/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
12/01/2025HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
12/01/2025HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
12/01/2025Maintenance informationFAHAD FATEHenergy_progress
12/01/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
12/06/2022Fenestration air leakageFAHAD FATEHenergy_progress
12/06/2022Wall Panels, Curtain Walls, and VeneersFAHAD FATEHspecial
12/06/2022Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
12/06/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
12/06/2022Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
12/06/2022Fire-Resistance Rated ConstructionFAHAD FATEHprogress
12/06/2022Energy Code Compliance InspectionsFAHAD FATEHprogress
12/06/2022Lighting in dwelling unitsFAHAD FATEHenergy_progress
12/06/2022Fenestration areasFAHAD FATEHenergy_progress
12/06/2022Protection of exposed foundation insulationFAHAD FATEHenergy_progress
Latest 25 of 58.
▾Documents — 104 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
09/03/2026B00056165-I1Request digital key ↗
08/29/2026B00773990-I1Request digital key ↗
08/28/2026B00583486-P3Request digital key ↗
Showing 3 of 13 on file for this type
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION5
03/26/2020321779090Open ↗
11/02/2018321779090Open ↗
05/22/2018321779134Open ↗
Showing 3 of 5 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
05/22/2018321779134Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
05/18/2018321779090Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
05/18/2018321779090Open ↗
▸Seals & Professional Certifications37
▸DOB NOWProgress Inspector Seal & Signature14
09/01/2026B00583486-S4Open ↗
09/01/2026B00583486-I1Open ↗
09/01/2026B00583486-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
09/03/2026B00056165-I1Open ↗
08/29/2026B00773990-I1Open ↗
08/28/2026B00583486-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/01/2026B00583486-S4Open ↗
09/01/2026B00583486-S4Open ↗
09/01/2026B00583486-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
03/19/2018321779090Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/19/2018321779090Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
05/22/2018321779134Open ↗
05/18/2018321779090Open ↗
▸DOB NOWStreet Tree Checklist2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00583486-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form7
08/13/2026B00583486-S3Open ↗
08/13/2026B00583486-S1Open ↗
08/13/2026B00583486-S5Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/19/2018321779090Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/19/2018321779090Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00583486-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWSOIL REPORT1
08/13/2026B00583486-S4Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00583486-S4Open ↗
▸Approvals, Objections & Sign-offs2
▸BISSCHEDULE A - OCCUPANCY / USE2
11/02/2018321779090Open ↗
03/19/2018321779090Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/22/2018321779134Open ↗
03/19/2018321779090Open ↗
▸Filing & Intake Forms4
▸BISEFILING COVER SHEET3
05/22/2018321779134Open ↗
05/15/2018321779090Open ↗
03/19/2018321779090Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
05/22/2018321779134Open ↗
▸Other Documents14
▸DOB NOWPlot Diagram5
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
08/13/2026B00583486-S5Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026B00583486-S4Open ↗
08/13/2026B00583486-S5Open ↗
▸DOB NOWProperty Ownership Certification2
08/15/2026B00583486-I1Open ↗
08/13/2026B00583486-P1Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026B00583486-I1Open ↗