| Owner | Filings | Most Recent |
|---|---|---|
| Highpoint Property Group | 20 | 07/08/2026 |
| 64 2nd Ave Owner | 16 | 03/22/2026 |
| Owner | 14 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/28/2018 | $7.0M | — | — → — | $1,158/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ADG Engineering | 3 | 10/15/2026 |
| LCD Design | 1 | 09/16/2026 |
| Brian McDonough, PE | 6 | 08/13/2026 |
| William Lenart, Architects | 4 | 08/06/2024 |
| Salvator A. Caradonna JR | 1 | 02/14/2022 |
| Concept Design Group | 6 | 09/24/2021 |
| Joel Phagoo P.E | 4 | 08/12/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM Zoning | 22 | 03/21/2026 |
| SNR Expediting Design | 4 | 03/21/2026 |
| All in Permit Consultants | 1 | 03/21/2026 |
| Concept Design Group | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Stepping Stone Construction* | General Contractor | 8 | 07/08/2026 |
| Billy Enterprises | Scaffold | 4 | 07/08/2026 |
| Vai Construction | General Contractor | 4 | 07/08/2026 |
| J & G Construction Services | Scaffold | 2 | 07/08/2026 |
| ZB Construction Group | General Contractor | 1 | 08/27/2026 |
| Balaton Consulting | Sign hanger | 1 | 07/08/2026 |
| Accurate Mechanical | Plumbing | 1 | 07/08/2026 |
| Amok | Fire Protection | 1 | 07/08/2026 |
| Amok | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Milrose Consultants | 2003 | 1 | 09/16/2026 |
| McDonough Engineering Pra | 9377 | 1 | 08/13/2026 |
| PSI Agency | 254 | 10 | 09/09/2024 |
| CDG Architects LLC /Dba | 1327 | 6 | 09/24/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | ZB Construction Group | 08/26/2026 |
| DOB NOW | Plumbing | Signed-off | Amok | 07/02/2024 |
| DOB NOW | Sprinklers | Signed-off | Amok | 07/02/2024 |
| DOB NOW | General Construction | Signed-off | Vai Construction | 05/14/2024 |
| DOB NOW | Structural | Signed-off | Vai Construction | 05/14/2024 |
| DOB NOW | Sign | Signed-off | North Shore Neon Sign Co | 03/03/2022 |
| DOB NOW | Structural | Signed-off | Stepping Stone Construction* | 06/11/2021 |
| DOB NOW | Mechanical Systems | Signed-off | Stepping Stone Construction* | 05/13/2021 |
| DOB NOW | Plumbing | Signed-off | Anthony Disabato | 11/13/2020 |
| DOB NOW | Mechanical Systems | Signed-off | Stepping Stone Construction* | 08/20/2020 |
| DOB NOW | Structural | Signed-off | Stepping Stone Construction* | 08/19/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Billy Enterprises | 08/12/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Billy Enterprises | 08/12/2019 |
| DOB NOW | Supported Scaffold | Signed-off | J & G Construction Services | 07/19/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G Construction Services | 07/19/2019 |
| BIS | — | ISSUED | 64 2nd Ave Owner | 08/30/2021 |
| BIS | OT | ISSUED | Stepping Stone Construction* | 08/19/2020 |
| BIS | PL | ISSUED | Orbit Plumbing & Heating | 05/04/2018 |
| BIS | OT | ISSUED | Trident Restoration | 04/24/2018 |
| BIS | OT | ISSUED | Instyle Home Renovations | 03/16/2018 |
| BIS | PL | ISSUED | Pro Star Plumbing, Heating & Mechanical | 03/16/2018 |
| BIS | OT | ISSUED | Action Awning & Sign | 04/11/2008 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/13/2026 | Permit Issued | ZB Construction Group | Air Conditioning Systems | Cooling Mitsubishi Electric MXZ-8C48NAHZ 48,000 BTU · Condensing Unit ×2 MXZ-SM36NAMHZ 36,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2020 | Permit Issued | Accurate Electrical | General Wiring |
| 08/12/2019 | Permit Issued | Richard Neu | — |
| 05/03/2018 | Permit Issued | Dennison Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | — | — | Steel, Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/18/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 09/18/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/06/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/04/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/12/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/12/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/15/2026 | Concrete - Cast-In-Place | — | special |
| 10/15/2026 | Post-installed anchors in masonry | — | special |
| 10/13/2026 | Structural Steel - High Strength Bolting | — | special |
| 10/13/2026 | Final | — | progress |
| 10/13/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 10/13/2026 | Structural Steel - Details | — | special |
| 10/13/2026 | Structural Cold-Formed Steel | — | special |
| 10/13/2026 | Structural Steel - Welding | — | special |
| 08/12/2026 | Duct leakage testing, insulation and design | Brian McDonough | energy_progress |
| 07/13/2026 | Final | Brian McDonough | progress |
| 07/13/2026 | Mechanical Systems | Brian McDonough | special |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | Brian McDonough | special |
| 07/13/2026 | Energy Code Compliance Inspections | Brian McDonough | progress |
| 07/13/2026 | HVAC-R and service water heating system controls | Brian McDonough | energy_progress |
| 07/13/2026 | Maintenance information | Brian McDonough | energy_progress |
| 07/13/2026 | HVAC-R and service water piping design and insulation | Brian McDonough | energy_progress |
| 07/13/2026 | HVAC-R and service water heating equipment | Brian McDonough | energy_progress |
| 07/01/2026 | Fenestration air leakage | Benjamin Plotnick | energy_progress |
| 07/01/2026 | Fenestration areas | Benjamin Plotnick | energy_progress |
| 07/01/2026 | Fenestration and door U-factor and product ratings | Benjamin Plotnick | energy_progress |
| 06/29/2026 | Fire-Resistant Penetrations and Joints | Benjamin Plotnick | special |
| 06/29/2026 | Structural Stability – Alterations of existing buildings | Benjamin Plotnick | special |
| 06/29/2026 | Fire-Resistance Rated Construction | Benjamin Plotnick | progress |
| 06/29/2026 | Energy Code Compliance Inspections | Benjamin Plotnick | progress |
| 09/09/2024 | Fire-Resistance Rated Construction | MAURICIO ANDRADE | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Bronx Brewery | Restaurant / Food Service | Cellar, Floor 1, Roof | Project M00499816 Project M00381824 Project M00381744 Project M00381798 |