Condo, residential tower (mixed-use, multi-family elevator) [derived]
64 EAST 11 STREET
MANHATTAN · Greenwich Village · BIN 1009106
💬 Discuss this project
1929Year Built
8Stories
RMBuilding Class
C6-1Zoning
29,278 sfGross Floor Area
7Units
LL97 CoveredRent Stabilized0 Open ViolationsFISP: SAFE
Condo, residential tower (mixed-use, multi-family elevator) [derived] · 4,021 sf lot · 7.28 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction17p · 5 filings · 20 docs
Bulkhead1p · 1 filing · 6 docs
Floor 8Under Construction5p · 4 filings · 20 docs
Floor 7Under Construction5p · 4 filings · 20 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Site & exterior2 filings · 14 docs
Filed — no permit issued1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
JERRICK ASSOCIATES1007/08/2026
J C LAMB MANAGEMENT703/22/2026
BUTTER GROUP603/21/2026
66 EAST 11TH STREET CONDOMINIUM503/21/2026
GRENVILLE PROPERTIES403/21/2026
PHOENIX BRIDGING INC DBA PHOENIX403/21/2026
CENTRAL PARKING SYSTEMS303/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LOMBARDO BUILDING CONSULTANTS103/21/2026
UNITED SAFETY CONSULTANTS403/21/2026
AE DESIGN SOLUTION403/21/2026
JM ZONING, LLC.1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor1107/08/2026
HIGHLINE CONSTRUCTION GRGeneral Contractor907/08/2026
JERRICK ASSOCIATES INCGeneral Contractor507/08/2026
KG SPRINKLER CORPFire Protection307/08/2026
DONATO PLUMBING, INCPlumbing307/08/2026
TOMASZ PUZAElectrical103/21/2026
ARCON PLBG SOLUTIONSPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMANI INSPECTION SERVICE843608/19/2026
Building Lifecycle
All (159)Filed (14)Permit Issued (29)Signed Off (5)Facade (FISP) (13)Violation (47)Inspection (17)Objection (4)Special Inspection (30)
08/21/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/19/2026
Filed — Alteration
FILED FOR INT AND EX RENOVATIONS OF MULTISTORY PH LOCATED AT THE 7TH,8TH & PH FLOORS REM/REP INT COMMUNICATING NON-EGRESS STAIRS, NONBEARING PART, FIXT AND FINISHES AND REPLACE EX SOLARIUM ROOF DECK AND ROOF DECK NO CHANGE TO USE, EGRESS OR OCCUPANCY
M00605825-P1
08/11/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/30/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-S1
06/22/2026
Permit issued — Protection and Mechanical Methods
M01068432-S1-PMM
06/22/2026
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
06/15/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/03/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/02/2026
Permit issued — Plumbing
M00606170-I1-PL
06/02/2026
Permit issued — Sprinklers
M00606170-I1-EW-SP
05/28/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/31/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/17/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-I1
02/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/20/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/18/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/12/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/13/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/13/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/13/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
10/10/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/09/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-S2
09/30/2025
Permit issued — Structural
M00606774-I1-ST
09/30/2025
Permit issued — General Construction
M00605825-I1-GC
09/30/2025
Permit issued — Mechanical Systems
M00606166-I1-MS
08/01/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-S3
07/10/2025
Signed off — Alteration
M01145286-I1
06/20/2025
Permit issued — Sidewalk Shed
M01068432-I1-SH
06/20/2025
Permit issued — Protection and Mechanical Methods
M01068432-S1-PMM
05/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN MCMONAGLE
05/09/2025
Special inspection requirement — Energy Code Compliance Inspections
JOHN MCMONAGLE
05/09/2025
Special inspection requirement — Sprinkler Systems
JOHN MCMONAGLE
05/09/2025
Special inspection requirement — Post-installed Anchors
JOHN MCMONAGLE
05/01/2025
Filed — Alteration
FILING HEREWITH PLUMBING WORK FOR THE RENOVATION OF THE 7TH FLOOR, 8TH FLOOR AND OF AT THE ADDRESS NOTED.
M00606170-P1
04/23/2025
Permit issued — Plumbing
M00606170-I1-EW-SP
03/21/2025
Permit issued — Plumbing
M00606170-I1-PL
03/17/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/14/2025
Special inspection requirement — Post-installed Anchors
JOHN MCMONAGLE
03/14/2025
Special inspection requirement — Energy Code Compliance Inspections
JOHN MCMONAGLE
03/14/2025
Special inspection requirement — Sprinkler Systems
JOHN MCMONAGLE
03/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN MCMONAGLE
02/28/2025
Permit issued — Suspended Scaffold
M01145286-I1-SC
01/07/2025
Permit issued — General Construction
M00605825-I1-GC
01/07/2025
Permit issued — Mechanical Systems
M00606166-I1-MS
01/07/2025
Permit issued — Structural
M00606774-I1-ST
01/03/2025
Filed — Alteration
M01145286-I1
01/03/2025
Permit issued — Suspended Scaffold
M01145286-I1-SC
11/20/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Lombardo
11/15/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/07/2024
Permit issued — Construction Fence
M01068432-S3-FN
11/01/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-S3
10/28/2024
Permit issued — Supported Scaffold
M01068432-S2-SF
10/23/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-S2
06/21/2024
Permit issued — Protection and Mechanical Methods
M01068432-S1-PMM
06/20/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-S1
06/20/2024
Permit issued — Sidewalk Shed
M01068432-I1-SH
06/19/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01068432-I1
03/28/2024
Permit issued — Plumbing
M00606170-I1-PL
01/23/2024
Permit issued — Sprinklers
M00606170-I1-EW-SP
01/23/2024
Permit issued — Sprinklers
M00606170-I1-PL
Latest 60 of 159 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC06/22/2026
DOB NOWPlumbingPermit IssuedDONATO PLUMBING, INC06/02/2026
DOB NOWSprinklersPermit IssuedKG SPRINKLER CORP06/02/2026
DOB NOWStructuralPermit IssuedHIGHLINE CONSTRUCTION GR09/30/2025
DOB NOWGeneral ConstructionPermit IssuedHIGHLINE CONSTRUCTION GR09/30/2025
DOB NOWMechanical SystemsPermit IssuedHIGHLINE CONSTRUCTION GR09/30/2025
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/20/2025
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC06/20/2025
DOB NOWPlumbingPermit IssuedH M SPRINKLER INC04/23/2025
DOB NOWPlumbingPermit IssuedDONATO PLUMBING, INC03/21/2025
DOB NOWSuspended ScaffoldSigned-offSKYTRAC ACCESS GROUP LLC02/28/2025
DOB NOWGeneral ConstructionPermit IssuedHIGHLINE CONSTRUCTION GR01/07/2025
DOB NOWMechanical SystemsPermit IssuedHIGHLINE CONSTRUCTION GR01/07/2025
DOB NOWStructuralPermit IssuedHIGHLINE CONSTRUCTION GR01/07/2025
DOB NOWSuspended ScaffoldSigned-offSKYTRAC ACCESS GROUP LLC01/03/2025
DOB NOWConstruction FenceSigned-offSPRING SCAFFOLDING LLC11/07/2024
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC10/28/2024
DOB NOWProtection and Mechanical MethodsSigned-offSPRING SCAFFOLDING LLC06/21/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/20/2024
DOB NOWPlumbingPermit IssuedDONATO PLUMBING, INC03/28/2024
DOB NOWSprinklersPermit IssuedH M SPRINKLER INC01/23/2024
DOB NOWSprinklersPermit IssuedARCON PLBG SOLUTIONS01/23/2024
DOB NOWMechanical SystemsPermit IssuedHIGHLINE CONSTRUCTION GR01/11/2024
DOB NOWStructuralPermit IssuedHIGHLINE CONSTRUCTION GR01/11/2024
DOB NOWGeneral ConstructionPermit IssuedHIGHLINE CONSTRUCTION GR01/11/2024
DOB NOWSupported ScaffoldPermit IssuedGE 2A CONSTRUCTION01/26/2022
DOB NOWSidewalk ShedPermit IssuedGE 2A CONSTRUCTION01/04/2022
DOB NOWSupported ScaffoldPermit IssuedGE 2A CONSTRUCTION01/20/2021
DOB NOWSidewalk ShedPermit IssuedGE 2A CONSTRUCTION01/08/2021
BISOTISSUEDJERRICK ASSOCIATES INC03/24/2021
BISOTISSUEDJERRICK ASSOCIATES INC01/13/2021
BISOTISSUEDC&A SENECA CONSTRUCTION L12/28/2020
BISMHISSUEDC&A SENECA CONSTRUCTION L06/22/2020
BISOTISSUEDC&A SENECA CONSTRUCTION L12/24/2019
BISOTISSUEDC&A SENECA CONSTRUCTION L05/06/2019
BISOTISSUEDRELIABLE RENOVATIONS USA02/22/2019
BISSPISSUEDDEMAR PLUMBING CORP01/10/2019
BISPLISSUEDDEMAR PLUMBING CORP01/10/2019
BISMHISSUEDC&A SENECA CONSTRUCTION L11/14/2018
BISOTISSUEDC&A SENECA CONSTRUCTION L11/13/2018
+ 39 more permits on file
1 project · most recent 05/12/2022
Associated Ducts and Piping Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/12/2022Permit IssuedHIGHLINE CONSTRUCTION GRAssociated Ducts and Piping, Heating and Air Conditioning Systems
Heat / Cool
Daikin ×11
Ducts & Piping
1 project · most recent 05/01/2025
FiledStatusContractorScope
05/01/2025Permit IssuedKG SPRINKLER CORP386 heads
1 project · most recent 05/01/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
05/01/2025Permit IssuedDONATO PLUMBING, INCGas, Storm, Water/Sanitary
6 projects · most recent 12/05/2024
General Wiring
FiledStatusContractorScope
12/05/2024CompleteAPOLLO ELECTRIC INC.General Wiring
05/03/2024CompleteTOP SHELF ELECTRIC CORP—
01/19/2024CompleteAPOLLO ELECTRIC INC.—
01/06/2021CompleteBOROWIDE ELECT'L CONTR'S—
04/30/2019Permit IssuedC.FALCO ELETL CONT CORPGeneral Wiring
06/15/2018CancelledP.L. ELEC'L CONTR'G CORPGeneral Wiring
3 projects · most recent 11/01/2024
Scaffold Fence Sidewalk Shed
FiledStatusContractorScope
11/01/2024Signed-offSPRING SCAFFOLDING LLCFence, Scaffold
01/19/2021Permit IssuedJERRICK ASSOCIATES INCScaffold
01/07/2021Permit IssuedJERRICK ASSOCIATES INCSidewalk Shed
▾Field Inspections (DOB CAP) — 17
DateTypeResultReport
08/21/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/11/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/22/2026No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
06/15/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/03/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/28/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/31/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/20/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/18/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/12/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/13/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/13/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/13/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/10/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/17/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/15/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
05/09/2025Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
05/09/2025Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
05/09/2025Sprinkler SystemsJOHN MCMONAGLEspecial
05/09/2025Post-installed AnchorsJOHN MCMONAGLEspecial
03/14/2025Post-installed AnchorsJOHN MCMONAGLEspecial
03/14/2025Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
03/14/2025Sprinkler SystemsJOHN MCMONAGLEspecial
03/14/2025Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
11/20/2024Alternative Materials - OTCR Buildings Bulletin NumberMichael Lombardospecial
03/29/2022Mastic and Intumescent Fire-resistant CoatingsJOHN MCMONAGLEspecial
03/29/2022Sprayed fire-resistant materialsJOHN MCMONAGLEspecial
03/29/2022Wall Panels, Curtain Walls, and VeneersJOHN MCMONAGLEspecial
03/29/2022Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
03/29/2022Fire-Resistance Rated ConstructionJOHN MCMONAGLEprogress
03/29/2022FinalJOHN MCMONAGLEprogress
03/29/2022Fenestration and door U-factor and product ratingsJOHN MCMONAGLEenergy_progress
03/29/2022Fenestration air leakageJOHN MCMONAGLEenergy_progress
03/29/2022Air barrier - visual inspectionJOHN MCMONAGLEenergy_progress
03/29/2022Fenestration areasJOHN MCMONAGLEenergy_progress
03/29/2022Insulation placement and R valuesJOHN MCMONAGLEenergy_progress
03/29/2022Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
03/29/2022MasonryJOHN MCMONAGLEspecial
10/14/2021Maintenance informationJOHN MCMONAGLEenergy_progress
10/14/2021Shutoff dampersJOHN MCMONAGLEenergy_progress
10/14/2021HVAC-R and service water heating system controlsJOHN MCMONAGLEenergy_progress
Latest 25 of 34.
▾Documents — 512 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch12
09/02/2026M00605825-I1Request digital key ↗
09/02/2026M00605825-P1Request digital key ↗
09/02/2026M00606774-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00447206-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/04/2026M00448619-I1Request digital key ↗
▸Applications & Permits115
▸BISWORK PERMIT APPLICATION58
01/13/2021123781443Open ↗
12/26/2019123498125Open ↗
12/26/2019123498125Open ↗
Showing 3 of 58 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION55
10/04/2019122961456Open ↗
09/30/2019122961456Open ↗
09/17/2019122961456Open ↗
Showing 3 of 55 on file for this type
▸BISSIDEWALK SHED APPLICATION & PERMIT1
01/13/2021123781443Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications116
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION60
05/01/2020122961456Open ↗
05/01/2020122961456Open ↗
06/24/2019123498125Open ↗
Showing 3 of 60 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST14
10/03/2018123498125Open ↗
06/01/2018123235187Open ↗
12/12/2016122961456Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
09/04/2026M00447206-I1Open ↗
09/02/2026M00606774-I1Open ↗
08/27/2026M01068432-S3Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT12
10/03/2018123498125Open ↗
06/01/2018123235187Open ↗
12/12/2016122961456Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026M00606170-I1Open ↗
08/31/2026M00606166-I1Open ↗
08/31/2026M00606166-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026M00606170-I1Open ↗
08/31/2026M00606166-I1Open ↗
08/27/2026M00606170-P1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISApplicant / Owner Signature1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment51
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE18
10/04/2019122961456Open ↗
09/30/2019122961456Open ↗
09/17/2019122961456Open ↗
Showing 3 of 18 on file for this type
▸BISSELF-CERT PLUMBING NOTICE17
11/02/2015122329079Open ↗
Showing 1 of 17 on file for this type
▸BISSCHEDULE B - PLUMBING7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
11/02/2015122329079Open ↗
▸BISEQUIPMENT USE PERMITS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection8
▸BISTenant Protection Plan and Notes4
05/31/2019123781443Open ↗
10/03/2018123498125Open ↗
06/01/2018123235187Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISStreet Trees- Receipt of Street Trees Site Plan1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos21
▸BISASBESTOS: CERTIFICATION (DEP ACP5)10
05/31/2019123781443Open ↗
10/03/2018123498125Open ↗
06/05/2018123235187Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/02/2026M00606774-I1Open ↗
08/23/2026M00606170-P1Open ↗
08/21/2026M00605825-P1Open ↗
Showing 3 of 7 on file for this type
▸BISTHIS IS NOT AN ASBESTOS PROJECT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance27
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS18
05/01/2020122961456Open ↗
05/01/2020122961456Open ↗
06/24/2019123498125Open ↗
Showing 3 of 18 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
08/10/2022123781443Open ↗
05/01/2020122961456Open ↗
02/09/2016122329060Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
08/10/2022123781443Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY3
08/10/2022123781443Open ↗
08/10/2022123781443Open ↗
01/13/2021123781443Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCONCRETE DESIGN MIX (TR-3) 27-6051
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs44
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST21
08/11/2022123781443Open ↗
06/19/2017120737408Open ↗
02/09/2016122329088Open ↗
Showing 3 of 21 on file for this type
▸BISADMINISTRATIVE OBJECTIONS7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION6
06/24/2019123498125Open ↗
Showing 1 of 6 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
08/13/2026M01068432-S1Open ↗
08/13/2026M01068432-I1Open ↗
08/13/2026M01068432-S3Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSUPERSEDING LETTER1
02/26/2019122961456Open ↗
▸BISSHED LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership33
▸BISCOST AFFIDAVIT33
08/10/2022123781443Open ↗
05/01/2020122961456Open ↗
05/31/2019123781443Open ↗
Showing 3 of 33 on file for this type
▸Filing & Intake Forms62
▸BISADDITIONAL INFORMATION31
10/04/2019122961456Open ↗
09/17/2019122961456Open ↗
07/15/2019122961456Open ↗
Showing 3 of 31 on file for this type
▸BISEFILING COVER SHEET23
05/31/2019123781443Open ↗
10/03/2018123498125Open ↗
06/01/2018123235187Open ↗
Showing 3 of 23 on file for this type
▸BISBOROUGH INTAKE FORM7
05/01/2020122961456Open ↗
09/30/2019122961456Open ↗
09/17/2019122961456Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Other Documents10
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSITE CONNECTION: DEP1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWManufacturer's Specifications1
08/13/2026M01145286-I1Open ↗
▸DOB NOWCalculations1