← Back
STATEN ISLAND
64 PITTSVILLE AVENUE
STATEN ISLAND · Tottenville-Charleston · BIN 5088028
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone X
Locations of Work
ArchitectureGeneral
Filed — no permit issued8p · 1 filing · 17 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AVID DESIGNS, INC109/08/2022
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AVID DESIGNS, INC.453109/08/2022
Building Lifecycle
All (40)Filed (1)Objection (13)Special Inspection (26)
12/02/2022
Special inspection requirement — Metering
Jeffrey Geary
10/18/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Jeffrey Geary
10/18/2022
Special inspection requirement — HVAC-R and service water heating system controls
Jeffrey Geary
09/29/2022
Objection raised — Mechanical
09/29/2022
Objection resolved — Resolved
09/29/2022
Objection raised — Zoning
09/29/2022
Objection resolved — Resolved
09/29/2022
Objection raised — Other
09/29/2022
Objection resolved — Resolved
09/29/2022
Objection raised — Zoning
09/29/2022
Objection resolved — Resolved
09/29/2022
Objection raised — Admin
09/29/2022
Objection resolved — Resolved
09/29/2022
Objection raised — Scope
09/29/2022
Objection raised — Zoning
09/29/2022
Objection resolved — Resolved
09/08/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
ENLARGMENT OF THE SECOND FLOOR RESIDENCE AND EXTENSION OVER THE GARAGE
S00760888-I1
08/25/2022
Special inspection requirement — Subgrade Inspections
Jeffrey Geary
08/25/2022
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
06/20/2022
Special inspection requirement — Fire-Resistance Rated Construction
Jeffrey Geary
06/20/2022
Special inspection requirement — Structural Wood Frame
Jeffrey Geary
06/20/2022
Special inspection requirement — Final
James Carroll
06/20/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Jeffrey Geary
06/20/2022
Special inspection requirement — Air barrier — testing
Jeffrey Geary
06/20/2022
Special inspection requirement — Ventilation and air distribution system
Jeffrey Geary
06/20/2022
Special inspection requirement — Insulation placement and R values
Jeffrey Geary
06/20/2022
Special inspection requirement — Fenestration areas
Jeffrey Geary
06/20/2022
Special inspection requirement — Air barrier - visual inspection
Jeffrey Geary
06/20/2022
Special inspection requirement — Interior lighting power
Jeffrey Geary
06/20/2022
Special inspection requirement — Electric vehicle service equipment requirements
Jeffrey Geary
06/20/2022
Special inspection requirement — Fireplaces
Jeffrey Geary
06/20/2022
Special inspection requirement — Maintenance information
Jeffrey Geary
06/20/2022
Special inspection requirement — Fenestration air leakage
Jeffrey Geary
06/20/2022
Special inspection requirement — HVAC-R and service water heating equipment
Jeffrey Geary
06/20/2022
Special inspection requirement — Concrete - Cast-In-Place
Jeffrey Geary
06/20/2022
Special inspection requirement — Permanent certificate
Jeffrey Geary
06/20/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jeffrey Geary
06/20/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
Jeffrey Geary
06/20/2022
Special inspection requirement — Mechanical Systems
Jeffrey Geary
06/20/2022
Special inspection requirement — Energy Code Compliance Inspections
Jeffrey Geary
Nothing on file for this building.
1 project · most recent 09/08/2022
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/08/2022——Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Trane TEM4A0B36L1000A 36,000 BTU · Fan Coil Indoor ×2
TEM4A0B36S31SB 34,000 BTU · Condensing Unit ×2
Heating
Navien NFB-175H 95% AFUE (SELECTED COP DUE TO LIMITATION OF FORM) 139,000 BTU · Boiler ×1
Ventilation
Fantech SHR 260 RD 239 CFM · Erv ×1
2 projects · most recent 07/14/2026
FiledStatusContractorScope
07/14/2026Permit IssuedMANGI ELECTRICAL CORP1 meters, 1 new_meters
03/05/2024CompleteMANGI ELECTRICAL CORP1 meters, 1 new_meters
1 project · most recent 09/08/2022
Wood
FiledStatusContractorScope
09/08/2022——Wood
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
12/02/2022MeteringJeffrey Gearyenergy_progress
10/18/2022HVAC-R and service water piping design and insulationJeffrey Gearyenergy_progress
10/18/2022HVAC-R and service water heating system controlsJeffrey Gearyenergy_progress
08/25/2022Subgrade InspectionsJeffrey Gearyspecial
08/25/2022Subsurface Investigations (Borings/Test Pits)—special
06/20/2022Fire-Resistance Rated ConstructionJeffrey Gearyprogress
06/20/2022Structural Wood FrameJeffrey Gearyprogress
06/20/2022FinalJames Carrollprogress
06/20/2022Fenestration and door U-factor and product ratingsJeffrey Gearyenergy_progress
06/20/2022Air barrier — testing Jeffrey Gearyenergy_progress
06/20/2022Ventilation and air distribution systemJeffrey Gearyenergy_progress
06/20/2022Insulation placement and R valuesJeffrey Gearyenergy_progress
06/20/2022Fenestration areasJeffrey Gearyenergy_progress
06/20/2022Air barrier - visual inspectionJeffrey Gearyenergy_progress
06/20/2022Interior lighting powerJeffrey Gearyenergy_progress
06/20/2022Electric vehicle service equipment requirementsJeffrey Gearyenergy_progress
06/20/2022FireplacesJeffrey Gearyenergy_progress
06/20/2022Maintenance informationJeffrey Gearyenergy_progress
06/20/2022Fenestration air leakageJeffrey Gearyenergy_progress
06/20/2022HVAC-R and service water heating equipmentJeffrey Gearyenergy_progress
06/20/2022Concrete - Cast-In-PlaceJeffrey Gearyspecial
06/20/2022Permanent certificateJeffrey Gearyenergy_progress
06/20/2022Fire-Resistant Penetrations and JointsJeffrey Gearyspecial
06/20/2022Structural Stability – Alterations of existing buildingsJeffrey Gearyspecial
06/20/2022Mechanical SystemsJeffrey Gearyspecial
Latest 25 of 26.
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/15/2026S00760888-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
07/31/2024540264541Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
09/04/2024540264541Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S00760888-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00760888-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00760888-I1Open ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
09/25/2026S00760888-I1Open ↗
09/25/2026S00760888-I1Open ↗
09/25/2026S00760888-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/31/2024540264541Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/31/2024540264541Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/25/2026S00760888-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S00760888-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00760888-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00760888-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S00760888-I1Open ↗
▸Inspections & Test Reports4
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
09/04/2024540264541Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
07/31/2024540264541Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00760888-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026S00760888-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
09/04/2024540264541Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
07/31/2024540264541Open ↗
▸Other Documents10
▸BISBPP - SUPPORTING DOCUMENTATION4
09/04/2024540264541Open ↗
09/04/2024540264541Open ↗
09/04/2024540264541Open ↗
Showing 3 of 4 on file for this type
▸BISBPP: TOPOGRAPHIC SURVEY1
09/04/2024540264541Open ↗
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form1
09/04/2024540264541Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
09/04/2024540264541Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026S00760888-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026S00760888-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026S00760888-I1Open ↗