| Firm | Filings | Most Recent |
|---|---|---|
| HANSA BUILDING ENGINEERING SERVICES | 3 | 03/16/2023 |
| BL CONSULTANT | 2 | 05/12/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| H DESIGN STUDIO INC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CJ HEATING & MECHANICAL C | Plumbing | 3 | 07/08/2026 |
| JIMENEZ LUIS | Electrical | 1 | 03/21/2026 |
| LUIS JIMENEZ | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASKON ARCHITECT, P.C. | 3596 | 3 | 03/16/2023 |
| IP CONCRETE TESTING AND I | 6252 | 2 | 05/12/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | CJ HEATING & MECHANICAL C | 11/22/2022 |
| DOB NOW | Plumbing | Signed-off | CJ HEATING & MECHANICAL C | 11/07/2022 |
| DOB NOW | Plumbing | Signed-off | CJ HEATING & MECHANICAL C | 04/12/2022 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 01/30/2008 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 06/04/2001 |
| BIS | OT | ISSUED | IDEAL FIRE CONTROL | 11/18/1994 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/16/2023 | Signed-off | CJ HEATING & MECHANICAL C | Gas, Plumbing-Sprinkler |
| 05/12/2022 | Signed-off | CJ HEATING & MECHANICAL C | Gas |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/18/2023 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 05/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/14/2023 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 03/01/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/19/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/28/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/17/2023 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 03/17/2023 | Energy Code Compliance Inspections | HANSA PERSAUD | progress |
| 03/09/2023 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 03/09/2023 | Energy Code Compliance Inspections | HANSA PERSAUD | progress |
| 11/08/2022 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 11/08/2022 | Energy Code Compliance Inspections | HANSA PERSAUD | progress |
| 06/16/2022 | Energy Code Compliance Inspections | BALDEMIRO LEON | progress |
| 06/16/2022 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 05/10/2022 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 05/10/2022 | Energy Code Compliance Inspections | BALDEMIRO LEON | progress |