| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/14/2025 | Permit Issued | NICON BUILD LLC | Heating and Air Conditioning Systems | Heat / Cool Fujitsu AOU96RLAVL 8 tons · Heat Pump Outdoor ×1 |
| 10/26/2021 | — | — | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/26/2022 | Permit Issued | R.J.C. MECHANICAL CORP | 50 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/26/2022 | Permit Issued | GREAT OAKS MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | EMPIRE STATE ELECTL CORP | General Wiring |
| 04/17/2026 | Complete | BRIGHTLINK ELECTRIC INC. | General Wiring |
| 08/28/2025 | Permit Issued | RICHARD NEU | — |
| 12/11/2023 | Complete | EMPIRE STATE ELECTL CORP | General Wiring |
| 08/18/2023 | Permit Issued | OMD ELECTRICAL CORP | 1 meters, 1 new_meters |
| 06/26/2023 | Complete | EMPIRE STATE ELECTL CORP | — |
| 03/20/2023 | Complete | ATHENS ELECTRIC INC. | HVAC Wiring |
| 01/25/2023 | Permit Issued | ALBA ELECTRIC CORP | General Wiring |
| 08/10/2022 | Complete | ATHENS ELECTRIC INC. | 2 meters, 2 new_meters |
| 07/17/2022 | Complete | ATHENS ELECTRIC INC. | — |
| 08/20/2020 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 07/31/2020 | Complete | GEORGE HOLNESS | General Wiring |
| 03/13/2020 | Complete | RESPONSE ELECTRIC INC. | General Wiring |
| 01/10/2019 | Complete | I.P. ELECTRIC INC | General Wiring |
| 11/16/2018 | Complete | R-2 ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/19/2025 | Permit Issued | PHOENIX SUTTON STR INC | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2024 | Permit Issued | TAURINO MANAGEMENT, INC | Tenant Protection Plan 72 Hour |
| Owner | Filings | Most Recent |
|---|---|---|
| SHULSKY PROPERTIES | 68 | 07/08/2026 |
| NOVA CONSTRUCTION SERVICES | 9 | 03/22/2026 |
| BLEECKER TOWERS TENANTS | 102 | 03/22/2026 |
| ANDREWS BUILDING | 9 | 03/22/2026 |
| OWNER OF 644 BWAY | 1 | 03/22/2026 |
| BLUE WILLOW ENT LTD | 3 | 03/22/2026 |
| CEPRINE CONSTRUCTION | 1 | 03/22/2026 |
| 644 BROADWAY TENANTS | 9 | 03/21/2026 |
| C O VILES CONTRACTING | 4 | 03/21/2026 |
| BLEECKER TOWERS TENANTS COR | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 2 | 09/19/2025 |
| DEREK ZIEMER ARCHITECTURE, PLLC | 4 | 05/14/2025 |
| BENJAMIN PORTO ARCHITECTURE D.P.C. | 7 | 07/25/2024 |
| CFS ENGINEERING, DPC | 11 | 05/06/2024 |
| SKYLINE ENGINEERING, LLC | 2 | 09/14/2023 |
| ANCORA ENGINEERING, PLLC | 1 | 08/28/2023 |
| RONALD NEMEC ARCHITECT PC | 2 | 02/22/2023 |
| VINCENT J. LIOTTA P.E. | 1 | 02/01/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 01/20/2023 |
| COLLADO ENGINEERING | 1 | 06/13/2022 |
| E4P CONSULTING ENGINEERING PLLC | 1 | 10/26/2021 |
| KZ ENGINEERING, P.C | 2 | 08/26/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 41 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 2 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TAURINO MANAGEMENT, INC | General Contractor | 21 | 07/08/2026 |
| NOVA CONSTRUCTION SERVICE | General Contractor | 6 | 03/21/2026 |
| NICON BUILD LLC | General Contractor | 3 | 07/08/2026 |
| DEMAR PLUMBING CORP | Fire Protection | 3 | 07/08/2026 |
| DA SILVA, JAMES | Electrical | 2 | 03/21/2026 |
| CEPRINE CONSTRUCTION INC | General Contractor | 2 | 07/08/2026 |
| PERFECTAIRE CO INC | General Contractor | 2 | 03/21/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 2 | 08/25/2026 |
| DEMAR MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| CALCOE ASSOCIATES INC | General Contractor | 1 | 07/08/2026 |
| HENICK-LANE SERVICE CORP | General Contractor | 1 | 07/08/2026 |
| DP FLYNN PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| BERGER CARLOS | Electrical | 1 | 03/21/2026 |
| R.J.C. MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| BOROWIDE ELECT'L CONTR'S | Electrical | 1 | 03/22/2026 |
| EGBERT BAPTISTE | Electrical | 1 | 03/21/2026 |
| HOLNESS, GEORGE | Electrical | 1 | 03/21/2026 |
| KREMER, WILLIAM | Electrical | 1 | 03/21/2026 |
| NAVAS, WILMER | Electrical | 1 | 03/21/2026 |
| R-2 ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| TRANSCANADA | Electrical | 1 | 03/21/2026 |
| R.J.C. MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| OUTSOURCE SPECIAL INSPECT | 2827 | 1 | 05/14/2025 |
| AK ENGINEERING PC | 678 | 18 | 05/06/2024 |
| VINCENT J. LIOTTA P. E. | 1974 | 1 | 02/01/2023 |
| GC ENG & ASSOCIATES PC | 1796 | 2 | 09/26/2022 |
| COLLADO ENGINEERING, DPC | 3432 | 1 | 06/13/2022 |
| HT ENGINEERING, PLLC | 6274 | 1 | 10/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | PHOENIX SUTTON STR INC | 08/24/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PHOENIX SUTTON STR INC | 08/26/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | NICON BUILD LLC | 06/25/2025 |
| DOB NOW | Structural | Signed-off | TAURINO MANAGEMENT, INC | 01/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TAURINO MANAGEMENT, INC | 01/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | General Construction | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | General Construction | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | Structural | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | General Construction | Permit Issued | TAURINO MANAGEMENT, INC | 10/24/2023 |
| DOB NOW | Sprinklers | Signed-off | DEMAR PLUMBING CORP | 09/29/2023 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 09/14/2023 |
| DOB NOW | General Construction | Signed-off | TAURINO MANAGEMENT, INC | 09/13/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TAURINO MANAGEMENT, INC | 09/13/2023 |
| DOB NOW | Structural | Signed-off | TAURINO MANAGEMENT, INC | 09/01/2023 |
| DOB NOW | Sprinklers | Signed-off | DEMAR PLUMBING CORP | 07/12/2023 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 07/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TAURINO MANAGEMENT, INC | 07/10/2023 |
| DOB NOW | Sprinklers | Signed-off | DEMAR PLUMBING CORP | 07/10/2023 |
| DOB NOW | Structural | Signed-off | TAURINO MANAGEMENT, INC | 07/05/2023 |
| DOB NOW | General Construction | Signed-off | TAURINO MANAGEMENT, INC | 06/30/2023 |
| DOB NOW | Plumbing | Signed-off | DP FLYNN PLBG & HTG INC | 04/11/2023 |
| DOB NOW | General Construction | Signed-off | CALCOE ASSOCIATES INC | 04/05/2023 |
| DOB NOW | Mechanical Systems | Signed-off | PERFECTAIRE CO INC | 02/21/2023 |
| DOB NOW | Supported Scaffold | Signed-off | NOVA CONSTRUCTION SERVICE | 01/20/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | NOVA CONSTRUCTION SERVICE | 01/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | HENICK-LANE SERVICE CORP | 11/09/2022 |
| DOB NOW | General Construction | Permit Issued | NICON BUILD LLC | 10/12/2022 |
| DOB NOW | Sprinklers | Permit Issued | R.J.C. MECHANICAL CORP | 10/05/2022 |
| DOB NOW | Sprinklers | Permit Issued | R.J.C. MECHANICAL CORP | 10/05/2022 |
| DOB NOW | General Construction | Signed-off | NICON BUILD LLC | 06/24/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CEPRINE CONSTRUCTION INC | 08/26/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CEPRINE CONSTRUCTION INC | 08/26/2020 |
| BIS | SP | ISSUED | DEMAR PLUMBING CORP | 11/09/2022 |
| BIS | BL | ISSUED | A & C HTG SERVICES, INC | 12/17/2020 |
| BIS | PL | ISSUED | A & C HTG SERVICES, INC | 12/17/2020 |
| BIS | OT | ISSUED | BAYSIDE CONTRACTING INC | 12/11/2020 |
| BIS | OT | ISSUED | A & C HEATING SERVICES IN | 12/09/2020 |
| BIS | MH | ISSUED | A & C HEATING SERVICES IN | 12/09/2020 |
| BIS | OT | ISSUED | A & C HEATING SERVICES IN | 12/09/2020 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/30/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/23/2024 | No Access-Final SP - Up to 3 Requested Floors | No Access | View ↗ |
| 04/11/2024 | Fail-Final SP - Up to 3 Requested Floors | Fail | View ↗ |
| 04/04/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/11/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/11/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/11/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/06/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/06/2024 | Pass-Final SD - Up to 3 Requested Floors | Pass | View ↗ |
| 03/06/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/05/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/11/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/09/2024 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 01/04/2024 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 12/15/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/07/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/06/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/01/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/26/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/20/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/07/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/05/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/13/2025 | Energy Code Compliance Inspections | Derek Ziemer | progress |
| 03/11/2025 | HVAC-R and service water piping design and insulation | Derek Ziemer | energy_progress |
| 03/11/2025 | Final | Derek Ziemer | progress |
| 03/11/2025 | HVAC-R and service water heating equipment | Derek Ziemer | energy_progress |
| 03/11/2025 | Tenant Protection Plan Compliance | JONAR MADRIAGA | special |
| 03/11/2025 | Mechanical Systems | JONAR MADRIAGA | special |
| 08/06/2024 | Tenant Protection Plan Compliance | — | special |
| 07/10/2024 | Tenant Protection Plan Compliance | — | special |
| 05/20/2024 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 05/20/2024 | Tenant Protection Plan Compliance | Ari Kamo | special |
| 04/02/2024 | Tenant Protection Plan Compliance | — | special |
| 03/25/2024 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 02/29/2024 | Tenant Protection Plan Compliance | Ari Kamo | special |
| 02/29/2024 | Final | Ari Kamo | progress |
| 02/29/2024 | Mechanical Systems | Ari Kamo | special |
| 02/27/2024 | Tenant Protection Plan Compliance | Ari Kamo | special |
| 02/27/2024 | Final | Ari Kamo | progress |
| 02/05/2024 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 02/05/2024 | Sprinkler Systems | Ari Kamo | special |
| 02/05/2024 | Tenant Protection Plan Compliance | Ari Kamo | special |
| 01/22/2024 | Tenant Protection Plan Compliance | Ari Kamo | special |
| 01/22/2024 | Final | Ari Kamo | progress |
| 01/22/2024 | Fire-Resistance Rated Construction | Ari Kamo | progress |
| 01/22/2024 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 01/22/2024 | Sprayed fire-resistant materials | Ari Kamo | special |