| Firm | Filings | Most Recent |
|---|---|---|
| NKM ENGINEERING PLLC | 1 | 08/21/2026 |
| CKL ENGINEERING | 2 | 05/13/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2026 | Permit Issued | CHARISMA ELECL CONTS LLC | HVAC Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/21/2026 | Air barrier — testing | — | energy_progress |
| 08/21/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/21/2026 | Energy Code Compliance Inspections | — | progress |
| 08/21/2026 | Fire-Resistance Rated Construction | — | progress |
| 08/21/2026 | Final | — | progress |
| 08/21/2026 | Air barrier - visual inspection | — | energy_progress |
| 08/21/2026 | Fenestration air leakage | — | energy_progress |
| 08/21/2026 | Insulation placement and R values | — | energy_progress |
| 08/21/2026 | Interior lighting power | — | energy_progress |
| 08/21/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 05/12/2026 | Final | — | progress |
| 05/12/2026 | Energy Code Compliance Inspections | — | progress |
| 05/12/2026 | Fire-Resistance Rated Construction | — | progress |
| 05/12/2026 | Air barrier — testing | — | energy_progress |
| 05/12/2026 | Insulation placement and R values | — | energy_progress |
| 05/12/2026 | Interior lighting power | — | energy_progress |
| 05/12/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 05/12/2026 | Air barrier - visual inspection | — | energy_progress |
| 05/12/2026 | Fenestration air leakage | — | energy_progress |