← Back
Miscellaneous and old-style bank buildings
648 BROADWAY
MANHATTAN · BIN 1008419
💬 Discuss this project
1892Year Built
10Stories
O9Building Class
M1-5/R9AZoning
49,310 sfGross Floor Area
56Units
LL97 Covered2 Open Violations ▸FISP: UNSAFE
Miscellaneous and old-style bank buildings · Owner of record: FRANMAR INFANTS WEAR INC · 5,292 sf lot · 9.32 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipment
Permit Issued — active, not yet Signed-off
RoofUnder Construction29p · 10 filings · 20 docs
Bulkhead1p · 1 filing · 3 docs
Floor 10Under Construction9p · 2 filings · 15 docs
Floor 9Under Construction9p · 2 filings · 15 docs
Floor 8Under Construction10p · 3 filings · 20 docs
Floor 7Under Construction10p · 3 filings · 20 docs
Floor 6Under Construction9p · 2 filings · 15 docs
Floor 5Under Construction28p · 6 filings · 20 docs
Floor 4Under Construction9p · 2 filings · 15 docs
Floor 3Under Construction14p · 3 filings · 20 docs
Floor 2Under Construction9p · 2 filings · 15 docs
Floor 1Under Construction11p · 4 filings · 20 docs
Cellar7p · 3 filings · 20 docs
Sub-Cellar5p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PRAT ENTERPRISES1909/07/2026
NEWMARK409/01/2026
TRIHILL MANAGEMENT3207/08/2026
CEPRINE CONSTRUCTION807/08/2026
TRI BOROUGH SCAFFOLDING607/08/2026
TRI HILL2407/08/2026
LEE ASSOCIATES MGT407/08/2026
CERINA GENERAL CONTRACT I103/22/2026
FRANMAR INFANTS WEST INC103/22/2026
SIERRA REALITY CORP.903/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MUNICIPAL BUILDING CONSULTANTS1703/21/2026
MICHAEL ZENREICH ARCHITECT1003/21/2026
SYNERGY BUILDING CONSULTANTS103/21/2026
Rigid Structural Design, LLC303/21/2026
HLZAE103/21/2026
PRAT ENTERPRISES403/21/2026
AE DESIGN SOLUTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PRAT ENTERPRISES CORPGeneral Contractor2609/07/2026
TRI BOROUGH SCAFFOLDINGGeneral Contractor707/08/2026
STEPPING STONE CONSTRUCT*General Contractor507/08/2026
CEPRINE CONSTRUCTION INCGeneral Contractor407/08/2026
VERA FORMA LLCGeneral Contractor407/08/2026
PRESS BUILDERS INCGeneral Contractor307/08/2026
MC SUPERSTRUCTURE INCGeneral Contractor203/21/2026
ARCH MW LLCGeneral Contractor207/08/2026
NYC TRANSITElectrical103/21/2026
PARISI, DINOElectrical103/21/2026
ARCO PLBG AND HTG INCFire Protection107/08/2026
ENOBRAC PLUMBING, INCFire Protection107/08/2026
METRO FIRE PROTECTION INCFire Protection107/08/2026
ARCO PLBG AND HTG INCPlumbing107/08/2026
BABICH, ETTOREElectrical103/21/2026
TRISTAR PLUMBING & HTG INPlumbing107/08/2026
BARRETT, ORALElectrical103/21/2026
CADOGAN, JOELElectrical103/21/2026
CLIFFORD, NICHOLASElectrical103/21/2026
GAJEWSKI, STANISLAWElectrical103/21/2026
HARVEY ISAACMANElectrical103/21/2026
ISAACMAN, JOELElectrical103/21/2026
JTE ELECTRICAL SERVICESElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMANI INSPECTION SERVICE843511/25/2025
METRIC CONSULTING AND INS18031107/15/2025
THOMAS A. FENNIMAN ARCHIT260601/25/2023
KATZ ENGINEERING238210/07/2022
HOWARD L ZIMMERMAN ARCHIT1712103/15/2022
RICHARD H. BALSER ENGINEE3028105/19/2020
Building Lifecycle
All (106)Filed (34)Permit Issued (37)Signed Off (11)Facade (FISP) (24)
08/03/2026
Filed — Alteration
INSTALLATION AND USE OF SUSPENDED SCAFFOLD FOR FACADE RESTORATION/ INSPECTION AS PER PLANS SUBMITTED
M01440313-I1
07/24/2026
Permit issued — Sidewalk Shed
M00726809-I1-SH
04/24/2026
Permit issued — Sidewalk Shed
M00726809-I1-SH
04/03/2026
Permit issued — General Construction
M00691592-I1-GC
12/17/2025
Signed off — Alteration
MECHANICAL WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00840672-I1
11/25/2025
Filed — Alteration
MECHANICAL WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00840672-P1
10/07/2025
Signed off — Alteration
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00840769-I1
09/30/2025
Signed off — Alteration
INSTALLATION AND USE OF SUSPENDED SCAFFOLD FOR FACADE RESTORATION/INSPECTION AS PER PLANS SUBMITTED
M01122712-I1
07/25/2025
Cycle 9 facade report submitted
07/23/2025
Cycle 9 facade report signed — UNSAFE
07/16/2025
Cycle 9 facade inspection completed
07/15/2025
Filed — Alteration
STRUCTURAL WORK FOR THE PASSENGER ELEVATOR UPGRADE AS PER THE PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. FILED IN CONJUNCTION WITH DOB APPLICATION 123788384.
M00492235-P2
05/12/2025
Filed — Alteration
M01224494-I1
05/01/2025
Permit issued — Sidewalk Shed
M00726809-I1-SH
04/28/2025
Permit issued — General Construction
M00691592-I1-GC
10/09/2024
Permit issued — Suspended Scaffold
M01122712-I1-SC
10/07/2024
Filed — Alteration
INSTALLATION AND USE OF SUSPENDED SCAFFOLD FOR FACADE RESTORATION/INSPECTION AS PER PLANS SUBMITTED
M01122712-I1
08/26/2024
Signed off — Alteration
Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M08037312-I1
06/06/2024
Cycle 9 facade report submitted
06/06/2024
Cycle 9 facade report signed — UNSAFE
05/31/2024
Cycle 9 facade inspection completed
05/14/2024
Signed off — Alteration
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00468463-I1
05/03/2024
Permit issued — Sidewalk Shed
M00726809-I1-SH
04/30/2024
Signed off — Alteration
Installation of temporary supported scaffold as per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00726816-I1
04/26/2024
Permit issued — General Construction
M00691592-I1-GC
03/11/2024
Permit issued — Sprinklers
M00840789-I1-EW-SP
03/08/2024
Permit issued — Mechanical Systems
M00840672-I1-MS
03/07/2024
Permit issued — Plumbing
M00840769-I1-PL
02/05/2024
Permit issued — Sidewalk Shed
M00468463-I1-SH
09/07/2023
Cycle 9 facade report submitted
09/06/2023
Cycle 9 facade report signed — UNSAFE
08/29/2023
Cycle 9 facade inspection completed
08/22/2023
Permit issued — Protection and Mechanical Methods
M08037312-I1-PMM
08/21/2023
Filed — Alteration
Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M08037312-I1
08/17/2023
Permit issued — Supported Scaffold
M00248261-I1-SF
08/07/2023
Permit issued — General Construction
M00840381-I1-GC
07/06/2023
Filed — Alteration
MECHANICAL WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00840672-I1
07/06/2023
Filed — Alteration
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00840769-I1
07/06/2023
Filed — Alteration
SPRINKLER WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00840789-I1
05/15/2023
Permit issued — Supported Scaffold
M00726816-I1-SF
05/11/2023
Filed — Alteration
M00840381-I1
05/05/2023
Permit issued — Sidewalk Shed
M00726809-I1-SH
04/24/2023
Signed off — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-S3
04/24/2023
Signed off — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-S2
04/24/2023
Signed off — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-S1
04/24/2023
Signed off — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-I1
04/24/2023
Permit issued — General Construction
M00691592-I1-GC
01/31/2023
Permit issued — Sidewalk Shed
M00468463-I1-SH
01/25/2023
Filed — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-P2
01/25/2023
Filed — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-P3
01/18/2023
Permit issued — Mechanical Systems
M00705929-S2-MS
12/02/2022
Filed — No Work
M08047986-I1
11/25/2022
Permit issued — Sprinklers
M00705929-S3-EW-SP
11/16/2022
Permit issued — Plumbing
M00705929-S1-PL
10/07/2022
Filed — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-S3
10/07/2022
Filed — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-S2
09/21/2022
Filed — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-P1
09/15/2022
Filed — Alteration
Installation of domestic and sanitary systems and associated piping, equipment, and specialties.
M00705929-S1
09/15/2022
Permit issued — General Construction
M00705929-I1-GC
08/04/2022
Permit issued — Supported Scaffold
M00248261-I1-SF
Latest 60 of 106 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedPRAT ENTERPRISES CORP07/24/2026
DOB NOWSidewalk ShedPermit IssuedPRAT ENTERPRISES CORP04/24/2026
DOB NOWGeneral ConstructionPermit IssuedPRAT ENTERPRISES CORP04/03/2026
DOB NOWSidewalk ShedPermit IssuedPRAT ENTERPRISES CORP05/01/2025
DOB NOWGeneral ConstructionPermit IssuedPRAT ENTERPRISES CORP04/28/2025
DOB NOWSuspended ScaffoldPermit IssuedPRATT CONSTRUCTION & RES10/09/2024
DOB NOWSidewalk ShedPermit IssuedPRAT ENTERPRISES CORP05/03/2024
DOB NOWGeneral ConstructionPermit IssuedPRAT ENTERPRISES CORP04/26/2024
DOB NOWSprinklersPermit IssuedARCO PLBG AND HTG INC03/11/2024
DOB NOWMechanical SystemsSigned-offPRESS BUILDERS INC03/08/2024
DOB NOWPlumbingSigned-offARCO PLBG AND HTG INC03/07/2024
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC02/05/2024
DOB NOWProtection and Mechanical MethodsSigned-offPRAT ENTERPRISES CORP08/22/2023
DOB NOWSupported ScaffoldPermit IssuedMC SUPERSTRUCTURE INC08/17/2023
DOB NOWGeneral ConstructionPermit IssuedPRESS BUILDERS INC08/07/2023
DOB NOWSupported ScaffoldSigned-offPRAT ENTERPRISES CORP05/15/2023
DOB NOWSidewalk ShedPermit IssuedPRAT ENTERPRISES CORP05/05/2023
DOB NOWGeneral ConstructionPermit IssuedPRAT ENTERPRISES CORP04/24/2023
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC01/31/2023
DOB NOWMechanical SystemsSigned-offVERA FORMA LLC01/18/2023
DOB NOWSprinklersSigned-offMETRO FIRE PROTECTION INC11/25/2022
DOB NOWPlumbingSigned-offTRISTAR PLUMBING & HTG IN11/16/2022
DOB NOWGeneral ConstructionSigned-offVERA FORMA LLC09/15/2022
DOB NOWSupported ScaffoldPermit IssuedTRI BOROUGH SCAFFOLDING08/04/2022
DOB NOWGeneral ConstructionPermit IssuedARCH MW LLC08/04/2022
DOB NOWSupported ScaffoldSigned-offPRAT ENTERPRISES CORP05/05/2022
DOB NOWSidewalk ShedPermit IssuedPRAT ENTERPRISES CORP05/05/2022
DOB NOWGeneral ConstructionPermit IssuedPRAT ENTERPRISES CORP04/21/2022
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC02/10/2022
DOB NOWGeneral ConstructionPermit IssuedARCH MW LLC01/24/2022
DOB NOWMechanical SystemsPermit IssuedSTEPPING STONE CONSTRUCT*09/15/2021
DOB NOWMechanical SystemsPermit IssuedSTEPPING STONE CONSTRUCT*09/15/2021
DOB NOWStructuralPermit IssuedSTEPPING STONE CONSTRUCT*09/15/2021
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC02/23/2021
DOB NOWSupported ScaffoldPermit IssuedTRI BOROUGH SCAFFOLDING10/27/2020
DOB NOWSprinklersSigned-offENOBRAC PLUMBING, INC06/04/2020
DOB NOWSupported ScaffoldPermit IssuedTRI BOROUGH SCAFFOLDING11/07/2019
BISOTISSUEDPRESS BUILDERS INC10/30/2023
BISOTISSUEDSTEPPING STONE CONSTRUCT*07/13/2021
BISOTISSUEDSTEPPING STONE CONSTRUCT*07/13/2021
+ 47 more permits on file
2 projects · most recent 04/21/2021
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
04/21/2021Permit IssuedSTEPPING STONE CONSTRUCT*Air Conditioning Systems
Cooling
Lg ARNU243SKA4 / ARUN024GSS4 24,200 BTU · Vrf Indoor ×2
03/15/2021Permit IssuedSTEPPING STONE CONSTRUCT*Air Conditioning Systems
Cooling
Lg ARNU243SKA4 / ARUN024GSS4 24,200 BTU · Vrf Indoor ×2
2 projects · most recent 07/06/2023
FiledStatusContractorScope
07/06/2023Permit IssuedARCO PLBG AND HTG INC122 heads
03/15/2021——4 heads
1 project · most recent 07/06/2023
FiledStatusContractorScope
07/06/2023———
7 projects · most recent 03/22/2026
General Wiring
FiledStatusContractorScope
03/22/2026Permit IssuedAURORA ELECL CONTG INC—
01/23/2026Permit IssuedTITAN ELEC'L & ELEV CONTR—
05/17/2024Permit IssuedNET POWER ELECTRIC CORPGeneral Wiring
04/03/2023CompleteJTE ELECTRICAL SERVICESGeneral Wiring
04/02/2023Permit IssuedSTEVEN FARKAS—
03/04/2021CompleteBOROWIDE ELECT'L CONTR'S—
04/30/2019Permit IssuedNEE ELECTRICAL, LLCGeneral Wiring
2 projects · most recent 07/15/2025
Steel Concrete
FiledStatusContractorScope
07/15/2025——Steel, Concrete
04/13/2021Permit IssuedSTEPPING STONE CONSTRUCT*Steel
1 project · most recent 04/29/2022
Sidewalk Shed
FiledStatusContractorScope
04/29/2022Permit IssuedPRAT ENTERPRISES CORPSidewalk Shed
1 project · most recent 08/03/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
08/03/2026——Suspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
09/16/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/12/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/12/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/12/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/14/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/15/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/14/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/03/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/28/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 66
DateRequirementInspectorRole
11/26/2025FinalJOHN MCMONAGLEprogress
11/26/2025Mechanical SystemsJOHN MCMONAGLEspecial
11/26/2025Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
10/06/2025Tenant Protection Plan Compliance—special
10/06/2025FinalJOHN MCMONAGLEprogress
10/06/2025Mechanical SystemsJOHN MCMONAGLEspecial
07/15/2025Structural Steel - WeldingSAMI HAJJAR P.Especial
07/15/2025Structural Steel - DetailsSAMI HAJJAR P.Especial
07/15/2025FinalSAMI HAJJAR P.Eprogress
07/15/2025Structural Stability – Alterations of existing buildingsSAMI HAJJAR P.Especial
07/10/2025Structural Steel - WeldingSAMI HAJJAR P.Especial
07/10/2025Structural Steel - DetailsSAMI HAJJAR P.Especial
07/10/2025Structural Stability – Alterations of existing buildingsSAMI HAJJAR P.Especial
07/10/2025FinalSAMI HAJJAR P.Eprogress
03/15/2023Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
03/15/2023Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
03/08/2023Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
03/08/2023Post-installed AnchorsJOHN MCMONAGLEspecial
03/08/2023Sprinkler SystemsJOHN MCMONAGLEspecial
03/08/2023Post-installed AnchorsJOHN MCMONAGLEspecial
03/08/2023Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
02/02/2023FinalThomas Fennimanprogress
02/02/2023Fire-Resistant Penetrations and JointsThomas Fennimanspecial
02/02/2023Fire-Resistant Penetrations and JointsThomas Fennimanspecial
01/19/2023FinalThomas Fennimanprogress
Latest 25 of 66.
▾Documents — 720 on file (BIS + DOB NOW)
▸Plans & Drawings34
▸DOB NOWPlans/Sketch25
09/03/2026M00492235-P1Request digital key ↗
09/03/2026M00492235-I1Request digital key ↗
09/03/2026M00492235-P2Request digital key ↗
Showing 3 of 25 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/04/2026M00272706-I1Request digital key ↗
09/03/2026M00272684-I1Request digital key ↗
08/15/2026M00272684-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler3
09/04/2026M00334815-I1Request digital key ↗
09/04/2026M00272743-I1Request digital key ↗
09/04/2026M00272732-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
09/01/2026M08047986-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/05/2026M00248261-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00468463-I1Request digital key ↗
▸Applications & Permits133
▸BISPLAN / WORK APPROVAL APPLICATION67
04/02/2024122489823Open ↗
01/30/2024123788892Open ↗
11/13/2023123788892Open ↗
Showing 3 of 67 on file for this type
▸BISWORK PERMIT APPLICATION30
10/31/2023140107337Open ↗
01/15/2021123788384Open ↗
01/15/2021123788892Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWLPC Approval/Permit21
09/03/2026M00492235-I1Open ↗
09/03/2026M00492235-P1Open ↗
09/02/2026M00705929-P3Open ↗
Showing 3 of 21 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION9
12/23/2020123788892Open ↗
12/23/2020123788892Open ↗
12/23/2020123788892Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
11/14/2023123788892Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWHPD - Permit Notice2
09/02/2026M00705929-I1Open ↗
08/15/2026M00705929-S3Open ↗
▸BISApplication Withdrawal/Address Change Form OP-1131
02/11/2019140423851Open ↗
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications151
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION39
12/21/2020123788384Open ↗
12/21/2020123788892Open ↗
10/23/2019123788892Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature31
09/05/2026M00248261-I1Open ↗
09/04/2026M00468463-I1Open ↗
09/03/2026M00492235-I1Open ↗
Showing 3 of 31 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature29
09/28/2026M00705929-S3Open ↗
09/23/2026M00492288-I1Open ↗
09/23/2026M00492288-I1Open ↗
Showing 3 of 29 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT15
10/23/2019123788892Open ↗
10/22/2019123788384Open ↗
Showing 2 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/23/2026M00492288-I1Open ↗
09/02/2026M00272706-I1Open ↗
09/02/2026M00272706-I1Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST12
10/23/2019123788892Open ↗
10/22/2019123788384Open ↗
Showing 2 of 12 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment26
▸BISEQUIPMENT USE PERMITS10
05/18/2023101806119Open ↗
05/18/2023101806119Open ↗
05/15/2023101806119Open ↗
Showing 3 of 10 on file for this type
▸BISSCHEDULE B - PLUMBING4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
05/18/2023101806119Open ↗
10/18/2021122260383Open ↗
10/18/2021122260383Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection17
▸BISTenant Protection Plan and Notes9
10/23/2019123788892Open ↗
10/22/2019123788384Open ↗
12/03/2018123595653Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWTenant Protection Plan7
08/13/2026M00272684-I1Open ↗
08/13/2026M00272684-P1Open ↗
08/13/2026M00248261-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTENANT PROTECTION PLAN 2008 CODE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos43
▸DOB NOWDEP ACP-5: Asbestos Assessment Report20
09/02/2026M00705929-P2Open ↗
09/02/2026M00705929-P3Open ↗
09/02/2026M00705929-S2Open ↗
Showing 3 of 20 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)16
12/21/2020123788384Open ↗
12/21/2020123788892Open ↗
12/04/2018123595653Open ↗
Showing 3 of 16 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026M00492235-I1Open ↗
▸Energy Compliance39
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS17
12/21/2020123788384Open ↗
12/21/2020123788892Open ↗
10/23/2019123788892Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY7
11/05/2021123595653Open ↗
09/20/2021123595653Open ↗
Showing 2 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
09/20/2021123595653Open ↗
Showing 1 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS2
07/06/2022140107337Open ↗
06/28/2022123595653Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISINTERIOR LIGHTING POWER1
07/06/2022140107337Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/05/2021123595653Open ↗
▸Inspections & Test Reports32
▸BISTECHNICAL REPORT: RESPONSIBILITY28
05/09/2023122957327Open ↗
05/08/2023122957327Open ↗
05/04/2023101806119Open ↗
Showing 3 of 28 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
06/28/2022123595653Open ↗
09/28/2021122260383Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
05/10/2023101806119Open ↗
▸BISDOB FINAL INSPECTION REQUIRED1
11/28/2023140107337Open ↗
▸Approvals, Objections & Sign-offs75
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST30
11/29/2023140107337Open ↗
06/06/2023122957327Open ↗
05/16/2023101806119Open ↗
Showing 3 of 30 on file for this type
▸BISLANDMARKS APPROVAL20
07/13/2022102543197Open ↗
12/21/2020123788384Open ↗
12/21/2020123788892Open ↗
Showing 3 of 20 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION8
04/19/2023140107337Open ↗
Showing 1 of 8 on file for this type
▸BISLANDMARKS SIGNOFF6
03/31/2023122957327Open ↗
09/28/2021122260383Open ↗
09/20/2021123595653Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISFINAL3
05/15/2023122957327Open ↗
06/28/2022123595653Open ↗
10/08/2021122260383Open ↗
▸BISSUPERSEDING LETTER1
10/31/2023140107337Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
05/10/2022102543197Open ↗
▸Cost, Insurance & Ownership38
▸BISCOST AFFIDAVIT29
10/23/2019123788892Open ↗
10/22/2019123788384Open ↗
12/03/2018123595653Open ↗
Showing 3 of 29 on file for this type
▸BISOK TO ISSUE TCO PENDING RESOLUTION OFOPEN FACADE VIOLATION - AFFIDAVIT ATTACHED4
09/03/2025102543197Open ↗
05/22/2025102543197Open ↗
11/26/2024102543197Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
04/11/2023122957327Open ↗
10/08/2021122260383Open ↗
09/20/2021123595653Open ↗
Showing 3 of 4 on file for this type
▸BISOK TO ISSUE TCO PENDING RESOLUTINO OFOPEN FACADE VIOLATION - AFFIDAVIT ATTACHED1
01/23/2026102543197Open ↗
▸Filing & Intake Forms67
▸BISBOROUGH INTAKE FORM26
10/31/2023140107337Open ↗
10/25/2023140107337Open ↗
10/17/2023140107337Open ↗
Showing 3 of 26 on file for this type
▸BISEFILING COVER SHEET19
12/21/2020123788892Open ↗
10/23/2019123788892Open ↗
10/22/2019123788384Open ↗
Showing 3 of 19 on file for this type
▸BISADDITIONAL INFORMATION14
01/30/2024123788892Open ↗
06/06/2023122957327Open ↗
05/16/2023122957327Open ↗
Showing 3 of 14 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸Other Documents63
▸DOB NOWLoft Board Certificate30
09/04/2026M00468463-I1Open ↗
09/03/2026M00492235-I1Open ↗
09/03/2026M00492235-P1Open ↗
Showing 3 of 30 on file for this type
▸BISLOFT BOARD CERTIFICATE16
12/21/2020123788384Open ↗
12/21/2020123788892Open ↗
12/14/2018123595653Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProof of Historic Building5
09/02/2026M00705929-P2Open ↗
09/02/2026M00705929-I1Open ↗
08/15/2026M00705929-P1Open ↗
Showing 3 of 5 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
04/02/2024122489823Open ↗
12/23/2020123788892Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWManufacturer's Specifications3
08/14/2026M01440313-I1Open ↗
08/13/2026M01122712-I1Open ↗
08/13/2026M01224494-I1Open ↗
▸DOB NOWCalculations3
08/14/2026M01440313-I1Open ↗
08/13/2026M01122712-I1Open ↗
Showing 2 of 3 on file for this type
▸BIS* VENT. SYS.-ENGINEER/INSTALLER 27-136,7791
05/10/2023101806119Open ↗
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.