← Back
Two stories - detached, small or mid-size
65-40 53 DRIVE
QUEENS · BIN 4054900
💬 Discuss this project
1930Year Built
2Stories
A1Building Class
R4-1Zoning
1,200 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,600 sf lot · 0.46 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR105/24/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281105/24/2024
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
05/30/2024
Permit issued — Solar
Q01054956-I1-SL
05/24/2024
Filed — Alteration
Q01054956-I1
05/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
05/21/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
05/21/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
05/21/2024
Special inspection requirement — Final
Mina Makar
05/21/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR05/30/2024
1 project · most recent 05/21/2024
FiledStatusContractorScope
05/21/2024CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/21/2024Fire-Resistant Penetrations and JointsMina Makarspecial
05/21/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
05/21/2024Energy Code Compliance InspectionsMina Makarprogress
05/21/2024FinalMina Makarprogress
05/21/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026Q01054956-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
09/16/2026Q01054956-I1Open ↗
09/16/2026Q01054956-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01054956-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/16/2026Q01054956-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01054956-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01054956-I1Open ↗