| Owner | Filings | Most Recent |
|---|---|---|
| 1483 Dekalb | 9 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/06/2022 | $1.1M | — | Private party → 1483 Dekalb | $502/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CL Engineering | 3 | 12/05/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| H J Building Consulting | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Intelogic Electric | Electrical | 1 | 03/22/2026 |
| Splen Construction | General Contractor | 1 | 07/08/2026 |
| American Standard P&H Cororp | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL Engineering | 6781 | 3 | 12/05/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | American Standard P&H Cororp | 11/09/2022 |
| DOB NOW | General Construction | Signed-off | Splen Construction | 11/04/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/06/2023 | Complete | Intelogic Electric | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/13/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/02/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/01/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/12/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/12/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/12/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/05/2022 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 12/05/2022 | Energy Code Compliance Inspections | CHRISTIAN LOZADA | progress |
| 12/05/2022 | HVAC-R and service water piping design and insulation | CHRISTIAN LOZADA | energy_progress |
| 12/05/2022 | Permanent certificate | CHRISTIAN LOZADA | energy_progress |
| 12/05/2022 | HVAC-R and service water heating equipment | CHRISTIAN LOZADA | energy_progress |
| 12/05/2022 | Maintenance information | CHRISTIAN LOZADA | energy_progress |
| 12/05/2022 | HVAC-R and service water heating system controls | CHRISTIAN LOZADA | energy_progress |
| 11/02/2022 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 11/02/2022 | Maintenance information | CHRISTIAN LOZADA | energy_progress |
| 11/02/2022 | Energy Code Compliance Inspections | CHRISTIAN LOZADA | progress |
| 11/02/2022 | Fire-Resistance Rated Construction | CHRISTIAN LOZADA | progress |
| 11/02/2022 | Interior lighting power | CHRISTIAN LOZADA | energy_progress |
| 11/02/2022 | Lighting in dwelling units | CHRISTIAN LOZADA | energy_progress |
| 11/02/2022 | Lighting controls | CHRISTIAN LOZADA | energy_progress |
| 11/02/2022 | Permanent certificate | CHRISTIAN LOZADA | energy_progress |