← Back
Office only, 7-19 stories
65 COURT STREET
BROOKLYN · Brooklyn Heights · BIN 3002557
💬 Discuss this project
1963Year Built
18Stories
O3Building Class
C5-2AZoning
308,053 sfGross Floor Area
1Units
LL97 Covered48 Open Violations 45 unresolved · 3 paperwork only ▸FISP: UNSAFEFDNY Report ↗
Office only, 7-19 stories · Owner of record: NYC DEPARTMENT OF EDUCATION · 17,769 sf lot · 17.34 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentCivilGeneralOther
Permit Issued — active, not yet Signed-off
Floor 1331p · 2 filings · 20 docs
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Site & exteriorUnder Construction27p · 3 filings · 20 docs
Filed — no permit issued22p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION AUTHORITY3507/08/2026
NY SCHOOL CONSTRUCTION AUTHORITY1803/21/2026
NYC SCHOOL CONSTRUCT AUTHORITY1403/21/2026
NEW YORK CITY PUBLIC SCHOOL709/15/2026
N Y C SCHOOL CONSTR AUTH203/21/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
EME CONSULTING ENGINEERING GROUP502/18/2025
NYMS CONSULTING, LLC509/02/2024
BRAND ACCESS SOLUTIONS210/27/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A1 EXPEDITING SERVICE403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MARIC PLUMBING & HEATINGGeneral Contractor2106/28/2026
FRANCIS RICHARDSElectrical1003/21/2026
SAFWAY ATLANTIC, LLCGeneral Contractor707/08/2026
GRIDSPAN CORPORATIONGeneral Contractor504/09/2026
CHARAN ELEC'L ENTERP'S INElectrical203/22/2026
STANCO SYSTEM ELEC'L CONTElectrical103/22/2026
GEMINI ELECTRIC CO., INC.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JPC LOGISTICS DBA JPCL EN351502/18/2025
TWIN PEAKS INC.317410/27/2023
Building Lifecycle
All (155)Filed (13)Permit Issued (25)Facade (FISP) (15)Violation (60)Inspection (6)Objection (6)Special Inspection (30)
09/03/2026
Permit issued — Suspended Scaffold
B01445211-I1-SC
08/19/2026
Filed — Alteration
MATERIAL HOIST. FOR MATERIAL ONLY. NO WORK FROM HOIST.
B01445211-I1
07/02/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
06/25/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
06/22/2026
Permit issued — Construction Fence
B00939762-I1-FN
06/22/2026
Permit issued — Mechanical Systems
B00939762-S2-MS
11/21/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/07/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/02/2025
Permit issued — Supported Scaffold
B00953369-I1-SF
09/25/2025
Permit issued — Sidewalk Shed
B00953358-I1-SH
07/23/2025
Permit issued — Construction Fence
B00939762-I1-FN
07/23/2025
Permit issued — Mechanical Systems
B00939762-S2-MS
06/16/2025
Permit issued — Mechanical Systems
B00939762-S2-MS
06/16/2025
Permit issued — Construction Fence
B00939762-I1-FN
05/28/2025
Permit issued — Construction Fence
B00939762-I1-FN
05/28/2025
Permit issued — Mechanical Systems
B00939762-S2-MS
03/18/2025
Violation issued (ECB, closed)
Boilers
03/10/2025
Permit issued — General Construction
B01143895-I1-GC
03/10/2025
Permit issued — Mechanical Systems
B01143895-S1-MS
03/07/2025
Permit issued — Construction Fence
B00939762-I1-FN
03/06/2025
Permit issued — Mechanical Systems
B00939762-S2-MS
02/18/2025
Filed — Alteration
Remove all existing ductwork associated with 13th floor old data center non-functioning AHU, the old data center is now converted to new office space. Install 6 new indoor units for the new office space and 1 outdoor on 14th floor low roof.
B01143895-S1
02/18/2025
Special inspection requirement — HVAC-R and service water heating equipment
Asma Hashmi
02/18/2025
Special inspection requirement — HVAC-R and service water heating system controls
Asma Hashmi
02/18/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Asma Hashmi
02/18/2025
Special inspection requirement — Maintenance information
Asma Hashmi
02/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Asma Hashmi
02/13/2025
Special inspection requirement — Post-installed Anchors
Asma Hashmi
02/13/2025
Special inspection requirement — Energy Code Compliance Inspections
Asma Hashmi
02/10/2025
Filed — Alteration
Remove all existing ductwork associated with 13th floor old data center non-functioning AHU, the old data center is now converted to new office space. Install 6 new indoor units for the new office space and 1 outdoor on 14th floor low roof.
B01143895-I1
11/18/2024
Special inspection requirement — Mechanical Systems
Asma Hashmi
11/18/2024
Special inspection requirement — Final
Asma Hashmi
10/08/2024
Permit issued — Construction Fence
B00939762-I1-FN
10/07/2024
Permit issued — Mechanical Systems
B00939762-S2-MS
09/30/2024
Permit issued — Sidewalk Shed
B00953358-I1-SH
09/30/2024
Permit issued — Supported Scaffold
B00953369-I1-SF
09/02/2024
Filed — Alteration
K801, INSTALLATION OF +/- 278 LF OF TEMPORARY FENCE TO ENCLOSE THE TEMPORARY EMERGENCY MOBILE BOILER. ENCLOSURE AND STAGING AREA IN CONJUNCTION WITH RED DOT PROJECT UNDER LLW # 135901 ON BEHALF OF CONTRACTOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
B00939762-P2
06/03/2024
Violation issued (ECB, closed)
Construction
02/08/2024
Violation issued (FDNY_NOV, closed)
01/19/2024
Violation issued (FDNY_NOV, closed)
12/19/2023
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
11/16/2023
Permit issued — Sidewalk Shed
B00953358-I1-SH
11/15/2023
Permit issued — Supported Scaffold
B00953369-I1-SF
11/08/2023
Objection resolved — Addressed
11/08/2023
Objection resolved — Addressed
11/02/2023
Objection raised — Other
11/02/2023
Objection raised — Other
10/27/2023
Filed — Alteration
LLW# 135901: TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00953369-I1
10/27/2023
Filed — Alteration
LLW# 135901: HEAVY DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00953358-I1
10/25/2023
Permit issued — Boiler Equipment
B00939762-S1-BE
10/25/2023
Special inspection requirement — Post-installed Anchors
MIKHAIL ZEYGMAN
10/24/2023
Special inspection requirement — Fuel-Oil Storage and Fuel-Oil Piping Systems
MIKHAIL ZEYGMAN
10/23/2023
Filed — Alteration
K801, INSTALLATION OF +/- 278 LF OF TEMPORARY FENCE TO ENCLOSE THE TEMPORARY EMERGENCY MOBILE BOILER. ENCLOSURE AND STAGING AREA IN CONJUNCTION WITH RED DOT PROJECT UNDER LLW # 135901 ON BEHALF OF CONTRACTOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
B00939762-P1
10/23/2023
Permit issued — Mechanical Systems
B00939762-S2-MS
10/23/2023
Permit issued — Construction Fence
B00939762-I1-FN
10/23/2023
Special inspection requirement — Fuel-Oil Storage and Fuel-Oil Piping Systems
MIKHAIL ZEYGMAN
10/19/2023
Violation issued (ECB, closed)
Construction
10/12/2023
Violation issued (FDNY_NOV, closed)
10/10/2023
Filed — Alteration
K801, INSTALLATION OF +/- 278 LF OF TEMPORARY FENCE TO ENCLOSE THE TEMPORARY EMERGENCY MOBILE BOILER. ENCLOSURE AND STAGING AREA IN CONJUNCTION WITH RED DOT PROJECT UNDER LLW # 135901 ON BEHALF OF CONTRACTOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
B00939762-S2
Latest 60 of 155 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedROSENWACH TANK CO.,LLC09/03/2026
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING06/22/2026
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING06/22/2026
DOB NOWSupported ScaffoldPermit IssuedSAFWAY ATLANTIC, LLC10/02/2025
DOB NOWSidewalk ShedPermit IssuedSAFWAY ATLANTIC, LLC09/25/2025
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING07/23/2025
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING07/23/2025
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING06/16/2025
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING06/16/2025
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING05/28/2025
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING05/28/2025
DOB NOWGeneral ConstructionPermit IssuedGRIDSPAN CORPORATION03/10/2025
DOB NOWMechanical SystemsPermit IssuedGRIDSPAN CORPORATION03/10/2025
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING03/07/2025
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING03/06/2025
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING10/08/2024
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING10/07/2024
DOB NOWSidewalk ShedPermit IssuedSAFWAY ATLANTIC, LLC09/30/2024
DOB NOWSupported ScaffoldPermit IssuedSAFWAY ATLANTIC, LLC09/30/2024
DOB NOWSidewalk ShedPermit IssuedSAFWAY ATLANTIC, LLC11/16/2023
DOB NOWSupported ScaffoldPermit IssuedSAFWAY ATLANTIC, LLC11/15/2023
DOB NOWBoiler EquipmentSigned-offMARIC PLBG & HTG INC10/25/2023
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING10/23/2023
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING10/23/2023
DOB NOWGeneral ConstructionPermit IssuedGRIDSPAN CORPORATION06/07/2022
BISPLISSUEDVARSITY PLBG AND HTG INC06/12/2025
BISPLISSUEDVARSITY PLBG AND HTG INC06/17/2024
BISPLISSUEDVARSITY PLBG AND HTG INC01/25/2023
BISMHISSUEDU & I MECHANICAL CORP07/08/2022
BISOTISSUEDNATIONAL ENVIROMENTAL SAFETY02/15/2022
BISPLISSUEDVARSITY PLBG AND HTG INC02/01/2022
BISMHISSUEDU & I MECHANICAL CORP07/14/2021
BISMHISSUEDU & I MECHANICAL CORP02/23/2021
BISPLISSUEDVARSITY PLBG AND HTG INC02/03/2021
BISOTISSUEDWHITESTONE CONSTRUCTION CORP04/07/2020
BISPLISSUEDVARSITY PLBG AND HTG INC02/05/2020
BISMHISSUEDU & I MECHANICAL CORP09/20/2019
BISOTISSUEDNATIONAL ENVIROMENTAL SAFETY05/10/2019
BISOTISSUEDWHITESTONE CONSTRUCTION CORP04/01/2019
BISOTISSUEDWHITESTONE CONSTRUCTION CORP02/26/2019
+ 33 more permits on file
3 projects · most recent 02/18/2025
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
02/18/2025Permit IssuedGRIDSPAN CORPORATIONAir Conditioning Systems
Cooling
Fujitsu AUUA24TLAV2 24,000 BTU · Fan Coil Indoor ×6
AOU120RLAVL 12,000 BTU · Condensing Unit ×1
05/09/2022Permit IssuedGRIDSPAN CORPORATIONAir Conditioning Systems
Cooling
Mitsubishi Electric PKA-A36KA7 1,000 CFM · Fan Coil Indoor ×2
PUY-A36NKA7 36,000 BTU · Condensing Unit ×2
03/08/2022——Air Conditioning Systems
Cooling
Mitsubishi Electric PKA-A36KA7 1,000 CFM · Fan Coil Indoor ×2
PUY-A36NKA7 36,000 BTU · Condensing Unit ×2
13 projects · most recent 11/15/2023
General Wiring
FiledStatusContractorScope
11/15/2023Permit IssuedCORPORATE ELEC. GROUP INC—
10/13/2023Permit IssuedSTANCO SYSTEM ELEC'L CONT—
02/21/2023CompleteGEMINI ELECTRIC CO., INC.—
12/05/2022CompleteGEMINI ELECTRIC CO., INC.—
07/05/2022CompleteCHARAN ELEC'L ENTERP'S INGeneral Wiring
05/13/2022CompleteCHARAN ELEC'L ENTERP'S IN—
10/04/2021CompleteCHARAN ELEC'L ENTERP'S IN—
10/14/2020CompleteSAMCO ELECTRIC CORP.General Wiring
09/11/2019CompleteCHARAN ELEC'L ENTERP'S IN—
05/09/2019Permit IssuedA & S ELECTRIC INC.General Wiring
02/19/2019CompleteSAMCO ELECTRIC CORP.—
01/11/2019Permit IssuedA & S ELECTRIC INC.General Wiring
01/25/2018CompleteCENTENNIAL ELEVATOR INDUS—
3 projects · most recent 09/02/2024
Fence Scaffold Sidewalk Shed
FiledStatusContractorScope
09/02/2024Permit IssuedMARIC PLUMBING & HEATINGFence
10/27/2023Permit IssuedSAFWAY ATLANTIC, LLCScaffold
10/27/2023Permit IssuedSAFWAY ATLANTIC, LLCSidewalk Shed
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
07/02/2026Pass-Final PL - UndergroundPassView ↗
06/25/2026Pass-Final PL - UndergroundPassView ↗
11/21/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/07/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/19/2023Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 39
DateRequirementInspectorRole
02/18/2025HVAC-R and service water heating equipmentAsma Hashmienergy_progress
02/18/2025HVAC-R and service water heating system controlsAsma Hashmienergy_progress
02/18/2025HVAC-R and service water piping design and insulationAsma Hashmienergy_progress
02/18/2025Maintenance informationAsma Hashmienergy_progress
02/13/2025Fire-Resistant Penetrations and JointsAsma Hashmispecial
02/13/2025Post-installed AnchorsAsma Hashmispecial
02/13/2025Energy Code Compliance InspectionsAsma Hashmiprogress
11/18/2024Mechanical SystemsAsma Hashmispecial
11/18/2024FinalAsma Hashmiprogress
10/25/2023Post-installed AnchorsMIKHAIL ZEYGMANspecial
10/24/2023Fuel-Oil Storage and Fuel-Oil Piping SystemsMIKHAIL ZEYGMANspecial
10/23/2023Fuel-Oil Storage and Fuel-Oil Piping SystemsMIKHAIL ZEYGMANspecial
10/02/2023HVAC-R and service water piping design and insulationMIKHAIL ZEYGMANenergy_progress
09/26/2023FinalMIKHAIL ZEYGMANprogress
09/26/2023Post-installed AnchorsMIKHAIL ZEYGMANspecial
09/26/2023Mechanical SystemsMIKHAIL ZEYGMANspecial
09/26/2023Chimneys and ventsMIKHAIL ZEYGMANspecial
05/05/2022Fire-Resistant Penetrations and JointsAsma Hashmispecial
05/05/2022Mechanical SystemsAsma Hashmispecial
05/05/2022Post-installed AnchorsAsma Hashmispecial
05/05/2022Energy Code Compliance InspectionsAsma Hashmiprogress
05/05/2022HVAC-R and service water heating equipmentAsma Hashmienergy_progress
05/05/2022Interior lighting powerAsma Hashmienergy_progress
05/05/2022HVAC-R and service water piping design and insulationAsma Hashmienergy_progress
05/05/2022HVAC-R and service water heating system controlsAsma Hashmienergy_progress
Latest 25 of 39.
▾Documents — 116 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/31/2026B00683428-I1Request digital key ↗
08/29/2026B00696014-P1Request digital key ↗
08/29/2026B00696014-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸Seals & Professional Certifications52
▸DOB NOWProgress Inspector Seal & Signature24
09/26/2026B00696014-P1Open ↗
09/26/2026B00696014-P1Open ↗
09/26/2026B00696014-P1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/26/2026B00696014-P1Open ↗
09/26/2026B00696014-P1Open ↗
09/26/2026B00696014-P1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/29/2026B00696014-I1Open ↗
08/29/2026B00696014-P1Open ↗
08/26/2026B00939762-I1Open ↗
Showing 3 of 13 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWNYCSCA - Approved Site Safety Plans4
08/26/2026B00939762-I1Open ↗
08/13/2026B00939762-P2Open ↗
08/13/2026B00953369-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/13/2026B01143895-S1Open ↗
08/13/2026B01143895-I1Open ↗
08/13/2026B00683428-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B00939762-S2Open ↗
▸Approvals, Objections & Sign-offs28
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter13
08/29/2026B00696014-I1Open ↗
08/29/2026B00696014-P1Open ↗
08/26/2026B00939762-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)12
08/26/2026B00939762-S1Open ↗
08/26/2026B00939762-I1Open ↗
08/13/2026B01143895-I1Open ↗
Showing 3 of 12 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION1
01/22/2019302574925Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)1
08/13/2026B00683428-I1Open ↗
▸DOB NOWDEP Variance (V5) letter1
08/29/2026B00696014-I1Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWNYCSCA Wrap-up Insurance2
08/13/2026B00953358-I1Open ↗
08/13/2026B00953369-I1Open ↗
▸Other Documents13
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal9
08/26/2026B00939762-I1Open ↗
08/26/2026B00939762-S1Open ↗
08/13/2026B00696014-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWPro Cert Restriction Exception (LL158/17)2
08/13/2026B01143895-S1Open ↗
08/13/2026B01143895-I1Open ↗
▸DOB NOWCalculations1
08/20/2026B01445211-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/20/2026B01445211-I1Open ↗