| Firm | Filings | Most Recent |
|---|---|---|
| ZPROEKT ARCHITECTURE | 8 | 08/04/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| HM CONSULTING EXPEDITING | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| IP STATE BUILDER INC | General Contractor | 10 | 07/08/2026 |
| VSP MECHANICAL INC | Plumbing | 2 | 07/10/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEEL CORE ENGINEERING PL | 1098 | 7 | 08/04/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | VSP MECHANICAL INC | 07/09/2026 |
| DOB NOW | Structural | Permit Issued | IP STATE BUILDER INC | 03/31/2026 |
| DOB NOW | General Construction | Permit Issued | IP STATE BUILDER INC | 02/10/2026 |
| DOB NOW | Construction Fence | Permit Issued | IP STATE BUILDER INC | 01/22/2026 |
| DOB NOW | Plumbing | Permit Issued | VSP MECHANICAL INC | 06/12/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | IP STATE BUILDER INC | 02/26/2025 |
| DOB NOW | Structural | Permit Issued | IP STATE BUILDER INC | 02/25/2025 |
| DOB NOW | Construction Fence | Permit Issued | IP STATE BUILDER INC | 02/05/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/04/2026 | Permit Issued | IP STATE BUILDER INC | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | VSP MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | AP ELECTL SER & MAIN INC | General Wiring |
| 02/27/2025 | Permit Issued | AP ELECTL SER & MAIN INC | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | VSP MECHANICAL INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | VSP MECHANICAL INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/30/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/01/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/01/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/03/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/16/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/11/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/17/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/23/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/23/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/03/2026 | Final | Alexander Sheyman | progress |
| 08/03/2026 | Structural Stability – Alterations of existing buildings | Alexander Sheyman | special |
| 08/03/2026 | Mechanical Systems | Alexander Sheyman | special |
| 08/03/2026 | Interior lighting power | Alexander Sheyman | energy_progress |
| 08/03/2026 | Heating Systems | Alexander Sheyman | special |
| 08/03/2026 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 08/03/2026 | Concrete - Cast-In-Place | Alexander Sheyman | special |
| 08/03/2026 | Fenestration and door U-factor and product ratings | Alexander Sheyman | energy_progress |
| 08/03/2026 | HVAC-R and service water heating equipment | Alexander Sheyman | energy_progress |
| 08/03/2026 | Air barrier - visual inspection | Alexander Sheyman | energy_progress |
| 08/03/2026 | Ventilation and air distribution system | Alexander Sheyman | energy_progress |
| 08/03/2026 | Air barrier — testing | Alexander Sheyman | energy_progress |
| 08/03/2026 | Electric vehicle service equipment requirements | Alexander Sheyman | energy_progress |
| 08/03/2026 | Maintenance information | Alexander Sheyman | energy_progress |
| 08/03/2026 | Metering | Alexander Sheyman | energy_progress |
| 08/03/2026 | Fenestration air leakage | Alexander Sheyman | energy_progress |
| 08/03/2026 | Insulation placement and R values | Alexander Sheyman | energy_progress |
| 08/03/2026 | Permanent certificate | Alexander Sheyman | energy_progress |
| 08/03/2026 | HVAC-R and service water piping design and insulation | Alexander Sheyman | energy_progress |
| 08/03/2026 | HVAC-R and service water heating system controls | Alexander Sheyman | energy_progress |
| 08/03/2026 | Fenestration areas | Alexander Sheyman | energy_progress |
| 08/03/2026 | Fire-Resistance Rated Construction | Alexander Sheyman | progress |
| 08/03/2026 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 02/25/2026 | Permanent certificate | Alexander Sheyman | energy_progress |
| 02/25/2026 | HVAC-R and service water piping design and insulation | Alexander Sheyman | energy_progress |