Two family brick
650 ALABAMA AVENUE
BROOKLYN · BIN 3804153
💬 Discuss this project
2021Year Built
3Stories
B1Building Class
R6Zoning
—Gross Floor Area
2Units
Two family brick · Owner of record: HP MJM Housing Development Fund Company · 1.33 FAR built · Flood zone X
Locations of Work
StructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 1Pipe scaffold installation11p · 1 filing · 6 docs
Site & exteriorPipe scaffold installation11p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HP MJM Houisng Development F1707/08/2026
NYC Department of Housing Preservation and Development203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KZ Engineering204/06/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Synergy Building Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Apex Building CompanyGeneral Contractor703/21/2026
Reliant Electrical Cont'gElectrical103/21/2026
Apex Building CompanyScaffold107/08/2026
Leema Plumbing & HeatingPlumbing105/28/2020
Rock BuiltGeneral Contractor303/11/2026
Building Lifecycle
12/18/2021
Permit expired, never signed off — Supported Scaffold
The city's record still shows this permit as issued, with no sign-off on its filing
B00441033-I1-SF
04/06/2021
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B00441033-P1
01/15/2021
Permit issued — Supported Scaffold
B00441033-I1-SF
01/14/2021
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B00441033-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedApex Building Company01/15/2021
BIS—ISSUEDRock Built03/11/2026
BISEQISSUEDRock Built11/19/2025
BIS—ISSUEDRock Built11/19/2025
BISMHISSUEDApex Building Company04/08/2021
BIS—ISSUEDApex Building Company04/08/2021
BIS—ISSUEDApex Building Company04/08/2021
BISEQISSUEDApex Building Company04/08/2021
BISMHISSUEDApex Building Company11/27/2020
BISPLISSUEDA & E Plumbing05/28/2020
BISEQISSUEDApex Building Company04/08/2020
BIS—ISSUEDApex Building Company04/08/2020
BIS—ISSUEDApex Building Company04/08/2020
BIS—ISSUEDApex Building Company12/11/2019
BISEQISSUEDApex Building Company12/11/2019
BIS—ISSUEDApex Building Company12/11/2019
BISEQISSUEDApex Building Company12/14/2018
BIS—ISSUEDApex Building Company12/14/2018
BIS—ISSUEDApex Building Company12/14/2018
1 project · most recent 04/06/2021
Scaffold
FiledStatusContractorScope
04/06/2021Permit IssuedApex Building CompanyScaffold
Nothing on file for this building.