Rent Stabilized1 Open Violation ▸FDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionLandscapeCivilGeneralOther
Roof89p · 1 filing · 20 docs
Penthouse86p · 1 filing · 20 docs
Floor 481p · 1 filing · 20 docs
Floor 384p · 1 filing · 20 docs
Floor 283p · 1 filing · 20 docs
Floor 181p · 1 filing · 20 docs
Cellar142p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DIDO PROPERTIES5807/08/2026
BULLS EYE CONTRACTOR903/22/2026
GBI CONTRACTING603/22/2026
HOUSING PRESERVATION DEVELOPME203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/23/2022$1.7M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
INFOCUS DESIGN AND PLANNING PC1609/25/2023
ENTHINK ENGINEERS LLC302/21/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
INFOCUS DESIGN AND PLANNING PC2603/21/2026
XH&RC PLUMBING AND HEATING INC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GBI CONTRACTING, LLCGeneral Contractor1007/08/2026
W.JAKE CONSTRUCTION CORPGeneral Contractor907/08/2026
BULLS EYE CONTRACTOR INCGeneral Contractor303/21/2026
WU CHENElectrical103/21/2026
DYNAMIC PLBNG & SPRKR CORFire Protection107/08/2026
HORBRIDGE PLUMBING & HEATINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION15191409/25/2023
Building Lifecycle
All (104)Filed (19)Permit Issued (15)Signed Off (8)Violation (22)Inspection (10)Special Inspection (30)
11/09/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S3
11/07/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S2
10/19/2023
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
10/16/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/03/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S6
10/02/2023
Special inspection requirement — Post-installed Anchors
Younes Abouyaala
10/02/2023
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
10/02/2023
Special inspection requirement — Sprinkler Systems
Younes Abouyaala
10/02/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/02/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
09/25/2023
Filed — New Building
new installation of plumbing and sprinkler fixtures
B00737250-P9
09/22/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/05/2023
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
09/05/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
09/05/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
09/05/2023
Special inspection requirement — Sprinkler Systems
Younes Abouyaala
09/05/2023
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
09/05/2023
Special inspection requirement — Post-installed Anchors
Younes Abouyaala
08/30/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/29/2023
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
08/29/2023
Special inspection requirement — Fenestration areas
Younes Abouyaala
08/29/2023
Special inspection requirement — Air barrier — testing
Younes Abouyaala
08/29/2023
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
08/29/2023
Special inspection requirement — Lighting in dwelling units
Younes Abouyaala
08/29/2023
Special inspection requirement — Exterior lighting power
Younes Abouyaala
08/29/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
08/29/2023
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
08/29/2023
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
TONY ONYEAGORO
08/29/2023
Special inspection requirement — Concrete - Precast
Younes Abouyaala
08/29/2023
Special inspection requirement — Preliminary
Younes Abouyaala
08/29/2023
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
08/29/2023
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
08/29/2023
Special inspection requirement — Lighting controls
Younes Abouyaala
08/29/2023
Special inspection requirement — Masonry
Younes Abouyaala
08/29/2023
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
08/29/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
08/29/2023
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
08/29/2023
Special inspection requirement — Interior lighting power
Younes Abouyaala
08/29/2023
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
08/23/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S4
08/21/2023
Permit issued — Plumbing
B00737250-S2-EW-SP
08/15/2023
Filed — New Building
new installation of plumbing and sprinkler fixtures
B00737250-P8
08/08/2023
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B08044278-I1
08/07/2023
Permit issued — Mechanical Systems
B00737250-S3-MS
08/04/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S5
06/29/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S1
06/29/2023
Signed off — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S7
06/26/2023
Violation issued (ECB, closed)
Construction
06/26/2023
Violation issued (ECB, closed)
Construction
05/30/2023
Filed — New Building
new installation of plumbing and sprinkler fixtures
B00737250-P7
03/31/2023
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
02/21/2023
Filed — New Building
new installation of plumbing and sprinkler fixtures
B00737250-P6
02/21/2023
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B08044278-P2
02/21/2023
Permit issued — Supported Scaffold
B00737250-S7-SF
02/15/2023
Filed — New Building
new installation of plumbing and sprinkler fixtures
B00737250-S7
02/14/2023
Violation issued (ECB, closed)
Construction
02/14/2023
Violation issued (ECB, closed)
Construction
02/14/2023
Violation issued (ECB, closed)
Construction
02/13/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/31/2023
Filed — New Building
new installation of plumbing and sprinkler fixtures
B00737250-P3
Latest 60 of 104 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCITYWIDE PLBG, HTG &SPRKL08/21/2023
DOB NOWMechanical SystemsSigned-offGBI CONTRACTING, LLC08/07/2023
DOB NOWSupported ScaffoldSigned-offGBI CONTRACTING, LLC02/21/2023
DOB NOWStructuralSigned-offGBI CONTRACTING, LLC12/07/2022
DOB NOWSidewalk ShedSigned-offBULLS EYE CONTRACTOR INC11/29/2022
DOB NOWSprinklersSigned-offHORBRIDGE PLUMBING & HEAT10/25/2022
DOB NOWGeneral ConstructionPermit IssuedGBI CONTRACTING, LLC10/11/2022
DOB NOWFoundationPermit IssuedGBI CONTRACTING, LLC10/08/2022
DOB NOWSupport of ExcavationSigned-offGBI CONTRACTING, LLC10/07/2022
DOB NOWFoundationPermit IssuedW.JAKE CONSTRUCTION CORP10/05/2022
DOB NOWSupport of ExcavationSigned-offW.JAKE CONSTRUCTION CORP10/05/2022
DOB NOWConstruction FenceSigned-offW.JAKE CONSTRUCTION CORP10/04/2022
DOB NOWConstruction FenceSigned-offGBI CONTRACTING, LLC10/04/2022
DOB NOWSupport of ExcavationSigned-offW.JAKE CONSTRUCTION CORP09/15/2022
DOB NOWConstruction FenceSigned-offW.JAKE CONSTRUCTION CORP09/09/2022
BIS—ISSUEDGATEWAY DEMO/CIVIL CORP05/23/2013
BISEQISSUEDGATEWAY DEMO/CIVIL CORP05/23/2013
BIS—ISSUEDGATEWAY DEMO/CIVIL CORP04/29/2013
BISEQISSUEDGATEWAY DEMO/CIVIL CORP04/29/2013
1 project · most recent 09/25/2023
Sprinkler System
FiledStatusContractorScope
09/25/2023Signed-offDYNAMIC PLBNG & SPRKR CORSprinkler System
1 project · most recent 09/25/2023
Storm Water/Sanitary
FiledStatusContractorScope
09/25/2023Signed-offHORBRIDGE PLUMBING & HEATStorm, Water/Sanitary
2 projects · most recent 05/17/2023
General Wiring Lighting
FiledStatusContractorScope
05/17/2023CompleteSAFEWAY CONSTRUCTION, INCGeneral Wiring, Lighting
12/01/2022CompleteRICHARD NEU—
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
10/19/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
10/16/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/22/2023Pass-Final CND-Occupancy InspectionPassView ↗
09/05/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
08/30/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/31/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
02/13/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/06/2023Pass-Final House ConnectionPassView ↗
11/18/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/18/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 124
DateRequirementInspectorRole
10/02/2023Energy Code Compliance InspectionsYounes Abouyaalaprogress
10/02/2023Post-installed AnchorsYounes Abouyaalaspecial
10/02/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
10/02/2023Sprinkler SystemsYounes Abouyaalaspecial
10/02/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
09/05/2023Sprinkler SystemsYounes Abouyaalaspecial
09/05/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
09/05/2023Post-installed AnchorsYounes Abouyaalaspecial
09/05/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
09/05/2023Energy Code Compliance InspectionsYounes Abouyaalaprogress
08/29/2023Concrete - Cast-In-PlaceYounes Abouyaalaspecial
08/29/2023MeteringYounes Abouyaalaenergy_progress
08/29/2023Insulation placement and R valuesYounes Abouyaalaenergy_progress
08/29/2023Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
08/29/2023Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
08/29/2023Fenestration air leakageYounes Abouyaalaenergy_progress
08/29/2023Air barrier — testing Younes Abouyaalaenergy_progress
08/29/2023Exterior lighting powerYounes Abouyaalaenergy_progress
08/29/2023Fenestration areasYounes Abouyaalaenergy_progress
08/29/2023Lighting in dwelling unitsYounes Abouyaalaenergy_progress
08/29/2023Lighting controlsYounes Abouyaalaenergy_progress
08/29/2023Interior lighting powerYounes Abouyaalaenergy_progress
08/29/2023Air barrier - visual inspectionYounes Abouyaalaenergy_progress
08/29/2023Energy Code Compliance InspectionsYounes Abouyaalaprogress
08/29/2023PreliminaryYounes Abouyaalaprogress
Latest 25 of 124.
▾Documents — 188 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch19
08/28/2026B08044278-P1Request digital key ↗
08/28/2026B08044278-I1Request digital key ↗
08/28/2026B08044278-P2Request digital key ↗
Showing 3 of 19 on file for this type
▸Applications & Permits14
▸BISPLAN / WORK APPROVAL APPLICATION7
12/01/2023322116697Open ↗
10/18/2023321986197Open ↗
10/18/2023320463592Open ↗
Showing 3 of 7 on file for this type
▸BISWORK PERMIT APPLICATION4
05/30/2013320732043Open ↗
05/30/2013320732043Open ↗
05/01/2013320732043Open ↗
Showing 3 of 4 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation2
05/19/2023340860642Open ↗
10/11/2022340860642Open ↗
▸BISBPP - Street Opening DOT Permit - BPP - Street Opening1
12/13/2023340860642Open ↗
▸Zoning, Tax Lot & Property Records15
▸DOB NOWZD1: DOB Zoning Diagram5
08/13/2026B00737250-P6Open ↗
08/13/2026B00737250-I1Open ↗
08/13/2026B00737250-P8Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/13/2026B00737250-P6Open ↗
08/13/2026B00737250-P7Open ↗
08/13/2026B00737250-P8Open ↗
Showing 3 of 5 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
12/12/2023322116697Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
12/12/2023322116697Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
12/12/2023322116697Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
12/12/2023322116697Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00737250-I1Open ↗
▸Seals & Professional Certifications63
▸DOB NOWSpecial Inspector Seal & Signature22
09/19/2026B00737250-S2Open ↗
09/19/2026B00737250-S2Open ↗
09/19/2026B00737250-S2Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature19
08/28/2026B08044278-I1Open ↗
08/28/2026B08044278-P2Open ↗
08/28/2026B08044278-P1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWProgress Inspector Seal & Signature18
09/19/2026B00737250-S2Open ↗
09/04/2026B00737250-P3Open ↗
09/01/2026B00737250-P2Open ↗
Showing 3 of 18 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
09/18/2019321986197Open ↗
04/20/2012320463592Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
10/11/2022340860642Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/11/2022340860642Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/13/2026B00737250-I1Open ↗
08/13/2026B00737250-P8Open ↗
08/13/2026B00737250-P2Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection13
▸DOB NOWStreet Tree Checklist5
08/27/2026B00737250-P6Open ↗
08/27/2026B00737250-P7Open ↗
08/27/2026B00737250-P2Open ↗
Showing 3 of 5 on file for this type
▸BISSTREET TREE CHECKLIST2
10/11/2022340860642Open ↗
09/18/2019321986197Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
05/01/2013320732043Open ↗
▸BISBPP: STREET TREES SITE PLAN1
10/11/2022340860642Open ↗
▸BISSTREET TREE SIGNOFF1
12/12/2023340860642Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00737250-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00737250-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00737250-I1Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/01/2013320732043Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
09/18/2019321986197Open ↗
▸BISTECHNICAL REPORT: ENERGY1
04/20/2012320463592Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026B00737250-I1Open ↗
▸Inspections & Test Reports8
▸DOB NOWSOIL REPORT5
08/13/2026B00737250-P2Open ↗
08/13/2026B00737250-P6Open ↗
08/13/2026B00737250-P8Open ↗
Showing 3 of 5 on file for this type
▸BISBPP: SIDEWALK CONCRETE STRENGTH REPORT1
12/13/2023340860642Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026B00737250-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00737250-I1Open ↗
▸Approvals, Objections & Sign-offs10
▸BISLETTERS - SUPPORTING DOCUMENTATION4
05/01/2013320732043Open ↗
05/01/2013320732043Open ↗
05/01/2013320732043Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE2
12/12/2023322116697Open ↗
09/18/2019321986197Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
03/19/2013320732043Open ↗
04/20/2012320463592Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
12/13/2023340860642Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
05/01/2013320732043Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
04/20/2012320463592Open ↗
▸BISBPP-11 - Affidavit as to Roadway Pavement And/Or Sidewalk and Curb Construction1
12/13/2023340860642Open ↗
▸Filing & Intake Forms8
▸BISEFILING COVER SHEET4
12/01/2023322116697Open ↗
09/18/2019321986197Open ↗
03/19/2013320732043Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION2
05/01/2013320732043Open ↗
03/19/2013320732043Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/11/2022340860642Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
10/11/2022340860642Open ↗
▸Other Documents27
▸DOB NOWProperty Ownership Certification8
08/27/2026B00737250-P6Open ↗
08/27/2026B00737250-P7Open ↗
08/27/2026B00737250-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSite Survey: Initial5
08/13/2026B00737250-P8Open ↗
08/13/2026B00737250-P7Open ↗
08/13/2026B00737250-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/13/2026B00737250-P8Open ↗
08/13/2026B00737250-P2Open ↗
08/13/2026B00737250-P7Open ↗
Showing 3 of 5 on file for this type
▸BISPLOT DIAGRAM2
12/12/2023322116697Open ↗
09/18/2019321986197Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
12/12/2023322116697Open ↗
12/12/2023322116697Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION2
12/13/2023340860642Open ↗
10/11/2022340860642Open ↗
▸BISBPP-PARKS: PLANT NEW TREE1
12/13/2023340860642Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00737250-S5Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00737250-I1Open ↗