| Owner | Filings | Most Recent |
|---|---|---|
| PRECISION OWNERS | 16 | 09/01/2026 |
| OWNERS REP | 6 | 04/09/2026 |
| LIBERTY 651 | 20 | 04/09/2026 |
| UPSTRATE | 2 | 03/22/2026 |
| OWNER OF 651 LIBRTY AVE | 2 | 03/22/2026 |
| A & D BAKERY CO | 1 | 03/22/2026 |
| 647 651 LIBERTY | 6 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/20/2015 | $525K | — | — → — | — not available |
| 06/16/2015 | $361K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| VASILIOS ARTEMIOU PE | 7 | 04/21/2026 |
| BMG DESIGN BUILD LLC | 3 | 02/11/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 12/04/2024 |
| ELEVATED ENGINEERING NYC | 1 | 05/02/2024 |
| JOEL PHAGOO P.E. PLLC | 1 | 12/05/2022 |
| P GEORGOPOULOS ARCHITECT PC | 1 | 06/05/2022 |
| SHAHRISH SHUVO ENGINEERING P.C. | 1 | — |
| Representative | Filings | Most Recent |
|---|---|---|
| BMG GROUP USA | 9 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| NYC DESIGN FILE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| B&B MECH PLBG & HTG LLC | Plumbing | 5 | 07/08/2026 |
| BMG ARCHITECT | General Contractor | 3 | 03/22/2026 |
| DYNAMO CONST GROUP LLC | General Contractor | 3 | 03/21/2026 |
| PRECISION BUILD USA INC | General Contractor | 3 | 07/08/2026 |
| TARGET PIPING NY LLC | Fire Protection | 2 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 2 | 04/09/2026 |
| AKM CONSTRUCTION NY CORP | General Contractor | 1 | 04/09/2026 |
| TARGET PIPING NY | General Contractor | 1 | 03/22/2026 |
| UPSTRATE INC | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING CONSULTING SE | 2050 | 8 | 04/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 10/29/2025 |
| DOB NOW | Sprinklers | Signed-off | TARGET PIPING NY LLC | 07/16/2025 |
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 10/16/2024 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 10/07/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 09/16/2024 |
| DOB NOW | Construction Fence | Signed-off | PRECISION BUILD USA INC | 09/16/2024 |
| DOB NOW | Structural | Signed-off | PRECISION BUILD USA INC | 08/05/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PRECISION BUILD USA INC | 07/23/2024 |
| DOB NOW | Sprinklers | Signed-off | TARGET PIPING NY LLC | 07/22/2024 |
| DOB NOW | Construction Fence | Signed-off | DYNAMO CONST GROUP LLC | 12/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | AKM CONSTRUCTION NY | 12/06/2022 |
| BIS | — | ISSUED | UPSTRATE INC | 09/25/2024 |
| BIS | — | RE-ISSUED | PRECISION BUILD USA INC | 08/30/2024 |
| BIS | — | ISSUED | GERALDO WATSON | 02/17/2023 |
| BIS | — | ISSUED | GERALDO WATSON | 01/25/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2025 | Complete | HIVOLTS ELECTRICAL INC | General Wiring |
| 09/19/2024 | Complete | SOLAS ELECTRICAL CORP | — |
| 06/06/2024 | Complete | HIVOLTS ELECTRICAL INC | — |
| 07/22/2022 | Complete | HIGH QUALITY ELECTRIC OF | — |
| 11/19/2019 | Complete | DORION NORTON ELECL CONT | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2022 | — | — | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/13/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 12/13/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/12/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/03/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/30/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/27/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/07/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/17/2026 | HVAC-R and service water piping design and insulation | PAUL MARINO | energy_progress |
| 05/17/2026 | HVAC-R and service water heating system controls | PAUL MARINO | energy_progress |
| 05/17/2026 | HVAC-R and service water heating equipment | PAUL MARINO | energy_progress |
| 05/17/2026 | Shutoff dampers | PAUL MARINO | energy_progress |
| 05/17/2026 | Duct leakage testing, insulation and design | PAUL MARINO | energy_progress |
| 05/17/2026 | Mechanical Systems | PAUL MARINO | special |
| 05/17/2026 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 05/17/2026 | Post-installed Anchors | PAUL MARINO | special |
| 05/17/2026 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 05/17/2026 | Final | JAMES SCHAEFER | progress |
| 05/17/2026 | Maintenance information | PAUL MARINO | energy_progress |
| 04/21/2026 | HVAC-R and service water heating equipment | PAUL MARINO | energy_progress |
| 04/21/2026 | Post-installed Anchors | PAUL MARINO | special |
| 04/21/2026 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 04/21/2026 | Final | JAMES SCHAEFER | progress |
| 04/21/2026 | Shutoff dampers | PAUL MARINO | energy_progress |
| 04/21/2026 | HVAC-R and service water piping design and insulation | PAUL MARINO | energy_progress |
| 04/21/2026 | Duct leakage testing, insulation and design | PAUL MARINO | energy_progress |
| 04/21/2026 | Maintenance information | PAUL MARINO | energy_progress |
| 04/21/2026 | HVAC-R and service water heating system controls | PAUL MARINO | energy_progress |
| 04/21/2026 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 04/21/2026 | Mechanical Systems | PAUL MARINO | special |
| 09/16/2025 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 09/16/2025 | Sprinkler Systems | PAUL MARINO | special |
| 09/16/2025 | Post-installed Anchors | PAUL MARINO | special |