| Owner | Filings | Most Recent |
|---|---|---|
| 131-44 40TH ROAD 2ND FLOO | 1 | 03/22/2026 |
| 654 JEFFERSON | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/23/2023 | $1.4M | — | Private party → 654 JEFFERSON LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| HPL ENGINEERING P.C. | 10 | 10/13/2025 |
| JIAN ENGINEERING PLLC | 2 | 07/31/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| H Z BUILDING NY | 20 | 03/21/2026 |
| SD DESIGN STUDIO | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACER CONSTRUCTION INC | General Contractor | 12 | 07/08/2026 |
| ACCRETE CONSTRUCTION GROUP | General Contractor | 3 | 03/21/2026 |
| PRECISION SPKLR SVCS LLC | Fire Protection | 1 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JIAN ENGINEERING PLLC | 7397 | 8 | 10/13/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | ACCRETE CONSTRUCTION GROU | 11/17/2025 |
| DOB NOW | General Construction | Permit Issued | ACER CONSTRUCTION INC | 03/05/2025 |
| DOB NOW | Sprinklers | Signed-off | PRECISION SPKLR SVCS LLC | 08/20/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ACER CONSTRUCTION INC | 08/01/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ACER CONSTRUCTION INC | 05/30/2024 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 04/30/2024 |
| DOB NOW | Support of Excavation | Signed-off | ACER CONSTRUCTION INC | 03/07/2024 |
| DOB NOW | Foundation | Signed-off | ACER CONSTRUCTION INC | 02/21/2024 |
| DOB NOW | General Construction | Permit Issued | ACER CONSTRUCTION INC | 02/15/2024 |
| DOB NOW | Structural | Signed-off | ACER CONSTRUCTION INC | 02/14/2024 |
| DOB NOW | Construction Fence | Signed-off | ACER CONSTRUCTION INC | 01/09/2024 |
| BIS | OT | ISSUED | MOHAMMED SANAULLAH | 02/01/2018 |
| BIS | PL | ISSUED | PLUMB-IT MECHANICAL INC | 09/21/2017 |
| BIS | OT | ISSUED | MOHAMMED SANAULLAH | 09/06/2017 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/13/2025 | Signed-off | ACCRETE CONSTRUCTION GROU | Heating and Air Conditioning Systems | Heat / Cool Cooper & Hunter CH-HPR36M-230VO 37,000 BTU · Condensing Unit ×6 CH-HPR48M-230VO 49,000 BTU · Condensing Unit ×1 CH-HPR55M-230VO 55,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2025 | Signed-off | INFINITI ESC PLUMBING COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Complete | K.A.B. ELECTRIC CORP | General Wiring |
| 01/22/2026 | Complete | K.A.B. ELECTRIC CORP | General Wiring |
| 06/26/2024 | Complete | ALL AROUND ELECTRIC CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2025 | Signed-off | ACCRETE CONSTRUCTION GROU | Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2025 | Signed-off | ACCRETE CONSTRUCTION GROU | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/08/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/15/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/14/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/11/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/18/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/18/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/11/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/09/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/21/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/21/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/17/2025 | Duct leakage testing, insulation and design | JIAN DENG | energy_progress |
| 09/26/2025 | Shutoff dampers | JIAN DENG | energy_progress |
| 09/26/2025 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 09/26/2025 | Maintenance information | JIAN DENG | energy_progress |
| 09/26/2025 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 09/26/2025 | Final | JIAN DENG | progress |
| 09/26/2025 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 09/26/2025 | Mechanical Systems | JIAN DENG | special |
| 09/26/2025 | Heating Systems | JIAN DENG | special |
| 09/26/2025 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 09/26/2025 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 09/17/2025 | Fenestration and door U-factor and product ratings | JIAN DENG | energy_progress |
| 09/17/2025 | Air barrier — testing | JIAN DENG | energy_progress |
| 09/17/2025 | Exterior lighting power | JIAN DENG | energy_progress |
| 09/17/2025 | Interior lighting power | JIAN DENG | energy_progress |
| 09/17/2025 | Air barrier - visual inspection | JIAN DENG | energy_progress |
| 09/17/2025 | Lighting controls | JIAN DENG | energy_progress |
| 09/17/2025 | Maintenance information | JIAN DENG | energy_progress |
| 09/17/2025 | Metering | JIAN DENG | energy_progress |
| 09/17/2025 | Fenestration air leakage | JIAN DENG | energy_progress |
| 09/17/2025 | Lighting in dwelling units | JIAN DENG | energy_progress |
| 09/17/2025 | Fenestration areas | JIAN DENG | energy_progress |
| 09/17/2025 | Insulation placement and R values | JIAN DENG | energy_progress |
| 09/17/2025 | Electrical motors and elevators | JIAN DENG | energy_progress |
| 09/17/2025 | Concrete - Cast-In-Place | JIAN DENG | special |