← Back
Two stories - detached, small or mid-size
6543 AMBOY ROAD
STATEN ISLAND · Annadale-Huguenot-Prince's Bay-Woodrow · BIN 5087083
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R3XZoning
1,460 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · Owner of record: G&W DEVELOPERS LLC · 11,408 sf lot · 0.13 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Filed — no permit issued15p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GORMAN CARBONE CONTRACTORS403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH M. MORACE, A.I.A., ARCHITECT212/14/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRICIA L GASS403/21/2026
Building Lifecycle
All (32)Filed (2)Objection (2)Special Inspection (28)
01/24/2024
Objection resolved — Addressed
12/14/2023
Filed — New Building
PROPOSED INSTALLATION OF PLUMBING, GAS AND STORMWATER FIXTURES AND ASSOCIATED PIPING FOR A NEW TWO-FAMILY DETACHED RESIDENCE.
S00674540-S1
09/15/2022
Objection raised — Scope
08/16/2022
Filed — New Building
PROPOSED INSTALLATION OF PLUMBING, GAS AND STORMWATER FIXTURES AND ASSOCIATED PIPING FOR A NEW TWO-FAMILY DETACHED RESIDENCE.
S00674540-I1
08/10/2022
Special inspection requirement — HVAC-R and service water heating equipment
08/10/2022
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
08/10/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/10/2022
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
08/10/2022
Special inspection requirement — Subgrade Inspections
08/10/2022
Special inspection requirement — Fenestration air leakage
08/10/2022
Special inspection requirement — HVAC-R and service water heating system controls
08/10/2022
Special inspection requirement — Concrete - Cast-In-Place
08/10/2022
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
08/10/2022
Special inspection requirement — Energy Code Compliance Inspections
08/10/2022
Special inspection requirement — Fire-Resistance Rated Construction
08/10/2022
Special inspection requirement — Structural Wood Frame
08/10/2022
Special inspection requirement — Metering
08/10/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
08/10/2022
Special inspection requirement — Air barrier — testing
08/10/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
08/10/2022
Special inspection requirement — Permanent certificate
08/10/2022
Special inspection requirement — Insulation placement and R values
08/10/2022
Special inspection requirement — Air barrier - visual inspection
08/10/2022
Special inspection requirement — Protection of exposed foundation insulation
08/10/2022
Special inspection requirement — Interior lighting power
08/10/2022
Special inspection requirement — Fenestration areas
08/10/2022
Special inspection requirement — Electric vehicle service equipment requirements
08/10/2022
Special inspection requirement — Ventilation and air distribution system
08/10/2022
Special inspection requirement — Maintenance information
02/04/2022
Special inspection requirement — Mechanical Systems
02/04/2022
Special inspection requirement — Footing and Foundation
02/04/2022
Special inspection requirement — Final
Nothing on file for this building.
1 project · most recent 12/14/2023
Concrete Wood
FiledStatusContractorScope
12/14/2023——Concrete, Wood
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
08/10/2022HVAC-R and service water heating equipment—energy_progress
08/10/2022Exterior Insulation and Finish Systems (EIFS)—special
08/10/2022Fire-Resistant Penetrations and Joints—special
08/10/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
08/10/2022Subgrade Inspections—special
08/10/2022Fenestration air leakage—energy_progress
08/10/2022HVAC-R and service water heating system controls—energy_progress
08/10/2022Concrete - Cast-In-Place—special
08/10/2022Subsurface Investigations (Borings/Test Pits)—special
08/10/2022Energy Code Compliance Inspections—progress
08/10/2022Fire-Resistance Rated Construction—progress
08/10/2022Structural Wood Frame—progress
08/10/2022Metering—energy_progress
08/10/2022HVAC-R and service water piping design and insulation—energy_progress
08/10/2022Air barrier — testing —energy_progress
08/10/2022Fenestration and door U-factor and product ratings—energy_progress
08/10/2022Permanent certificate—energy_progress
08/10/2022Insulation placement and R values—energy_progress
08/10/2022Air barrier - visual inspection—energy_progress
08/10/2022Protection of exposed foundation insulation—energy_progress
08/10/2022Interior lighting power—energy_progress
08/10/2022Fenestration areas—energy_progress
08/10/2022Electric vehicle service equipment requirements—energy_progress
08/10/2022Ventilation and air distribution system—energy_progress
08/10/2022Maintenance information—energy_progress
Latest 25 of 28.
▾Documents — 28 on file (BIS + DOB NOW)
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
05/27/2022540217219Open ↗
06/11/2020520453688Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
12/07/2022540217219Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
06/15/2020520453688Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
05/27/2022540217219Open ↗
▸DOB NOWRestrictive Declaration/Easement 11
08/13/2026S00674540-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S00674540-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00674540-I1Open ↗
▸Seals & Professional Certifications2
▸BISAPPLICANT OWNER SIGNATURE1
05/27/2022540217219Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/27/2022540217219Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026S00674540-I1Open ↗
▸Inspections & Test Reports3
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
05/27/2022540217219Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
05/27/2022540217219Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026S00674540-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
12/07/2022540217219Open ↗
▸BISNYS DEC FRESHWATER WETLANDS APPROVAL1
12/07/2022540217219Open ↗
▸BISLETTER OF PUBLIC DEDICATION1
12/07/2022540217219Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
06/15/2020520453688Open ↗
▸Filing & Intake Forms3
▸BISEFILING JOB APPLICATION COVER SHEET1
05/27/2022540217219Open ↗
▸BISBOROUGH INTAKE FORM1
06/11/2020520453688Open ↗
▸BISEFILING COVER SHEET1
06/11/2020520453688Open ↗
▸Other Documents7
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form1
05/27/2022540217219Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/15/2020520453688Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
12/07/2022540217219Open ↗
▸BISNYS DEC FRESHWATER WETLANDS MAP1
12/07/2022540217219Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
05/27/2022540217219Open ↗
▸BISWAIVER OF CURB AND SIDEWALK ALIGNMENT1
12/07/2022540217219Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026S00674540-I1Open ↗