| Firm | Filings | Most Recent |
|---|---|---|
| ATELIER XIA DONG | 13 | 10/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| FEBRUARY 30TH | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GREENPOINT CONSTRUCTION C | General Contractor | 10 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 2 | 07/08/2026 |
| ATMOS ELECTRIC SVCE CORP | Electrical | 1 | 03/22/2026 |
| XH&RC PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ATELIER XIA DONG ARCHITEC | 8523 | 5 | 10/26/2025 |
| PEBBLE STUDIO DESIGN | 8525 | 3 | 04/20/2025 |
| MW PROFESSIONAL ENGINEERI | 570 | 2 | 12/11/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | GREENPOINT CONSTRUCTION C | 06/03/2025 |
| DOB NOW | General Construction | Permit Issued | GREENPOINT CONSTRUCTION C | 03/06/2025 |
| DOB NOW | Construction Fence | Signed-off | GREENPOINT CONSTRUCTION C | 03/03/2025 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 02/04/2025 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 01/22/2025 |
| DOB NOW | Foundation | Signed-off | GREENPOINT CONSTRUCTION C | 10/15/2024 |
| DOB NOW | Plumbing | Signed-off | XH&RC PLBG AND HTG INC | 10/09/2024 |
| DOB NOW | Earth Work | Signed-off | GREENPOINT CONSTRUCTION C | 09/06/2024 |
| DOB NOW | General Construction | Permit Issued | GREENPOINT CONSTRUCTION C | 08/09/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2025 | Complete | ATMOS ELECTRIC SVCE CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/19/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/26/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/29/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/09/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 05/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/14/2025 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 02/07/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/08/2026 | Interior lighting power | Yao Dong | energy_progress |
| 01/08/2026 | Fenestration and door U-factor and product ratings | Yao Dong | energy_progress |
| 01/08/2026 | Electric vehicle service equipment requirements | Yao Dong | energy_progress |
| 01/08/2026 | Fenestration air leakage | Yao Dong | energy_progress |
| 01/08/2026 | Protection of exposed foundation insulation | Yao Dong | energy_progress |
| 01/08/2026 | Maintenance information | Yao Dong | energy_progress |
| 01/08/2026 | Insulation placement and R values | Yao Dong | energy_progress |
| 01/08/2026 | Metering | Yao Dong | energy_progress |
| 01/08/2026 | Fire-Resistant Penetrations and Joints | Di Xia | special |
| 01/08/2026 | Energy Code Compliance Inspections | Yao Dong | progress |
| 01/08/2026 | Fire-Resistance Rated Construction | Yao Dong | progress |
| 01/08/2026 | Permanent certificate | Yao Dong | energy_progress |
| 01/08/2026 | Air barrier - visual inspection | Yao Dong | energy_progress |
| 01/08/2026 | Fenestration areas | Yao Dong | energy_progress |
| 05/02/2025 | Protection of exposed foundation insulation | Yao Dong | energy_progress |
| 05/02/2025 | Metering | Yao Dong | energy_progress |
| 05/02/2025 | Permanent certificate | Yao Dong | energy_progress |
| 05/02/2025 | Fenestration air leakage | Yao Dong | energy_progress |
| 05/02/2025 | Insulation placement and R values | Yao Dong | energy_progress |
| 05/02/2025 | Fire-Resistance Rated Construction | Yao Dong | progress |
| 05/02/2025 | Energy Code Compliance Inspections | Yao Dong | progress |
| 05/02/2025 | Fire-Resistant Penetrations and Joints | Di Xia | special |
| 05/02/2025 | Electric vehicle service equipment requirements | Yao Dong | energy_progress |
| 05/02/2025 | Maintenance information | Yao Dong | energy_progress |
| 05/02/2025 | Interior lighting power | Yao Dong | energy_progress |